UEAP/PWD/C68
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1072 |
Package Name: |
UEAP/PWD/C68 |
Sanction Cost: |
898.00 lakhs |
District: |
Tehri |
Block: |
Pratapnagar |
Constituency: |
Pratapnagar |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
|
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5333 Bhaldina-Lambgaon Motor Road (16.000 KM.) (completed) |
|
Procurement: |
Package No.: 1072
Package Name:  UEAP/PWD/C68
Tender Date: 16-10-2014
Current Status: Agreement signed
Achieved on Date: 13-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C68
Contractor Name: ESPAN Infrastructure Ltd
|
Start Date: 05-03-2015
Intended Completion Date: 04-09-2016
|
Total Bond Cost: 76631713 (766.32 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 7011828 for +183 days
LD Analysis for Milestone2: calculated LD is Rs 4904448 for 128 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 2.10 KM | 6.57 | 2.10 KM | 2.10 KM | 1.01 | 6.57 | 2. | R/Wall, B/ Wall Type Protection works | 1115.00 m | 146.77 | 1115.00 m | 1115.00 m | 22.5 | 146.77 | 3. | G-2 | 6.28 KM | 43.27 | 6.28 KM | 6.28 KM | 6.63 | 43.27 | 4. | G-3 | 6.28 KM | 44.15 | 6.28 KM | 6.28 KM | 6.77 | 44.15 | 5. | BM i/c Prime Coat, Tack Coat | 8.75 KM | 212.56 | 8.75 KM | 8.75 KM | 32.58 | 212.56 | 6. | SDBC i/c Tackcoat | 17.02 KM | 137.21 | 17.02 KM | 17.02 KM | 21.03 | 137.21 | 7. | Cause Way | 1.00 No | 7.69 | 1.00 No | 1.00 No | 1.18 | 7.69 | 8. | Crash Barrier | 500.00 m | 16.00 | 500.00 m | 500.00 m | 2.45 | 16.00 | 9. | Parapet | 638.00 No | 28.37 | 638.00 No | 638.00 No | 4.35 | 28.37 | 10. | Road Furniture | 500.00 No | 9.78 | 500.00 No | 500.00 No | 1.5 | 9.78 |
Total Amount: |
652.37 |
|
100 |
652.37 |
|
Remarks:
No Remarks
Work Program Made On:
06-08-2015
Updation of work program on:
11-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 24-March-2015 | 0.16 lakhs |
2. | 20-June-2015 | 14.36 lakhs |
3. | 26-August-2015 | 20.68 lakhs |
4. | 08-October-2015 | 37.37 lakhs |
5. | 09-February-2016 | 18.92 lakhs |
6. | 29-March-2016 | 25.64 lakhs |
7. | 02-June-2016 | 25.61 lakhs |
8. | 24-June-2016 | 172.07 lakhs |
9. | 12-July-2016 | 71.85 lakhs |
10. | 06-September-2016 | 34.62 lakhs |
11. | 28-March-2017 | 148.38 lakhs |
12. | 29-March-2017 | 168.33 lakhs |
13. | 04-May-2017 | 35.83 lakhs |
14. | 29-July-2017 | 26.19 lakhs |
15. | 29-September-2017 | 30.92 lakhs |
Total |
830.93 lakhs |
% Payment |
108.43 % |
|
Advance Amount: 152.22 lakhs
Recovered Amount: 152.22 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 2 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 01-04-2017 | 13+600 | Core cutting | Roshan Singh Rana | JE | UEAP R&B Tehri | See Pic |
2. | 18-03-2017 | 9+800 | Cross barier inspection | Roshan Singh Rana | JE | UEAP R&B Tehri | See Pic |
|
|