Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C-79 Agreement signed
Project: UEAP-RB Package No.: 1083 Package Name: UEAP/PWD/C-79 Sanction Cost: 550.00  lakhs
District: Tehri Block: Narendra Nagar Constituency: Narendra Nagar Circle:
DEA: DEA UEAP Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  5335   Internal Motor Road of Muni Ki Reti & Tapowan Area (4.150 KM.) (completed)
Procurement:
Package No.: 1083        Package Name: UEAP/PWD/C-79        Tender Date: 14-08-2015        Current Status: Agreement signed        Achieved on Date: 30-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-79        Contractor Name: Maa Bhagwati Construction company       
Start Date: 21-01-2016        Intended Completion Date: 30-05-2017        Original End Date:  20-06-2017
Total Bond Cost: 47565125.5 (475.65 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 2853960 for 120 days        LD Analysis for Milestone2: calculated LD is Rs 4114459 for 173 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works550.00 m13.35550.00 m550.00 m2.8113.35
2.G-21.91 KM34.081.91 KM1.91 KM7.1734.08
3.G-31.91 KM21.541.91 KM1.91 KM4.5321.54
4.PC/CC i/c Prime Coat, Tack Coat6.20 KM3.156.20 KM6.20 KM0.663.15
5.BM i/c Prime Coat, Tack Coat2.40 KM37.831.20 KM1.20 KM7.9537.83
6.SDBC i/c Tackcoat3.80 KM105.063.42 KM3.42 KM22.09105.06
7.longitudinal Drain1100.00 m160.531100.00 m1100.00 m33.75160.53
8.Road Furniture117.00 No11.42117.00 No117.00 No2.411.42
9.Other Allied Works & Finishing Work 1.00 Job88.701.00 Job1.00 Job18.6588.70
Total Amount: 475.66 100   475.66
Remarks: No Remarks       Work Program Made On: 06-09-2016       Updation of work program on: 13-07-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-August-201626.58  lakhs
2.21-December-2016129.30  lakhs
3.28-February-201740.33  lakhs
4.17-June-201749.45  lakhs
5.27-June-201745.96  lakhs
6.31-August-201720.74  lakhs
7.28-September-201743.95  lakhs
Total 356.31  lakhs
% Payment 74.91 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
Test Information not Available.
Number of Pics Available on Web Repository: 22
Number of Notice(s) issued: 47

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-03-20171.350P.c.c layingAmit Kumar 2AEUDRP AF S&B Bageshwar See Pic
2.21-02-20171.550Tiles layingAmit Kumar 2AEUDRP AF S&B Bageshwar See Pic
3.21-02-20171.625Tiles layingAmit Kumar 2AEUDRP AF S&B Bageshwar See Pic
4.21-02-20171.600ConcretingAmit Kumar 2AEUDRP AF S&B Bageshwar See Pic
5.03-02-2017Ch.1+580Core cutting on BCAsha RawatJEUEAP R&B Tehri See Pic
6.03-02-2017Ch.1+710Core cuttingAsha RawatJEUEAP R&B Tehri See Pic
7.05-12-20160+550Visit by Exn sir on C-79 pkg at Laxman jhulhaShivendra PrakashAEUEAP- CA Tehri See Pic
8.05-12-20160+750Visit by Exn sir on C-79 pkg at Laxman jhulhaShivendra PrakashAEUEAP- CA Tehri See Pic
9.05-12-20160+870Finishing work of BM at Laxman jhulaShivendra PrakashAEUEAP- CA Tehri See Pic
10.05-12-20160+850Compaction on BM work at Laxman JhulhaShivendra PrakashAEUEAP- CA Tehri See Pic
11.05-12-20160+850Measure thickness of BM & found satisfactory at Laxman JhulhaShivendra PrakashAEUEAP- CA Tehri See Pic
12.05-12-20160+900Compaction on BM at Laxman jhulhaShivendra PrakashAEUEAP- CA Tehri See Pic
13.05-12-20160+900Laying of BM at laxman jhulhaShivendra PrakashAEUEAP- CA Tehri See Pic
14.05-12-20160+900Spreading tackcoat for BM work at Laxman jhulhaShivendra PrakashAEUEAP- CA Tehri See Pic
15.28-11-20161+570Finishingof BC workShivendra PrakashAEUEAP- CA Tehri See Pic
16.28-11-20161+550Laying of BC workShivendra PrakashAEUEAP- CA Tehri See Pic
17.28-11-20161+500Rolling on BC workShivendra PrakashAEUEAP- CA Tehri See Pic
18.28-11-20160+800Spreading Tack coat for BC workShivendra PrakashAEUEAP- CA Tehri See Pic
19.25-11-20162+350BC work is going on start from bhadrakaliShivendra PrakashAEUEAP- CA Tehri See Pic
20.23-11-20165+200Laying BCAsha RawatJEUEAP R&B Tehri See Pic