UEAP/PWD/C-70
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1074 |
Package Name: |
UEAP/PWD/C-70 |
Sanction Cost: |
1077.00 lakhs |
District: |
Multiple District |
Block: |
Sult |
Constituency: |
Salt |
Circle: |
|
DEA: |
DEA UEAP Nainital |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5506 Marchula-Saraikhet-Baijro-Pokhra Satpuli-Pauri (Pokhra Baijro Division) (29.000 KM.) (completed) |
|
Procurement: |
Package No.: 1074
Package Name: UEAP/PWD/C-70
Tender Date: 06-01-2015
Current Status: Agreement signed
Achieved on Date: 06-05-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C-70
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 15-05-2015
Intended Completion Date: 14-11-2016
|
Total Bond Cost: 93815906 (938.16 lakhs)
Variation Cost: 13881582.20 (138.82 lakhs) Hence Total Bond Cost is 107697488.2 (1076.97 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 6098040 for 130 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.95 KM | 1.70 | 0.45 KM | 0.45 KM | 0.16 | 1.70 | 2. | R/Wall, B/ Wall Type Protection works | 490.90 m | 47.98 | 398.00 m | 398.00 m | 4.46 | 47.98 | 3. | G-2 | 1.80 KM | 10.59 | 1.64 KM | 1.64 KM | 0.99 | 10.59 | 4. | G-3 | 2.89 KM | 22.43 | 5.38 KM | 5.38 KM | 2.09 | 22.43 | 5. | BM i/c Prime Coat, Tack Coat | 27.75 KM | 367.04 | 28.50 KM | 28.50 KM | 34.12 | 367.04 | 6. | SDBC i/c Tackcoat | 31.97 KM | 401.26 | 31.00 KM | 31.00 KM | 37.3 | 401.26 | 7. | Cause Way | 3.00 No | 13.92 | 2.00 No | 2.00 No | 1.29 | 13.92 | 8. | Culverts/Scupper | 3.00 No | 10.04 | 2.00 No | 2.00 No | 0.93 | 10.04 | 9. | longitudinal Drain | 23942.40 m | 26.89 | 8040.00 m | 8040.00 m | 2.5 | 26.89 | 10. | Crash Barrier | 2276.00 m | 68.28 | 529.00 m | 529.00 m | 6.35 | 68.28 | 11. | Parapet | 227.00 No | 9.46 | 139.00 No | 139.00 No | 0.88 | 9.46 | 12. | Road Furniture | 1980.00 No | 84.01 | 1980.00 No | 1980.00 No | 7.81 | 84.01 | 13. | Other Allied Works & Finishing Work | 2.00 Job | 12.04 | 2.00 Job | 2.00 Job | 1.12 | 12.04 |
Total Amount: |
1075.64 |
|
100 |
1075.64 |
|
Remarks:
No Remarks
Work Program Made On:
19-08-2015
Updation of work program on:
27-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-October-2015 | 28.80 lakhs |
2. | 09-November-2015 | 16.81 lakhs |
3. | 30-January-2016 | 34.42 lakhs |
4. | 19-March-2016 | 66.51 lakhs |
5. | 31-March-2016 | 110.57 lakhs |
6. | 29-April-2016 | 128.15 lakhs |
7. | 27-May-2016 | 237.51 lakhs |
8. | 03-June-2016 | 128.94 lakhs |
9. | 02-July-2016 | 148.54 lakhs |
10. | 28-September-2016 | 99.33 lakhs |
11. | 28-November-2016 | 42.69 lakhs |
12. | 20-June-2017 | 33.38 lakhs |
Total |
1075.65 lakhs |
% Payment |
99.88 % |
|
Advance Amount: 93.00 lakhs
Recovered Amount: 93.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 29 |
Number of Notice(s) issued: 73 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 29-11-2016 | Chainage 47+080 | SE sir final inspection of road | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
2. | 29-11-2016 | Chainage 48+450 | Road side tree guard | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
3. | 24-11-2016 | Chainage 69+630 | Inspection of Road by SE E sir | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
4. | 02-11-2016 | 51+200 | Road surface | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
5. | 02-11-2016 | 64+120 | Road Appearance | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
6. | 02-11-2016 | 57+223 | Existing old Culvert Damaged in Rain and Construction of New Culvert start for opening Communication. | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
7. | 02-11-2016 | 50+793 | Road Appearance | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
8. | 02-11-2016 | Near PWD Rest House | Inspection of Road by SDM Salt | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
9. | 01-09-2016 | 51.600 | Crash barrier & Thermoplastic compound | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
10. | 01-09-2016 | 68.900 | Near Bajward | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
11. | 01-09-2016 | kathpatiya village | Km 47.000 | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
12. | 14-07-2016 | Chainage 50+740 | Road surface after completion | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
13. | 14-07-2016 | Chainage 51+200 | Road after completion | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
14. | 13-05-2016 | 56+200 | SDM visit and resolved public issue with PIU staff and DSC staff C-70 Marchula sarikhet Motor Road | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
15. | 23-02-2016 | 47+000 | Parapet Construction | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
16. | 21-02-2016 | Chainage 49+100 | Road side kuccha drain excavated before Bitumenous work | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
17. | 21-02-2016 | Plant site inJhimaar at chainage 31+800 of Marchula Jhimaar Saraikhet motor road | HMP site for Marchula Saraikhet road | Rajiv Gururani | EE | UEAP R&B Nainital | See Pic |
18. | 20-02-2016 | 64+180 | Construction of parapet walls | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
19. | 07-11-2015 | Km 61+200 | B/wall Excavations in progress package C 70 | O P Singh | unknown | UEAP R&B Pauri | See Pic |
20. | 26-10-2015 | Km 52+480 | Plum concrete in progress package C 70 | O P Singh | unknown | UEAP R&B Pauri | See Pic |
|
|