Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C-73 Agreement signed
Project: UEAP-RB Package No.: 1077 Package Name: UEAP/PWD/C-73 Sanction Cost: 1226.00  lakhs
District: Nainital Block: Betalghat Constituency: Nainital Circle:
DEA: DEA UEAP Nainital DSC: CCEE Group India Pvt.Ltd DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5905   Ratighat-Betalghat Motor Road (19.000 KM.) (completed)
Procurement:
Package No.: 1077        Package Name: UEAP/PWD/C-73        Tender Date: 06-01-2015        Current Status: Agreement signed        Achieved on Date: 13-04-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-73        Contractor Name: Woodhill Infrastructure Ltd       
Start Date: 07-05-2015        Intended Completion Date: 06-11-2016       
Total Bond Cost: 106054285 (1060.54 lakhs)        Variation Cost: 15772285.00 (157.72 lakhs)     Hence Total Bond Cost is   121826570 (1218.27 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 159081 for 3 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.40 KM8.500.58 KM0.58 KM0.98.50
2.R/Wall, B/ Wall Type Protection works1523.00 m71.251874.00 m1874.00 m7.5871.25
3.GSB/RBI/G-10.40 KM2.150.20 KM0.20 KM0.232.15
4.G-20.48 KM6.571.50 KM1.50 KM0.76.57
5.G-35.88 KM31.777.60 KM7.60 KM3.3831.77
6.BM i/c Prime Coat, Tack Coat19.00 KM283.8719.00 KM19.00 KM30.19283.87
7.SDBC i/c Tackcoat19.00 KM249.5719.00 KM19.00 KM26.54249.57
8.Cause Way11.00 No40.0210.00 No10.00 No4.2640.02
9.Culverts/Scupper 25.00 No38.5125.00 No25.00 No4.138.51
10.longitudinal Drain6518.00 m58.667047.00 m7047.00 m6.2458.66
11.Crash Barrier2732.00 m84.692732.00 m2732.00 m9.0184.69
12.Parapet603.00 No54.24250.00 No250.00 No5.7754.24
13.Road Furniture48.00 No2.53186.00 No186.00 No0.272.53
14.Other Allied Works & Finishing Work 9.00 Job8.009.00 Job9.00 Job0.858.00
Total Amount: 940.33 100   940.33
Remarks: No Remarks       Work Program Made On: 31-07-2015       Updation of work program on: 25-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.25-July-201542.26  lakhs
2.19-September-201560.97  lakhs
3.20-October-201570.85  lakhs
4.28-November-201572.55  lakhs
5.31-December-201532.42  lakhs
6.29-February-201635.65  lakhs
7.31-March-201684.21  lakhs
8.29-April-2016107.49  lakhs
9.23-May-2016117.90  lakhs
10.20-June-2016142.72  lakhs
11.26-July-2016152.64  lakhs
12.29-September-201671.56  lakhs
13.27-October-201621.58  lakhs
14.28-February-201724.64  lakhs
15.19-June-201735.35  lakhs
16.11-October-201715.48  lakhs
Total 1088.27  lakhs
% Payment 89.33 %
Advance Amount:  105.00  lakhs        Recovered Amount:  105.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1144     No. of Test Done : 1146      No. of Test Passed : 1111      No. of Test Failed : 27   Test report of this package
Number of Pics Available on Web Repository: 46
Number of Notice(s) issued: 73

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.02-11-201623+400BM laying in progressLalit TiwariAEDEA ADB Nainital See Pic
2.28-06-2016Chainage 30+700Road after B CRajiv GururaniEEUEAP R&B Nainital See Pic
3.28-06-2016Chainage 31+400Road after completionRajiv GururaniEEUEAP R&B Nainital See Pic
4.29-05-2016Chainage 18+200Plum concrete at cause wayRajiv GururaniEEUEAP R&B Nainital See Pic
5.13-05-2016BM work in progressLalit TiwariAEDEA ADB Nainital See Pic
6.13-05-201621+350B C work with side kutcha drainLalit TiwariAEDEA ADB Nainital See Pic
7.18-03-201619+800BM LayingLalit TiwariAEDEA ADB Nainital See Pic
8.18-03-201618+600Plum wallLalit TiwariAEDEA ADB Nainital See Pic
9.17-03-2016Chainage 19+950B M work started from km 20Rajiv GururaniEEUEAP R&B Nainital See Pic
10.17-03-2016Chainage 19+850BM work in progressRajiv GururaniEEUEAP R&B Nainital See Pic
11.04-03-2016Chainage15+200Sprinkling water on W B MRajiv GururaniEEUEAP R&B Nainital See Pic
12.13-01-2016Chainage 15+600Sub Base preparation for B M at undulations & depressed portionRajiv GururaniEEDEA ADB Nainital See Pic
13.19-08-2015Chainage 0+200B/wall constructionRajiv GururaniEEDEA ADB Nainital See Pic
14.11-08-201523+000Construction of B/WLalit TiwariAEDEA ADB Nainital See Pic
15.11-08-201516+450Construction of R/WLalit TiwariAEDEA ADB Nainital See Pic
16.11-08-201515+025Construction of U Type Side DrainLalit TiwariAEDEA ADB Nainital See Pic
17.10-08-20150+230Construction of B/WLalit TiwariAEDEA ADB Nainital See Pic
18.24-07-201524-650Selep cleringAnil KumarJEUEAP R&B Nainital See Pic
19.22-07-201521-200Selep cleringAnil KumarJEUEAP R&B Nainital See Pic
20.16-07-201521.200Land slide/slip clrarence/Opening communicationRajendra Prasad SatiJEUEAP R&B Nainital See Pic