UEAP/PWD/C-81
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1085 |
Package Name: |
UEAP/PWD/C-81 |
Sanction Cost: |
740.00 lakhs |
District: |
Pauri |
Block: |
Khirsu |
Constituency: |
Srinagar |
Circle: |
|
DEA: |
DEA UEAP Pauri |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5514 Internal Motor Road of Nagar Palika Parishad Srinagar (12.000 KM.) (in prorgress) |
|
Procurement: |
Package No.: 1085
Package Name: UEAP/PWD/C-81
Tender Date: 14-08-2015
Current Status: Agreement signed
Achieved on Date: 17-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-81
Contractor Name: N P Buildwell Pvt. Ltd
|
Start Date: 30-12-2015
Intended Completion Date: 08-08-2017
Original End Date: 29-03-2017
|
Total Bond Cost: 66277367.5 (662.77 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 1391838 for 42 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 2.10 KM | 9.22 | 2.10 KM | 0.00 KM | 0 | 0.00 | 2. | R/Wall, B/ Wall Type Protection works | 426.00 m | 78.80 | 482.00 m | 417.00 m | 10.27 | 66.73 | 3. | GSB/RBI/G-1 | 1.06 KM | 7.39 | 0.90 KM | 0.76 KM | 0.94 | 6.24 | 4. | G-2 | 1.03 KM | 5.41 | 0.90 KM | 0.76 KM | 0.69 | 4.57 | 5. | G-3 | 1.44 KM | 7.79 | 1.30 KM | 0.96 KM | 0.87 | 5.76 | 6. | PC/CC i/c Prime Coat, Tack Coat | 1.73 KM | 22.60 | 1.73 KM | 0.00 KM | 0 | 0.00 | 7. | BM i/c Prime Coat, Tack Coat | 2.80 KM | 50.10 | 5.53 KM | 2.01 KM | 2.74 | 13.07 | 8. | SDBC i/c Tackcoat | 7.35 KM | 162.12 | 7.35 KM | 4.34 KM | 14.43 | 95.73 | 9. | Cause Way | 1.00 No | 7.65 | 1.00 No | 0.00 No | 0 | 0.00 | 10. | Culverts/Scupper | 4.00 No | 286.51 | 4.00 No | 0.00 No | 0 | 0.00 | 11. | longitudinal Drain | 3800.00 m | 10.94 | 1000.00 m | 790.00 m | 1.3 | 8.64 | 12. | Crash Barrier | 200.00 m | 5.40 | 200.00 m | 0.00 m | 0 | 0.00 | 13. | Road Furniture | 229.00 No | 4.83 | 234.00 No | 103.00 No | 0.32 | 0.96 | 14. | Other Allied Works & Finishing Work | 1.00 Job | 4.83 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
663.59 |
|
31.56 |
201.7 |
|
Remarks:
No Remarks
Work Program Made On:
12-09-2016
Updation of work program on:
28-06-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 12-December-2016 | 334.51 lakhs |
2. | 28-February-2017 | 25.49 lakhs |
3. | 18-April-2017 | 13.67 lakhs |
4. | 31-May-2017 | 30.46 lakhs |
5. | 19-June-2017 | 32.40 lakhs |
6. | 11-August-2017 | 14.66 lakhs |
7. | 16-October-2017 | 10.93 lakhs |
Total |
462.12 lakhs |
% Payment |
69.73 % |
|
Advance Amount: 11.70 lakhs
Recovered Amount: 23.40 lakhs
Balance to be Recovered -11.70 lakhs
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | Staff not deputed yet | Environment & Social Compliances(Sub Project level): | Internal Motor Road of Nagar Palika Parishad Srinagar(5514) | No Pending Issue |
Detailed report of this Package
|
|
Quality
|
Test Information not Available. |
Number of Pics Available on Web Repository: 12 |
Number of Notice(s) issued: 55 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 18-04-2017 | Gola bazar to Dr. Nethani resi Ch 0.430 | Core thickness checking | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
2. | 15-03-2017 | Gola bazar to Dr. Nethani resi road | Core cutting test | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
3. | 15-03-2017 | Grudwara road ch 0.350 | Core thickness checking | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
4. | 15-03-2017 | At Grudwara Road Ch 0.350 | Cure cutting test | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
5. | 08-03-2017 | Ch 0.740 | Road inspection by E.E. sir | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
6. | 08-03-2017 | Km 1Hec 0-2 | Site Inspection by C.E. sir at Dang Dhobighat M/R | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
7. | 19-11-2016 | Ch 0.390 | Hot mix work BC in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
8. | 19-11-2016 | Ch 0.460 Gola bazar to Dr.Nethani Resi Road | Hot mix work BC in progress | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
9. | 06-10-2016 | Ch 0.480 | Reinforcement in progress for C.C.road | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
10. | 30-09-2016 | Ch 1.460 | Brest wall in plum concrete | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
11. | 21-09-2016 | Ch 1.190 | Dang road visit | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
12. | 06-09-2016 | Internal rd Srinagar, 1+350 | CC road under construction | Col M S Bisht (Retd) | RE | DSC2 | See Pic |
|
|