UDRP/PWD/02/RD/097
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
108 |
Package Name: |
UDRP/PWD/02/RD/097 |
Sanction Cost: |
949.39 lakhs |
District: |
Chamoli |
Block: |
Tharali |
Constituency: |
Tharali |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
3 |
Subproject in this package |
1 1252 Lolti - Kasbinagar Motor Road (3.520 KM.) (completed) | 2 1253 Lolti - Malbajwad Motor Road (6.000 KM.) (completed) | 3 1275 Tharali-Junidhar Motor Road (3.600 KM.) (completed) |
|
Procurement: |
Package No.: 108
Package Name: UDRP/PWD/02/RD/097
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 11-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/RD/097
Contractor Name: Sansun Contractors Pvt. Ltd.
|
Start Date: 18-09-2015
Intended Completion Date: 25-06-2017
Original End Date: 17-12-2016
|
Total Bond Cost: 74543585.76 (745.44 lakhs)
Variation Cost: 18843460.57 (188.43 lakhs) Hence Total Bond Cost is 93387046.33 (933.87 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2459952 for 66 days
LD Analysis for Milestone2: calculated LD is Rs 3689928 for 99 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 10.10 KM | 39.48 | 10.10 KM | 10.10 KM | 5.9 | 39.48 | 2. | R/Wall, B/ Wall Type Protection works | 3136.00 m | 185.32 | 3136.00 m | 3136.00 m | 27.27 | 185.32 | 3. | G-2 | 6.60 KM | 54.98 | 6.10 KM | 6.10 KM | 7.8 | 54.98 | 4. | G-3 | 7.10 KM | 55.38 | 6.80 KM | 6.80 KM | 8.1 | 55.38 | 5. | PC/CC i/c Prime Coat, Tack Coat | 13.10 KM | 167.48 | 13.10 KM | 13.10 KM | 25.44 | 167.48 | 6. | Culverts/Scupper | 51.00 No | 66.22 | 51.00 No | 51.00 No | 9.49 | 66.22 | 7. | longitudinal Drain | 13100.00 m | 74.06 | 13100.00 m | 13100.00 m | 11.42 | 74.06 | 8. | Parapet | 332.00 No | 8.58 | 382.00 No | 382.00 No | 1.24 | 8.58 | 9. | Road Furniture | 489.00 No | 5.32 | 489.00 No | 489.00 No | 0.81 | 5.32 | 10. | Cause Way | 4.00 No | 10.17 | 4.00 No | 4.00 No | 1.59 | 10.17 | 11. | Crash Barrier | 325.00 m | 6.80 | 500.00 m | 500.00 m | 0.95 | 6.80 |
Total Amount: |
673.79 |
|
100 |
673.79 |
|
Remarks:
No Remarks
Work Program Made On:
25-09-2015
Updation of work program on:
24-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 25-January-2016 | 17.71 lakhs |
2. | 04-March-2016 | 55.89 lakhs |
3. | 31-March-2016 | 35.00 lakhs |
4. | 03-May-2016 | 47.13 lakhs |
5. | 30-June-2016 | 101.26 lakhs |
6. | 18-October-2016 | 39.23 lakhs |
7. | 26-October-2016 | 73.46 lakhs |
8. | 17-December-2016 | 41.83 lakhs |
9. | 23-March-2017 | 61.65 lakhs |
10. | 13-October-2017 | 118.44 lakhs |
11. | 27-November-2017 | 80.00 lakhs |
12. | 17-February-2018 | 97.99 lakhs |
13. | 13-September-2018 | 3.70 lakhs |
14. | 24-December-2015 | 8.31 lakhs |
15. | 09-March-2017 | 11.12 lakhs |
16. | 02-February-2017 | 22.34 lakhs |
17. | 25-May-2017 | 30.18 lakhs |
18. | 28-July-2017 | 82.60 lakhs |
Total |
927.84 lakhs |
% Payment |
99.35 % |
|
Advance Amount: 25.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 25.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 137 |
Number of Notice(s) issued: 71 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 12-05-2017 | .050 | Land slide due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
2. | 12-05-2017 | 0.150 | Scupper damage due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
3. | 12-05-2017 | 0.300 | Scupper damage due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
4. | 12-05-2017 | 0.300 | Land slide due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
5. | 12-05-2017 | 0.400 | Settlement of road due heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
6. | 12-05-2017 | Ch 0.400 | Settlement due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
7. | 12-05-2017 | 0.675 | Wire crate damage due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
8. | 12-05-2017 | Ch0 .875 | Wbm grading no 2 damage due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
9. | 12-05-2017 | Ch 1100 | Land slide due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
10. | 12-05-2017 | 1.150 | Wbm grading 2 damage due to heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
11. | 12-05-2017 | Ch.1.250 | Land slide due to last night heavy rain | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
12. | 21-01-2017 | 5.780 | Preparation for subgrade | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
13. | 21-01-2017 | 1.475 | 5.00 M span culvert work in progress | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
14. | 05-01-2017 | 5900 | Footpath for villegers | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
15. | 05-01-2017 | 5975 | B/W | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
16. | 05-01-2017 | 5840 | Wire crate | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
17. | 30-12-2016 | 2.525 | old.p.c | Sudhir Kumar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
18. | 30-12-2016 | 2.525 | old p.c | Sudhir Kumar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
19. | 19-12-2016 | 1.500 | Lolti malbajwab moter road layout of 6.0 m span culvert | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
20. | 19-12-2016 | 1.510 | 5.m.span.calvart | Ajay Narayan Pandey | RE | DSC1 R&B WB Chamoli | See Pic |
|
|