Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/02/RD/097 Agreement signed
Project: UDRP-RB Package No.: 108 Package Name: UDRP/PWD/02/RD/097 Sanction Cost: 949.39  lakhs
District: Chamoli Block: Tharali Constituency: Tharali Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 3
Subproject in this package
1  1252   Lolti - Kasbinagar Motor Road (3.520 KM.) (completed)
2  1253   Lolti - Malbajwad Motor Road (6.000 KM.) (completed)
3  1275   Tharali-Junidhar Motor Road (3.600 KM.) (completed)
Procurement:
Package No.: 108        Package Name: UDRP/PWD/02/RD/097        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 11-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/RD/097        Contractor Name: Sansun Contractors Pvt. Ltd.       
Start Date: 18-09-2015        Intended Completion Date: 25-06-2017        Original End Date:  17-12-2016
Total Bond Cost: 74543585.76 (745.44 lakhs)        Variation Cost: 18843460.57 (188.43 lakhs)     Hence Total Bond Cost is   93387046.33 (933.87 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2459952 for 66 days        LD Analysis for Milestone2: calculated LD is Rs 3689928 for 99 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence10.10 KM39.4810.10 KM10.10 KM5.939.48
2.R/Wall, B/ Wall Type Protection works3136.00 m185.323136.00 m3136.00 m27.27185.32
3.G-26.60 KM54.986.10 KM6.10 KM7.854.98
4.G-37.10 KM55.386.80 KM6.80 KM8.155.38
5.PC/CC i/c Prime Coat, Tack Coat13.10 KM167.4813.10 KM13.10 KM25.44167.48
6.Culverts/Scupper 51.00 No66.2251.00 No51.00 No9.4966.22
7.longitudinal Drain13100.00 m74.0613100.00 m13100.00 m11.4274.06
8.Parapet332.00 No8.58382.00 No382.00 No1.248.58
9.Road Furniture489.00 No5.32489.00 No489.00 No0.815.32
10.Cause Way4.00 No10.174.00 No4.00 No1.5910.17
11.Crash Barrier325.00 m6.80500.00 m500.00 m0.956.80
Total Amount: 673.79 100   673.79
Remarks: No Remarks       Work Program Made On: 25-09-2015       Updation of work program on: 24-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.25-January-201617.71  lakhs
2.04-March-201655.89  lakhs
3.31-March-201635.00  lakhs
4.03-May-201647.13  lakhs
5.30-June-2016101.26  lakhs
6.18-October-201639.23  lakhs
7.26-October-201673.46  lakhs
8.17-December-201641.83  lakhs
9.23-March-201761.65  lakhs
10.13-October-2017118.44  lakhs
11.27-November-201780.00  lakhs
12.17-February-201897.99  lakhs
13.13-September-20183.70  lakhs
14.24-December-20158.31  lakhs
15.09-March-201711.12  lakhs
16.02-February-201722.34  lakhs
17.25-May-201730.18  lakhs
18.28-July-201782.60  lakhs
Total 927.84  lakhs
% Payment 99.35 %
Advance Amount:  25.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  25.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 300     No. of Test Done : 301      No. of Test Passed : 255      No. of Test Failed : 46   Test report of this package
Number of Pics Available on Web Repository: 137
Number of Notice(s) issued: 71

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.12-05-2017.050Land slide due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
2.12-05-20170.150Scupper damage due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
3.12-05-20170.300Scupper damage due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
4.12-05-20170.300Land slide due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
5.12-05-20170.400Settlement of road due heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
6.12-05-2017Ch 0.400Settlement due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
7.12-05-20170.675Wire crate damage due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
8.12-05-2017Ch0 .875Wbm grading no 2 damage due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
9.12-05-2017Ch 1100Land slide due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
10.12-05-20171.150Wbm grading 2 damage due to heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
11.12-05-2017Ch.1.250Land slide due to last night heavy rainVikash SinghJEUDRP R&B Gopeshwar See Pic
12.21-01-20175.780Preparation for subgradeAshwani KumarREDSC4 R&B WB Chamoli See Pic
13.21-01-20171.4755.00 M span culvert work in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
14.05-01-20175900Footpath for villegersVikash SinghJEUDRP R&B Gopeshwar See Pic
15.05-01-20175975B/WVikash SinghJEUDRP R&B Gopeshwar See Pic
16.05-01-20175840Wire crateVikash SinghJEUDRP R&B Gopeshwar See Pic
17.30-12-20162.525old.p.cSudhir KumarSite EngineerDSC1 R&B WB Chamoli See Pic
18.30-12-20162.525old p.cSudhir KumarSite EngineerDSC1 R&B WB Chamoli See Pic
19.19-12-20161.500Lolti malbajwab moter road layout of 6.0 m span culvertVikash SinghJEUDRP R&B Gopeshwar See Pic
20.19-12-20161.5105.m.span.calvartAjay Narayan PandeyREDSC1 R&B WB Chamoli See Pic