Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C-71 Agreement signed
Project: UEAP-RB Package No.: 1075 Package Name: UEAP/PWD/C-71 Sanction Cost: 3636.00  lakhs
District: Pauri Block: Dogadda Constituency: Yamkeshwar Circle:
DEA: DEA UEAP Pauri DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5505   Lakshman jhoola Rathuwadhaab Dhumakot Motor road (80.000 KM.) (in prorgress)
Procurement:
Package No.: 1075        Package Name: UEAP/PWD/C-71        Tender Date: 06-01-2015        Current Status: Agreement signed        Achieved on Date: 25-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-71        Contractor Name: Woodhill Infrastructure Ltd       
Start Date: 01-07-2015        Intended Completion Date: 31-03-2017       
Total Bond Cost: 296910950 (2969.11 lakhs)        Variation Cost: 29646131.00 (296.46 lakhs)     Hence Total Bond Cost is   326557081 (3265.57 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 17517690 for 118 days        LD Analysis for Milestone2: calculated LD is Rs 9352665 for 63 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence4.22 KM31.281.89 KM1.20 KM0.3319.86
2.R/Wall, B/ Wall Type Protection works3004.00 m291.742341.00 m1360.00 m2.82169.49
3.GSB/RBI/G-10.59 KM4.130.59 KM0.00 KM00.00
4.G-21.59 KM19.361.25 KM0.70 KM0.1810.84
5.G-39.31 KM72.387.83 KM3.02 KM0.4727.92
6.PC/CC i/c Prime Coat, Tack Coat0.53 KM5.500.53 KM0.00 KM00.00
7.BM i/c Prime Coat, Tack Coat78.64 KM1057.7825.34 KM25.34 KM17.631000.00
8.SDBC i/c Tackcoat80.00 KM862.9580.00 KM73.00 KM13.13787.44
9.Cause Way40.00 No3031.3442.00 No15.00 No18.04357.14
10.Culverts/Scupper 41.00 No211.5640.00 No8.00 No0.7142.31
11.longitudinal Drain71785.00 m70.7867655.00 m45050.00 m0.7947.13
12.Crash Barrier3867.00 m112.143867.00 m1354.00 m0.6539.27
13.Parapet1560.00 No39.34160.00 No50.00 No0.2112.29
14.Road Furniture4561.00 No150.314571.00 No662.00 No0.363.16
15.Other Allied Works & Finishing Work 1.00 Job38.681.00 Job0.00 Job00.00
Total Amount: 5999.27 55.32   2516.85
Remarks: No Remarks       Work Program Made On: 14-09-2016       Updation of work program on: 28-06-2017      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.17-October-201541.73  lakhs
2.09-November-201517.73  lakhs
3.04-January-201654.75  lakhs
4.01-February-201686.52  lakhs
5.19-March-201666.13  lakhs
6.30-April-2016143.04  lakhs
7.22-May-2016100.86  lakhs
8.30-May-2016146.91  lakhs
9.24-June-201691.04  lakhs
10.28-June-201665.04  lakhs
11.29-June-201633.20  lakhs
12.25-July-201674.33  lakhs
13.30-July-201695.07  lakhs
14.31-August-201640.84  lakhs
15.15-September-201614.30  lakhs
16.25-October-2016242.22  lakhs
17.26-October-2016139.15  lakhs
18.30-November-2016184.11  lakhs
19.06-January-2017180.65  lakhs
20.12-January-2017116.66  lakhs
21.28-February-2017106.93  lakhs
22.09-March-201746.21  lakhs
23.20-April-2017103.92  lakhs
24.03-May-201786.88  lakhs
25.17-May-201755.13  lakhs
26.30-May-201726.44  lakhs
27.07-June-201795.85  lakhs
28.19-June-2017117.73  lakhs
29.31-August-201748.23  lakhs
30.16-October-2017177.35  lakhs
Total 2798.95  lakhs
% Payment 85.71 %
Advance Amount:  421.58  lakhs        Recovered Amount:  265.90  lakhs        Balance to be Recovered  155.68  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): workmen Insurance
Environment & Social Compliances(Sub Project level):
Lakshman jhoola Rathuwadhaab Dhumakot Motor road(5505) Land Owner Consent
Detailed report of this Package
Quality
No. of Test Required : 1551     No. of Test Done : 1600      No. of Test Passed : 1600      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 84
Number of Notice(s) issued: 79

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-07-2017Ch 106.450Tree plantation work in progressAlok JainAEUEAP R&B and CA Pauri See Pic
2.03-05-2017Ch 110.100Box culvert bridge in progressAlok JainAEUEAP R&B and CA Pauri See Pic
3.18-04-2017Ch 110.100Box culvert bridge in progressAlok JainAEUEAP R&B and CA Pauri See Pic
4.30-03-2017Km 98Sdbc work checking by CE sirAlok JainAEUEAP R&B and CA Pauri See Pic
5.29-03-2017Km 103Sdbc checking by CE 1 Pauri sirAlok JainAEUEAP R&B and CA Pauri See Pic
6.29-03-2017Ch 110.100Box culvert bridge site visit by CE 1 PauriAlok JainAEUEAP R&B and CA Pauri See Pic
7.29-03-2017Ch 110.100Box culvert bridge in progressAlok JainAEUEAP R&B and CA Pauri See Pic
8.17-03-2017Ch 110.100Box culvert bridge in progressAlok JainAEUEAP R&B and CA Pauri See Pic
9.17-03-2017Ch 110.100Box culvert bridge in progressAlok JainAEUEAP R&B and CA Pauri See Pic
10.08-03-2017Ch 110.100Site inspection by SE sir at bridgeAlok JainAEUEAP R&B and CA Pauri See Pic
11.08-03-2017Ch 62.500SE sir site inspectionAlok JainAEUEAP R&B and CA Pauri See Pic
12.08-03-2017Ch 51.600SE sir site visitAlok JainAEUEAP R&B and CA Pauri See Pic
13.08-03-2017Ch 41.995Thickness checking by SE SirAlok JainAEUEAP R&B and CA Pauri See Pic
14.08-03-2017Ch 25.750Thickness checking by SE sirAlok JainAEUEAP R&B and CA Pauri See Pic
15.08-03-2017Ch 25.750SDBC & BM work checking by SE SirAlok JainAEUEAP R&B and CA Pauri See Pic
16.08-03-2017Ch 19.050SDBC Thickness checking by SE sirAlok JainAEUEAP R&B and CA Pauri See Pic
17.08-03-2017Ch 18.005SDBC thickness by SE SirAlok JainAEUEAP R&B and CA Pauri See Pic
18.08-03-2017Ch 18.005SDBC checking by SE SirAlok JainAEUEAP R&B and CA Pauri See Pic
19.08-03-2017Ch 110.100 box culvert bridge near Hanumanti villageJoint Inspection for Reinforcement checkingAlok JainAEUEAP R&B and CA Pauri See Pic
20.08-03-2017Ch 110.100 box culvert bridge near HanumantiReinforcement work in bridge checkingAlok JainAEUEAP R&B and CA Pauri See Pic