UEAP/PWD/C67
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1071 |
Package Name: |
UEAP/PWD/C67 |
Sanction Cost: |
920.00 lakhs |
District: |
Tehri |
Block: |
Chamba |
Constituency: |
Tehri |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
|
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5332 Tyuni-Chakrata-Mussoorie-Chamba-Tehri-Kritinagar Motor Road (24.000 KM.) (in prorgress) |
|
Procurement: |
Package No.: 1071
Package Name:  UEAP/PWD/C67
Tender Date: 16-10-2014
Current Status: Agreement signed
Achieved on Date: 25-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C67
Contractor Name: SS Infratech
|
Start Date: 19-03-2015
Intended Completion Date: 06-09-2016
|
Total Bond Cost: 68577981.3 (685.78 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 6137731 for +179 days
LD Analysis for Milestone2: calculated LD is Rs 6137731 for +179 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 9.54 KM | 6.91 | 9.54 KM | 9.54 KM | 0.91 | 6.91 | 2. | R/Wall, B/ Wall Type Protection works | 900.00 m | 126.76 | 900.00 m | 900.00 m | 16.7 | 126.76 | 3. | GSB/RBI/G-1 | 0.30 KM | 4.37 | 0.30 KM | 0.00 KM | 0 | 0.00 | 4. | G-2 | 0.40 KM | 23.59 | 0.40 KM | 0.32 KM | 2.49 | 18.87 | 5. | G-3 | 0.40 KM | 25.30 | 0.40 KM | 0.32 KM | 2.67 | 20.24 | 6. | BM i/c Prime Coat, Tack Coat | 6.14 KM | 168.53 | 6.14 KM | 6.14 KM | 22.2 | 168.53 | 7. | SDBC i/c Tackcoat | 6.14 KM | 134.92 | 6.14 KM | 6.14 KM | 17.77 | 134.92 | 8. | Cause Way | 5.00 No | 11.84 | 5.00 No | 3.00 No | 0.94 | 7.11 | 9. | longitudinal Drain | 3585.00 m | 67.32 | 3585.00 m | 2115.00 m | 5.23 | 39.71 | 10. | Crash Barrier | 500.00 m | 150.01 | 500.00 m | 500.00 m | 19.76 | 150.01 | 11. | Parapet | 450.00 No | 22.29 | 450.00 No | 370.00 No | 2.41 | 18.33 | 12. | Road Furniture | 1321.00 No | 17.38 | 1321.00 No | 1200.00 No | 2.08 | 15.79 |
Total Amount: |
759.22 |
|
93.15 |
707.18 |
|
Remarks:
No Remarks
Work Program Made On:
04-09-2015
Updation of work program on:
09-01-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-September-2015 | 41.59 lakhs |
2. | 06-November-2015 | 24.17 lakhs |
3. | 05-March-2016 | 34.53 lakhs |
4. | 05-May-2016 | 22.02 lakhs |
5. | 15-June-2016 | 44.69 lakhs |
6. | 29-June-2016 | 34.90 lakhs |
7. | 19-August-2016 | 32.99 lakhs |
8. | 27-October-2016 | 87.72 lakhs |
9. | 09-December-2016 | 40.16 lakhs |
10. | 30-December-2016 | 47.45 lakhs |
11. | 08-March-2017 | 27.61 lakhs |
12. | 21-June-2017 | 28.42 lakhs |
13. | 24-September-2017 | 21.93 lakhs |
Total |
488.18 lakhs |
% Payment |
71.19 % |
|
Advance Amount: 60.00 lakhs
Recovered Amount: 60.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Bill should be issued |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | PUC vehicles | Environment & Social Compliances(Sub Project level): | Tyuni-Chakrata-Mussoorie-Chamba-Tehri-Kritinagar Motor Road(5332) | Sanitation Facility, Query, Borrow pits, DG set |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 27 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-05-2017 | 39+180 | Tharmoplast paint lining work in progres | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
2. | 06-05-2017 | 39+00 | Tharmoplast paint lining | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
3. | 04-05-2017 | 31+900 | Base of causeway | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
4. | 17-03-2017 | 34+600 | Delineator work in progres | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
5. | 21-12-2016 | 28+600 | Laying of BC work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
6. | 21-12-2016 | 28+550 | Spreading tack coat for BC work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
7. | 21-12-2016 | 28+600 | Finishing surface of BC work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
8. | 21-12-2016 | 28+525 | Rolling on BC works | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
9. | 11-11-2016 | 39+200 | Finishing surface of BC works | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
10. | 11-11-2016 | 39+250 | Finishing surface of BC work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
11. | 11-11-2016 | 39+250 | Rolling on BC work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
12. | 10-11-2016 | 39+250 | Laying of BC work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
13. | 10-11-2016 | 38+600 | Finishing surface of BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
14. | 10-11-2016 | 38+600 | Measure thickness & found satisfactory | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
15. | 10-11-2016 | 36+600 | Compaction by Rollar | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
16. | 10-11-2016 | 38+600 | Laying of BM work is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
17. | 10-11-2016 | 38+600 | Tack coat for BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
18. | 07-10-2016 | 36+850 pkg C-67 | Spreading lime on finishing surface of BC work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
19. | 07-10-2016 | 36+850 pkg C-67 | Finishing of the BC work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
20. | 07-10-2016 | 36+850 pkg C-67 | Laying of BC work.. | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
|
|