UEAP/PWD/C-83A
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1087 |
Package Name: |
UEAP/PWD/C-83A |
Sanction Cost: |
1639.00 lakhs |
District: |
Nainital |
Block: |
Haldwani |
Constituency: |
Lalkuan |
Circle: |
|
DEA: |
DEA UEAP Nainital |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5912 Ramnagar Kaladungi Haldwani Kathgodam Chorgaliya Sitarganj Bijti MR PHASE 3 (Km. 66 TO 76) (11.000 KM.) (completed) |
|
Procurement: |
Package No.: 1087
Package Name: UEAP/PWD/C-83A
Tender Date: 30-01-2016
Current Status: Agreement signed
Achieved on Date: 29-03-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-83A
Contractor Name: PRL Projects and Infrastructure Ltd.
|
Start Date: 07-04-2016
Intended Completion Date: 06-12-2016
|
Total Bond Cost: 102431100 (1024.31 lakhs)
Variation Cost: 7736929.01 (77.37 lakhs) Hence Total Bond Cost is 110168029.01 (1101.68 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 190.00 m | 3.47 | 70.00 m | 70.00 m | 0.75 | 3.47 | 2. | BM i/c Prime Coat, Tack Coat | 11.90 KM | 12.85 | 11.90 KM | 11.90 KM | 2.79 | 12.85 | 3. | SDBC i/c Tackcoat | 11.90 KM | 228.36 | 11.90 KM | 11.90 KM | 49.57 | 228.36 | 4. | Road Furniture | 11640.00 No | 38.36 | 11640.00 No | 11640.00 No | 8.33 | 38.36 | 5. | Other Allied Works & Finishing Work | 1.00 Job | 177.62 | 1.00 Job | 1.00 Job | 38.56 | 177.62 |
Total Amount: |
460.66 |
|
100 |
460.66 |
|
Remarks:
No Remarks
Work Program Made On:
17-06-2016
Updation of work program on:
25-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-April-2016 | 101.15 lakhs |
2. | 23-May-2016 | 113.61 lakhs |
3. | 02-June-2016 | 139.55 lakhs |
4. | 22-June-2016 | 179.42 lakhs |
5. | 23-July-2016 | 93.53 lakhs |
6. | 28-September-2016 | 74.91 lakhs |
7. | 10-October-2016 | 106.87 lakhs |
8. | 24-October-2016 | 89.13 lakhs |
9. | 26-November-2016 | 56.28 lakhs |
10. | 16-December-2016 | 19.72 lakhs |
11. | 24-March-2017 | 69.98 lakhs |
12. | 22-June-2017 | 23.31 lakhs |
13. | 11-October-2017 | 32.49 lakhs |
Total |
1099.95 lakhs |
% Payment |
99.84 % |
|
Advance Amount: 102.43 lakhs
Recovered Amount: 102.43 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 24 |
Number of Notice(s) issued: 31 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-05-2017 | Chainage 18+750 | Road safety audit inspection by the expert Dr T S Reddy sir | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
2. | 21-12-2016 | Chainage 76+030 | Start point of package C 83B | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
3. | 29-11-2016 | Chainage 73+950 | Inspection of B C work by SE Sir | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
4. | 24-11-2016 | Chainage 65+300 | Thermoplast marking work in progress | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
5. | 08-11-2016 | Chainage 65+550 | Core thickness checking by CE NH Hld | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
6. | 08-11-2016 | Chainage 65+550 | Thickness of core is 190 mm (150mm BM+40mm BC | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
7. | 08-11-2016 | Chainage 65+550 | Core cutting for checking of thickness of BM & B C | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
8. | 08-11-2016 | chainage 65+550 | Checking of themoplast thickness by CE NH Hld Er Aijaj Ahmad | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
9. | 08-11-2016 | chainage 65+550 | Checking of works by CE Ajay Ahmad | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
10. | 08-11-2016 | Chainage 67+850 | Camber checking by C E N H Er Aijaj Ahmad | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
11. | 02-11-2016 | 66+700 | BC laying in progress | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
12. | 02-11-2016 | 66+100 | Core cutting | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
13. | 02-11-2016 | 69+300 | SE sir Almora UEAP giving instruction for cleaning of Road surface before laying tack coat ,DBM layer | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
14. | 02-11-2016 | 69+155 | Laying of DBM in presence of SE sir Almora UEAP circle | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
15. | 02-11-2016 | 68+500 | SE sir Almora visit and thickness checking of DBM | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
16. | 10-10-2016 | 18.950 | BC work | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
17. | 10-10-2016 | 19.925 | BC work | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
18. | 28-09-2016 | Chainage 65+480 | BC laying in progress | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
19. | 15-09-2016 | chainage 22+170 | grade correction at approach of culvert by laying WMM | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
20. | 10-07-2016 | Chainage 23+800 | Plantation in road side near kamala village | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
|
|