UEAP/PWD/C-79
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1083 |
Package Name: |
UEAP/PWD/C-79 |
Sanction Cost: |
550.00 lakhs |
District: |
Tehri |
Block: |
Narendra Nagar |
Constituency: |
Narendra Nagar |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5335 Internal Motor Road of Muni Ki Reti & Tapowan Area (4.150 KM.) (completed) |
|
Procurement: |
Package No.: 1083
Package Name: UEAP/PWD/C-79
Tender Date: 14-08-2015
Current Status: Agreement signed
Achieved on Date: 30-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-79
Contractor Name: Maa Bhagwati Construction company
|
Start Date: 21-01-2016
Intended Completion Date: 30-05-2017
Original End Date: 20-06-2017
|
Total Bond Cost: 47565125.5 (475.65 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2853960 for 120 days
LD Analysis for Milestone2: calculated LD is Rs 4114459 for 173 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 550.00 m | 13.35 | 550.00 m | 550.00 m | 2.81 | 13.35 | 2. | G-2 | 1.91 KM | 34.08 | 1.91 KM | 1.91 KM | 7.17 | 34.08 | 3. | G-3 | 1.91 KM | 21.54 | 1.91 KM | 1.91 KM | 4.53 | 21.54 | 4. | PC/CC i/c Prime Coat, Tack Coat | 6.20 KM | 3.15 | 6.20 KM | 6.20 KM | 0.66 | 3.15 | 5. | BM i/c Prime Coat, Tack Coat | 2.40 KM | 37.83 | 1.20 KM | 1.20 KM | 7.95 | 37.83 | 6. | SDBC i/c Tackcoat | 3.80 KM | 105.06 | 3.42 KM | 3.42 KM | 22.09 | 105.06 | 7. | longitudinal Drain | 1100.00 m | 160.53 | 1100.00 m | 1100.00 m | 33.75 | 160.53 | 8. | Road Furniture | 117.00 No | 11.42 | 117.00 No | 117.00 No | 2.4 | 11.42 | 9. | Other Allied Works & Finishing Work | 1.00 Job | 88.70 | 1.00 Job | 1.00 Job | 18.65 | 88.70 |
Total Amount: |
475.66 |
|
100 |
475.66 |
|
Remarks:
No Remarks
Work Program Made On:
06-09-2016
Updation of work program on:
13-07-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-August-2016 | 26.58 lakhs |
2. | 21-December-2016 | 129.30 lakhs |
3. | 28-February-2017 | 40.33 lakhs |
4. | 17-June-2017 | 49.45 lakhs |
5. | 27-June-2017 | 45.96 lakhs |
6. | 31-August-2017 | 20.74 lakhs |
7. | 28-September-2017 | 43.95 lakhs |
Total |
356.31 lakhs |
% Payment |
74.91 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Bill should be issued |
|
Pending Environmental & Social issues
|
|
Quality
|
Test Information not Available. |
Number of Pics Available on Web Repository: 22 |
Number of Notice(s) issued: 47 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-03-2017 | 1.350 | P.c.c laying | Amit Kumar 2 | AE | UDRP AF S&B Bageshwar | See Pic |
2. | 21-02-2017 | 1.550 | Tiles laying | Amit Kumar 2 | AE | UDRP AF S&B Bageshwar | See Pic |
3. | 21-02-2017 | 1.625 | Tiles laying | Amit Kumar 2 | AE | UDRP AF S&B Bageshwar | See Pic |
4. | 21-02-2017 | 1.600 | Concreting | Amit Kumar 2 | AE | UDRP AF S&B Bageshwar | See Pic |
5. | 03-02-2017 | Ch.1+580 | Core cutting on BC | Asha Rawat | JE | UEAP R&B Tehri | See Pic |
6. | 03-02-2017 | Ch.1+710 | Core cutting | Asha Rawat | JE | UEAP R&B Tehri | See Pic |
7. | 05-12-2016 | 0+550 | Visit by Exn sir on C-79 pkg at Laxman jhulha | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
8. | 05-12-2016 | 0+750 | Visit by Exn sir on C-79 pkg at Laxman jhulha | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
9. | 05-12-2016 | 0+870 | Finishing work of BM at Laxman jhula | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
10. | 05-12-2016 | 0+850 | Compaction on BM work at Laxman Jhulha | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
11. | 05-12-2016 | 0+850 | Measure thickness of BM & found satisfactory at Laxman Jhulha | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
12. | 05-12-2016 | 0+900 | Compaction on BM at Laxman jhulha | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
13. | 05-12-2016 | 0+900 | Laying of BM at laxman jhulha | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
14. | 05-12-2016 | 0+900 | Spreading tackcoat for BM work at Laxman jhulha | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
15. | 28-11-2016 | 1+570 | Finishingof BC work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
16. | 28-11-2016 | 1+550 | Laying of BC work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
17. | 28-11-2016 | 1+500 | Rolling on BC work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
18. | 28-11-2016 | 0+800 | Spreading Tack coat for BC work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
19. | 25-11-2016 | 2+350 | BC work is going on start from bhadrakali | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
20. | 23-11-2016 | 5+200 | Laying BC | Asha Rawat | JE | UEAP R&B Tehri | See Pic |
|
|