UEAP/PWD/C66
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1070 |
Package Name: |
UEAP/PWD/C66 |
Sanction Cost: |
1352.00 lakhs |
District: |
Pauri |
Block: |
Birokhal |
Constituency: |
Lansdowne |
Circle: |
|
DEA: |
DEA UEAP Pauri |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5513 Rikhnikhal-Beerokhal ( KM.) (in prorgress) |
|
Procurement: |
Package No.: 1070
Package Name:  UEAP/PWD/C66
Tender Date: 28-10-2014
Current Status: Agreement signed
Achieved on Date: 13-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C66
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 05-03-2015
Intended Completion Date: 04-09-2016
|
Total Bond Cost: 132955020 (1329.55 lakhs)
Variation Cost: -2717809.92 (-27.18 lakhs) Hence Total Bond Cost is 130237210.08 (1302.37 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2260252 for 34 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 2.64 KM | 18.69 | 1.03 KM | 1.03 KM | 1.46 | 18.69 | 2. | R/Wall, B/ Wall Type Protection works | 1227.95 m | 221.12 | 1030.00 m | 1013.00 m | 17.01 | 217.47 | 3. | GSB/RBI/G-1 | 0.46 KM | 5.93 | 0.34 KM | 0.34 KM | 0.46 | 5.93 | 4. | G-2 | 9.58 KM | 15.23 | 1.55 KM | 1.55 KM | 1.19 | 15.23 | 5. | G-3 | 16.36 KM | 32.16 | 2.73 KM | 2.73 KM | 2.52 | 32.16 | 6. | BM i/c Prime Coat, Tack Coat | 19.00 KM | 243.66 | 15.29 KM | 15.29 KM | 19.06 | 243.66 | 7. | SDBC i/c Tackcoat | 30.00 KM | 514.05 | 30.00 KM | 30.00 KM | 40.2 | 514.05 | 8. | Cause Way | 7.00 No | 30.83 | 6.00 No | 6.00 No | 2.41 | 30.83 | 9. | Culverts/Scupper | 5.00 No | 26.26 | 4.00 No | 4.00 No | 2.05 | 26.26 | 10. | longitudinal Drain | 20782.00 m | 7.68 | 29104.00 m | 28105.00 m | 0.58 | 7.42 | 11. | Crash Barrier | 2822.00 m | 88.72 | 1970.00 m | 1964.00 m | 6.92 | 88.45 | 12. | Parapet | 266.00 No | 8.19 | 266.00 No | 0.00 No | 0 | 0.00 | 13. | Road Furniture | 2350.00 No | 66.23 | 1909.00 No | 1759.00 No | 4.77 | 61.02 |
Total Amount: |
1278.75 |
|
98.63 |
1261.17 |
|
Remarks:
No Remarks
Work Program Made On:
26-04-2015
Updation of work program on:
28-06-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 17-June-2015 | 50.45 lakhs |
2. | 19-September-2015 | 89.46 lakhs |
3. | 17-October-2015 | 189.68 lakhs |
4. | 08-November-2015 | 158.41 lakhs |
5. | 15-January-2016 | 152.86 lakhs |
6. | 14-March-2016 | 168.20 lakhs |
7. | 13-May-2016 | 33.06 lakhs |
8. | 30-June-2016 | 203.90 lakhs |
9. | 20-July-2016 | 112.29 lakhs |
10. | 15-September-2016 | 109.03 lakhs |
11. | 07-March-2017 | 49.74 lakhs |
Total |
1317.08 lakhs |
% Payment |
101.13 % |
|
Advance Amount: 254.04 lakhs
Recovered Amount: 254.04 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 1 |
Number of Notice(s) issued: 73 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-03-2017 | Ch 54.515 | Joint site inspectjon with DSC & Contrater | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
|
|