UEAP/PWD/C-75
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1079 |
Package Name: |
UEAP/PWD/C-75 |
Sanction Cost: |
477.00 lakhs |
District: |
Pithoragarh |
Block: |
Munsiari |
Constituency: |
Dharchula |
Circle: |
|
DEA: |
DEA UEAP Pithoragarh |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5610 Reconstruction of internal roads of nagar panchayat Munsiyari (6.250 KM.) (completed) |
|
Procurement: |
Package No.: 1079
Package Name: UEAP/PWD/C-75
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 28-10-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-75
Contractor Name: R K Gupta Contractor
|
Start Date: 18-11-2015
Intended Completion Date: 17-11-2016
|
Total Bond Cost: 42904458 (429.04 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 879532 for 41 days
LD Analysis for Milestone2: calculated LD is Rs 2509884 for 117 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | GSB/RBI/G-1 | 0.70 KM | 2.55 | 0.70 KM | 0.70 KM | 0.62 | 2.55 | 2. | G-2 | 0.70 KM | 2.23 | 0.70 KM | 0.70 KM | 0.54 | 2.23 | 3. | G-3 | 1.76 KM | 9.83 | 1.76 KM | 1.76 KM | 2.39 | 9.83 | 4. | PC/CC i/c Prime Coat, Tack Coat | 1.76 KM | 14.83 | 1.76 KM | 1.76 KM | 3.61 | 14.83 | 5. | BM i/c Prime Coat, Tack Coat | 6.30 KM | 131.20 | 6.30 KM | 6.30 KM | 31.95 | 131.20 | 6. | SDBC i/c Tackcoat | 6.30 KM | 87.64 | 6.30 KM | 6.30 KM | 21.34 | 87.64 | 7. | longitudinal Drain | 6540.00 m | 69.52 | 6540.00 m | 6540.00 m | 16.93 | 69.52 | 8. | Crash Barrier | 3000.00 m | 90.00 | 3000.00 m | 3000.00 m | 21.92 | 90.00 | 9. | Road Furniture | 80.00 No | 2.80 | 80.00 No | 80.00 No | 0.68 | 2.80 |
Total Amount: |
410.6 |
|
100 |
410.6 |
|
Remarks:
Package compleated on 31/05/2017
Work Program Made On:
12-09-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 19-March-2016 | 52.64 lakhs |
2. | 25-April-2016 | 27.64 lakhs |
3. | 22-June-2016 | 85.63 lakhs |
4. | 27-October-2016 | 27.76 lakhs |
5. | 25-November-2016 | 38.45 lakhs |
6. | 16-December-2016 | 19.20 lakhs |
Total |
251.32 lakhs |
% Payment |
58.58 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Bill should be issued |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 186 No. of Test Done : 182 No. of Test Passed : 161 No. of Test Failed : 0 No. of Test Result Awaited : 11
Test report of this package
|
|
Number of Pics Available on Web Repository: 56 |
Number of Notice(s) issued: 67 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 10-11-2016 | Chng 0.000 to 0.100 gic road | Tack coat on bm surface for sdbc laying | Ankit Nakoti | AE | UEAP- CA | See Pic |
2. | 10-11-2016 | Chng 0.150-0.175 G.I.C. Road | Loose thickness for sdbc | Ankit Nakoti | AE | UEAP- CA | See Pic |
3. | 10-11-2016 | Chng.150-.175 G.I.C. road | Compacted thickness reqd 25 mm loose thickness during layibg achieved as 35 mm | Ankit Nakoti | AE | UEAP- CA | See Pic |
4. | 10-11-2016 | Animal hosp road chng. .900 to 1.000 near zara hotel | 103 degree celcius temp achieved using evotherm addmixture at 2232 m altitude | Ankit Nakoti | AE | UEAP- CA | See Pic |
5. | 26-10-2016 | 0.125 to 0.150 animal hospital aproach road | Sdbc thickness loose 35 mm achieved during laying required thickness after compaction 25 mm | Ankit Nakoti | AE | UEAP- CA | See Pic |
6. | 26-10-2016 | Chng 0.250-0.200 animal hospital road | Sdbc surface dUring rolling | Ankit Nakoti | AE | UEAP- CA | See Pic |
7. | 26-10-2016 | 0.375 near helipad animal hospital road | Sdbc lahing | Ankit Nakoti | AE | UEAP- CA | See Pic |
8. | 26-10-2016 | Near helipad | Tack coat for.sdc laying @ animal.hospital road | Ankit Nakoti | AE | UEAP- CA | See Pic |
9. | 26-10-2016 | Chng 0.600-0.650 animal hospital road | Rolling on bm surface | Ankit Nakoti | AE | UEAP- CA | See Pic |
10. | 25-10-2016 | ChNg + 0.025 to +0.050 | Rolling on bm surface | Ankit Nakoti | AE | UEAP- CA | See Pic |
11. | 24-10-2016 | Near helipad | Rolling on bm surface | Ankit Nakoti | AE | UEAP- CA | See Pic |
12. | 24-10-2016 | Near helipad | Rolling om bm surface | Ankit Nakoti | AE | UEAP- CA | See Pic |
13. | 29-08-2016 | Police station aproach road | Inspection se sir | Ankit Nakoti | AE | UEAP- CA | See Pic |
14. | 29-08-2016 | Dhandadhaar jyati m/r | Inspection of SE sir, for checking of grading for G2 | Ankit Nakoti | AE | UEAP- CA | See Pic |
15. | 29-08-2016 | Polics statiom road | Se sir inspection for thickness of beam of crash barrier | Ankit Nakoti | AE | UEAP- CA | See Pic |
16. | 29-08-2016 | Police station approach road chng +.075 | Se sir inspection checkin standpost thickness | Ankit Nakoti | AE | UEAP- CA | See Pic |
17. | 29-08-2016 | Gic college road | Inspection of se sir wbm thickness | Ankit Nakoti | AE | UEAP- CA | See Pic |
18. | 29-08-2016 | Police statin aproach road chng 0.050 | Se sir inspection for wbm | Ankit Nakoti | AE | UEAP- CA | See Pic |
19. | 16-06-2016 | Animal hospital road | S.E. Sir inspection on site instructed for proper runoff of water from road surface and cross drainage to be constructed | Ankit Nakoti | AE | UEAP- CA | See Pic |
20. | 15-06-2016 | Animal hospital road | S.E.sir site inspection | Ankit Nakoti | AE | UEAP- CA | See Pic |
|
|