Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C-82A Agreement signed
Project: UEAP-RB Package No.: 1086 Package Name: UEAP/PWD/C-82A Sanction Cost: 1554.00  lakhs
District: Nainital Block: Kotabagh Constituency: Kaladhungi Circle:
DEA: DEA UEAP Nainital DSC: CCEE Group India Pvt.Ltd DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  5911   Ramnagar Kaladungi Haldwani Kathgodam Chorgaliya Sitarganj Bijti MR PHASE 1 (Km 5 TO 14 Km) (10.000 KM.) (completed)
Procurement:
Package No.: 1086        Package Name: UEAP/PWD/C-82A        Tender Date: 30-01-2016        Current Status: Agreement signed        Achieved on Date: 29-03-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-82A        Contractor Name: PRL Projects and Infrastructure Ltd.       
Start Date: 07-04-2016        Intended Completion Date: 06-12-2016       
Total Bond Cost: 94907998 (949.08 lakhs)        Variation Cost: 5673055.12 (56.73 lakhs)     Hence Total Bond Cost is   100581053.12 (1005.81 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works150.00 m10.52150.00 m150.00 m1.1810.52
2.BM i/c Prime Coat, Tack Coat13.80 KM640.8113.80 KM13.80 KM71.57640.81
3.SDBC i/c Tackcoat11.00 KM199.2111.00 KM11.00 KM22.25199.21
4.Cause Way2.00 No8.892.00 No2.00 No0.998.89
5.Culverts/Scupper 3.00 No9.073.00 No3.00 No1.019.07
6.Crash Barrier300.00 m6.90300.00 m300.00 m0.776.90
7.Road Furniture3700.00 No2.003700.00 No3700.00 No0.222.00
8.Other Allied Works & Finishing Work 110.00 Job18.00110.00 Job110.00 Job2.0118.00
Total Amount: 895.4 100   895.4
Remarks: No Remarks       Work Program Made On: 17-06-2016       Updation of work program on: 04-11-2016      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-April-2016199.50  lakhs
2.13-May-201683.63  lakhs
3.31-May-2016198.97  lakhs
4.21-June-201695.40  lakhs
5.30-September-2016123.02  lakhs
6.10-October-201692.50  lakhs
7.26-November-201658.08  lakhs
8.16-December-201626.56  lakhs
9.23-February-201759.86  lakhs
10.30-May-201733.79  lakhs
11.22-June-201710.66  lakhs
12.26-September-201722.28  lakhs
Total 1004.25  lakhs
% Payment 99.84 %
Advance Amount:  94.91  lakhs        Recovered Amount:  94.91  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1543     No. of Test Done : 1543      No. of Test Passed : 1519      No. of Test Failed : 1   Test report of this package
Number of Pics Available on Web Repository: 52
Number of Notice(s) issued: 31

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-12-2016Chainage 13+250Shoulder protection with Interlocking tilesRajiv GururaniEEUEAP R&B Nainital See Pic
2.30-12-2016Chainage 12+680Thermoplast work at start of BelparauRajiv GururaniEEUEAP R&B Nainital See Pic
3.09-12-201614..250Thermoplast paintRajendra Prasad SatiJEUEAP R&B Nainital See Pic
4.09-12-2016Ch 6.142 to 5.879Tile work in shoulder both side near Choi ChowkRajendra Prasad SatiJEUEAP R&B Nainital See Pic
5.09-12-2016Ch 5.879 to 6.142 both side near ChoiTile work in shoulder protection near ChoiRajendra Prasad SatiJEUEAP R&B Nainital See Pic
6.09-12-2016CH 5.879 to 6.142 in ChoiTile work in shoulder protectionRajendra Prasad SatiJEUEAP R&B Nainital See Pic
7.09-12-2016CH 4.775. RHS sideTile work in shoulder protectionRajendra Prasad SatiJEUEAP R&B Nainital See Pic
8.08-11-2016Choi Chauraha ChainageSE sir inspection of RoadRajiv GururaniEEUEAP R&B Nainital See Pic
9.02-11-201611+800Reinforcement Binding before Concrete work checked by SE Sir UEAP DehradunLalit TiwariAEDEA ADB Nainital See Pic
10.02-11-20166+035Checking of RBM Thickness by SE sir UEAP DehradunLalit TiwariAEDEA ADB Nainital See Pic
11.02-11-20166+020Camber checking by SE sir UEAP DehradunLalit TiwariAEDEA ADB Nainital See Pic
12.02-11-20169+500Social Expert site visitLalit TiwariAEDEA ADB Nainital See Pic
13.02-11-20169+900Camber Checking by Chief Engineer SirLalit TiwariAEDEA ADB Nainital See Pic
14.02-11-20169+950Chief Engineer sir visitLalit TiwariAEDEA ADB Nainital See Pic
15.02-11-20169+930CE sir visitLalit TiwariAEDEA ADB Nainital See Pic
16.02-11-20169+930CE sir VisitLalit TiwariAEDEA ADB Nainital See Pic
17.02-11-2016At plantBC Grading TestLalit TiwariAEDEA ADB Nainital See Pic
18.02-11-20166+020Core cutting DBMLalit TiwariAEDEA ADB Nainital See Pic
19.02-11-2016at kamolaPlantation on road sideLalit TiwariAEDEA ADB Nainital See Pic
20.02-11-20166+300Thickness checking of DB MLalit TiwariAEDEA ADB Nainital See Pic