Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C68 Agreement signed
Project: UEAP-RB Package No.: 1072 Package Name: UEAP/PWD/C68 Sanction Cost: 898.00  lakhs
District: Tehri Block: Pratapnagar Constituency: Pratapnagar Circle:
DEA: DEA UEAP Tehri DSC: DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  5333   Bhaldina-Lambgaon Motor Road (16.000 KM.) (completed)
Procurement:
Package No.: 1072        Package Name:  UEAP/PWD/C68        Tender Date: 16-10-2014        Current Status: Agreement signed        Achieved on Date: 13-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C68        Contractor Name: ESPAN Infrastructure Ltd       
Start Date: 05-03-2015        Intended Completion Date: 04-09-2016       
Total Bond Cost: 76631713 (766.32 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 7011828 for +183 days        LD Analysis for Milestone2: calculated LD is Rs 4904448 for 128 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence2.10 KM6.572.10 KM2.10 KM1.016.57
2.R/Wall, B/ Wall Type Protection works1115.00 m146.771115.00 m1115.00 m22.5146.77
3.G-26.28 KM43.276.28 KM6.28 KM6.6343.27
4.G-36.28 KM44.156.28 KM6.28 KM6.7744.15
5.BM i/c Prime Coat, Tack Coat8.75 KM212.568.75 KM8.75 KM32.58212.56
6.SDBC i/c Tackcoat17.02 KM137.2117.02 KM17.02 KM21.03137.21
7.Cause Way1.00 No7.691.00 No1.00 No1.187.69
8.Crash Barrier500.00 m16.00500.00 m500.00 m2.4516.00
9.Parapet638.00 No28.37638.00 No638.00 No4.3528.37
10.Road Furniture500.00 No9.78500.00 No500.00 No1.59.78
Total Amount: 652.37 100   652.37
Remarks: No Remarks       Work Program Made On: 06-08-2015       Updation of work program on: 11-09-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.24-March-20150.16  lakhs
2.20-June-201514.36  lakhs
3.26-August-201520.68  lakhs
4.08-October-201537.37  lakhs
5.09-February-201618.92  lakhs
6.29-March-201625.64  lakhs
7.02-June-201625.61  lakhs
8.24-June-2016172.07  lakhs
9.12-July-201671.85  lakhs
10.06-September-201634.62  lakhs
11.28-March-2017148.38  lakhs
12.29-March-2017168.33  lakhs
13.04-May-201735.83  lakhs
14.29-July-201726.19  lakhs
15.29-September-201730.92  lakhs
Total 830.93  lakhs
% Payment 108.43 %
Advance Amount:  152.22  lakhs        Recovered Amount:  152.22  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 904     No. of Test Done : 996      No. of Test Passed : 904      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 2
Number of Notice(s) issued: 68

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-04-201713+600Core cuttingRoshan Singh RanaJEUEAP R&B Tehri See Pic
2.18-03-20179+800Cross barier inspectionRoshan Singh RanaJEUEAP R&B Tehri See Pic