Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C-70 Agreement signed
Project: UEAP-RB Package No.: 1074 Package Name: UEAP/PWD/C-70 Sanction Cost: 1077.00  lakhs
District: Multiple District Block: Sult Constituency: Salt Circle:
DEA: DEA UEAP Nainital DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5506   Marchula-Saraikhet-Baijro-Pokhra Satpuli-Pauri (Pokhra Baijro Division) (29.000 KM.) (completed)
Procurement:
Package No.: 1074        Package Name: UEAP/PWD/C-70        Tender Date: 06-01-2015        Current Status: Agreement signed        Achieved on Date: 06-05-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C-70        Contractor Name: Woodhill Infrastructure Ltd       
Start Date: 15-05-2015        Intended Completion Date: 14-11-2016       
Total Bond Cost: 93815906 (938.16 lakhs)        Variation Cost: 13881582.20 (138.82 lakhs)     Hence Total Bond Cost is   107697488.2 (1076.97 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 6098040 for 130 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.95 KM1.700.45 KM0.45 KM0.161.70
2.R/Wall, B/ Wall Type Protection works490.90 m47.98398.00 m398.00 m4.4647.98
3.G-21.80 KM10.591.64 KM1.64 KM0.9910.59
4.G-32.89 KM22.435.38 KM5.38 KM2.0922.43
5.BM i/c Prime Coat, Tack Coat27.75 KM367.0428.50 KM28.50 KM34.12367.04
6.SDBC i/c Tackcoat31.97 KM401.2631.00 KM31.00 KM37.3401.26
7.Cause Way3.00 No13.922.00 No2.00 No1.2913.92
8.Culverts/Scupper 3.00 No10.042.00 No2.00 No0.9310.04
9.longitudinal Drain23942.40 m26.898040.00 m8040.00 m2.526.89
10.Crash Barrier2276.00 m68.28529.00 m529.00 m6.3568.28
11.Parapet227.00 No9.46139.00 No139.00 No0.889.46
12.Road Furniture1980.00 No84.011980.00 No1980.00 No7.8184.01
13.Other Allied Works & Finishing Work 2.00 Job12.042.00 Job2.00 Job1.1212.04
Total Amount: 1075.64 100   1075.64
Remarks: No Remarks       Work Program Made On: 19-08-2015       Updation of work program on: 27-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.13-October-201528.80  lakhs
2.09-November-201516.81  lakhs
3.30-January-201634.42  lakhs
4.19-March-201666.51  lakhs
5.31-March-2016110.57  lakhs
6.29-April-2016128.15  lakhs
7.27-May-2016237.51  lakhs
8.03-June-2016128.94  lakhs
9.02-July-2016148.54  lakhs
10.28-September-201699.33  lakhs
11.28-November-201642.69  lakhs
12.20-June-201733.38  lakhs
Total 1075.65  lakhs
% Payment 99.88 %
Advance Amount:  93.00  lakhs        Recovered Amount:  93.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 566     No. of Test Done : 566      No. of Test Passed : 566      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 29
Number of Notice(s) issued: 73

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.29-11-2016Chainage 47+080SE sir final inspection of roadRajiv GururaniEEUEAP R&B Nainital See Pic
2.29-11-2016Chainage 48+450Road side tree guardRajiv GururaniEEUEAP R&B Nainital See Pic
3.24-11-2016Chainage 69+630Inspection of Road by SE E sirRajiv GururaniEEUEAP R&B Nainital See Pic
4.02-11-201651+200Road surfaceLalit TiwariAEDEA ADB Nainital See Pic
5.02-11-201664+120Road AppearanceLalit TiwariAEDEA ADB Nainital See Pic
6.02-11-201657+223Existing old Culvert Damaged in Rain and Construction of New Culvert start for opening Communication.Lalit TiwariAEDEA ADB Nainital See Pic
7.02-11-201650+793Road AppearanceLalit TiwariAEDEA ADB Nainital See Pic
8.02-11-2016Near PWD Rest HouseInspection of Road by SDM SaltLalit TiwariAEDEA ADB Nainital See Pic
9.01-09-201651.600Crash barrier & Thermoplastic compoundRajendra Prasad SatiJEUEAP R&B Nainital See Pic
10.01-09-201668.900Near BajwardRajendra Prasad SatiJEUEAP R&B Nainital See Pic
11.01-09-2016kathpatiya villageKm 47.000Rajendra Prasad SatiJEUEAP R&B Nainital See Pic
12.14-07-2016Chainage 50+740Road surface after completionRajiv GururaniEEUEAP R&B Nainital See Pic
13.14-07-2016Chainage 51+200Road after completionRajiv GururaniEEUEAP R&B Nainital See Pic
14.13-05-201656+200SDM visit and resolved public issue with PIU staff and DSC staff C-70 Marchula sarikhet Motor RoadLalit TiwariAEDEA ADB Nainital See Pic
15.23-02-201647+000Parapet ConstructionLalit TiwariAEDEA ADB Nainital See Pic
16.21-02-2016Chainage 49+100Road side kuccha drain excavated before Bitumenous workRajiv GururaniEEUEAP R&B Nainital See Pic
17.21-02-2016Plant site inJhimaar at chainage 31+800 of Marchula Jhimaar Saraikhet motor roadHMP site for Marchula Saraikhet roadRajiv GururaniEEUEAP R&B Nainital See Pic
18.20-02-201664+180Construction of parapet wallsLalit TiwariAEDEA ADB Nainital See Pic
19.07-11-2015Km 61+200B/wall Excavations in progress package C 70O P SinghunknownUEAP R&B Pauri See Pic
20.26-10-2015Km 52+480Plum concrete in progress package C 70O P SinghunknownUEAP R&B Pauri See Pic