Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C-83A Agreement signed
Project: UEAP-RB Package No.: 1087 Package Name: UEAP/PWD/C-83A Sanction Cost: 1639.00  lakhs
District: Nainital Block: Haldwani Constituency: Lalkuan Circle:
DEA: DEA UEAP Nainital DSC: CCEE Group India Pvt.Ltd DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  5912   Ramnagar Kaladungi Haldwani Kathgodam Chorgaliya Sitarganj Bijti MR PHASE 3 (Km. 66 TO 76) (11.000 KM.) (completed)
Procurement:
Package No.: 1087        Package Name: UEAP/PWD/C-83A        Tender Date: 30-01-2016        Current Status: Agreement signed        Achieved on Date: 29-03-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-83A        Contractor Name: PRL Projects and Infrastructure Ltd.       
Start Date: 07-04-2016        Intended Completion Date: 06-12-2016       
Total Bond Cost: 102431100 (1024.31 lakhs)        Variation Cost: 7736929.01 (77.37 lakhs)     Hence Total Bond Cost is   110168029.01 (1101.68 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works190.00 m3.4770.00 m70.00 m0.753.47
2.BM i/c Prime Coat, Tack Coat11.90 KM12.8511.90 KM11.90 KM2.7912.85
3.SDBC i/c Tackcoat11.90 KM228.3611.90 KM11.90 KM49.57228.36
4.Road Furniture11640.00 No38.3611640.00 No11640.00 No8.3338.36
5.Other Allied Works & Finishing Work 1.00 Job177.621.00 Job1.00 Job38.56177.62
Total Amount: 460.66 100   460.66
Remarks: No Remarks       Work Program Made On: 17-06-2016       Updation of work program on: 25-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-April-2016101.15  lakhs
2.23-May-2016113.61  lakhs
3.02-June-2016139.55  lakhs
4.22-June-2016179.42  lakhs
5.23-July-201693.53  lakhs
6.28-September-201674.91  lakhs
7.10-October-2016106.87  lakhs
8.24-October-201689.13  lakhs
9.26-November-201656.28  lakhs
10.16-December-201619.72  lakhs
11.24-March-201769.98  lakhs
12.22-June-201723.31  lakhs
13.11-October-201732.49  lakhs
Total 1099.95  lakhs
% Payment 99.84 %
Advance Amount:  102.43  lakhs        Recovered Amount:  102.43  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1915     No. of Test Done : 1916      No. of Test Passed : 1893      No. of Test Failed : 6   Test report of this package
Number of Pics Available on Web Repository: 24
Number of Notice(s) issued: 31

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-05-2017Chainage 18+750Road safety audit inspection by the expert Dr T S Reddy sirRajiv GururaniEEUEAP R&B Nainital See Pic
2.21-12-2016Chainage 76+030Start point of package C 83BRajiv GururaniEEUEAP R&B Nainital See Pic
3.29-11-2016Chainage 73+950Inspection of B C work by SE SirRajiv GururaniEEUEAP R&B Nainital See Pic
4.24-11-2016Chainage 65+300Thermoplast marking work in progressRajiv GururaniEEUEAP R&B Nainital See Pic
5.08-11-2016Chainage 65+550Core thickness checking by CE NH HldRajiv GururaniEEUEAP R&B Nainital See Pic
6.08-11-2016Chainage 65+550Thickness of core is 190 mm (150mm BM+40mm BCRajiv GururaniEEUEAP R&B Nainital See Pic
7.08-11-2016Chainage 65+550Core cutting for checking of thickness of BM & B CRajiv GururaniEEUEAP R&B Nainital See Pic
8.08-11-2016chainage 65+550Checking of themoplast thickness by CE NH Hld Er Aijaj AhmadRajiv GururaniEEUEAP R&B Nainital See Pic
9.08-11-2016chainage 65+550Checking of works by CE Ajay AhmadRajiv GururaniEEUEAP R&B Nainital See Pic
10.08-11-2016Chainage 67+850Camber checking by C E N H Er Aijaj AhmadRajiv GururaniEEUEAP R&B Nainital See Pic
11.02-11-201666+700BC laying in progressLalit TiwariAEDEA ADB Nainital See Pic
12.02-11-201666+100Core cuttingLalit TiwariAEDEA ADB Nainital See Pic
13.02-11-201669+300SE sir Almora UEAP giving instruction for cleaning of Road surface before laying tack coat ,DBM layerLalit TiwariAEDEA ADB Nainital See Pic
14.02-11-201669+155Laying of DBM in presence of SE sir Almora UEAP circleLalit TiwariAEDEA ADB Nainital See Pic
15.02-11-201668+500SE sir Almora visit and thickness checking of DBMLalit TiwariAEDEA ADB Nainital See Pic
16.10-10-201618.950BC workRajendra Prasad SatiJEUEAP R&B Nainital See Pic
17.10-10-201619.925BC workRajendra Prasad SatiJEUEAP R&B Nainital See Pic
18.28-09-2016Chainage 65+480BC laying in progressRajiv GururaniEEUEAP R&B Nainital See Pic
19.15-09-2016chainage 22+170grade correction at approach of culvert by laying WMMRajiv GururaniEEUEAP R&B Nainital See Pic
20.10-07-2016Chainage 23+800Plantation in road side near kamala villageRajiv GururaniEEUEAP R&B Nainital See Pic