UDPR/PWD/03/RD/096
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
107 |
Package Name: |
UDPR/PWD/03/RD/096 |
Sanction Cost: |
468.26 lakhs |
District: |
Chamoli |
Block: |
Pokhari |
Constituency: |
Badrinath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
3 |
Subproject in this package |
1 1210 Nagnath Link MR (1.650 KM.) (completed) | 2 1269 Semi Bend to Siwai Motor Road (3.000 KM.) (completed) | 3 1273 Sarmola Motor Road (1.400 KM.) (completed) |
|
Procurement: |
Package No.: 107
Package Name: UDPR/PWD/03/RD/096
Tender Date: 23-05-2015
Current Status: Agreement signed
Achieved on Date: 03-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDPR/PWD/03/RD/096
Contractor Name: Hindustan Construction
|
Start Date: 10-09-2015
Intended Completion Date: 15-05-2017
Original End Date: 09-12-2016
|
Total Bond Cost: 38802100 (388.02 lakhs)
Variation Cost: 2853664.64 (28.54 lakhs) Hence Total Bond Cost is 41655764.64 (416.56 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 4.65 KM | 19.91 | 4.65 KM | 4.65 KM | 5.85 | 19.91 | 2. | R/Wall, B/ Wall Type Protection works | 1905.00 m | 57.91 | 1905.00 m | 1905.00 m | 16.61 | 57.91 | 3. | G-2 | 6.05 KM | 46.21 | 6.05 KM | 6.05 KM | 13.69 | 46.21 | 4. | G-3 | 6.05 KM | 36.46 | 6.05 KM | 6.05 KM | 10.61 | 36.46 | 5. | PC/CC i/c Prime Coat, Tack Coat | 6.05 KM | 71.27 | 6.05 KM | 6.05 KM | 20.94 | 71.27 | 6. | Culverts/Scupper | 19.00 No | 56.42 | 19.00 No | 19.00 No | 17.17 | 56.42 | 7. | longitudinal Drain | 5865.00 m | 14.27 | 5865.00 m | 5865.00 m | 4.36 | 14.27 | 8. | Parapet | 175.00 No | 4.86 | 215.00 No | 215.00 No | 1.35 | 4.86 | 9. | Road Furniture | 129.00 No | 2.01 | 129.00 No | 129.00 No | 0.6 | 2.01 | 10. | GSB/RBI/G-1 | 4.40 KM | 26.84 | 4.40 KM | 4.40 KM | 7.29 | 26.84 | 11. | Cause Way | 2.00 No | 3.94 | 5.00 No | 5.00 No | 1.11 | 3.94 | 12. | Crash Barrier | 70.00 m | 1.55 | 80.00 m | 80.00 m | 0.44 | 1.55 |
Total Amount: |
341.65 |
|
100 |
341.65 |
|
Remarks:
No Remarks
Work Program Made On:
25-09-2015
Updation of work program on:
06-06-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-December-2015 | 42.17 lakhs |
2. | 21-March-2016 | 47.57 lakhs |
3. | 03-April-2016 | 0.84 lakhs |
4. | 11-May-2016 | 19.67 lakhs |
5. | 30-June-2016 | 37.75 lakhs |
6. | 31-August-2016 | 12.94 lakhs |
7. | 27-October-2016 | 17.27 lakhs |
8. | 28-November-2016 | 31.33 lakhs |
9. | 31-March-2017 | 22.12 lakhs |
10. | 31-October-2015 | 37.47 lakhs |
11. | 31-January-2016 | 13.71 lakhs |
12. | 04-March-2016 | 13.43 lakhs |
13. | 25-January-2017 | 3.70 lakhs |
14. | 20-May-2017 | 59.77 lakhs |
15. | 14-July-2017 | 26.01 lakhs |
16. | 28-April-2018 | 30.88 lakhs |
Total |
416.63 lakhs |
% Payment |
100.02 % |
|
Advance Amount: 38.00 lakhs
Recovered Amount: 5.70 lakhs
Balance to be Recovered 32.30 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 322 |
Number of Notice(s) issued: 70 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 04-07-2017 | Ch.0+050 | Joint inspection for road handing with Pwd pokhari staff | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
2. | 27-05-2017 | Ch.1+950 | SE Sir site visit | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
3. | 04-05-2017 | Ch. 0+675 | Joint inspection with Pwd staff for Road handing over | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
4. | 16-04-2017 | Ch. 0+075 | OGPC Work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
5. | 14-04-2017 | Ch 0.075 | Thickness checking of G2 G3 | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
6. | 14-04-2017 | Ch 1.350 | Gradation of G3 | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
7. | 14-04-2017 | Ch 1.350 | AIV test of G3 found 20.91percent. Passed | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
8. | 14-04-2017 | Ch 2.100 | Superelevation at hp band found 10 percent | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
9. | 14-04-2017 | Ch 2.350 | Checking of superelevation | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
10. | 14-04-2017 | Ch 2.800 | Thickness checking of pc found 22 mm | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
11. | 06-04-2017 | Ch.0+075 | AIV Test | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
12. | 06-04-2017 | ch.2+420 | Pc thickness checked by Ex. Er. sir found 23 mm | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
13. | 06-04-2017 | ch. 2+320 | Scupper width ch. by Ex. Er. sir found 8.3 m | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
14. | 06-04-2017 | Ch. 0+050 | Road width measured by Ex. Er. sir | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
15. | 06-04-2017 | Ch. 0+075 | Discussion with contractor regarding the label of Wbm & Rcc Scupper | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
16. | 04-04-2017 | Ch. 2+075 | Seal coat Rolling work | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
17. | 28-03-2017 | Ch.2+225 | Patri filling work | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
18. | 24-03-2017 | Ch. 0+275 | Causeway casting work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
19. | 14-02-2017 | ch. 1+350 | AIV Test for G-2 stone found 11.62% | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
20. | 18-01-2017 | Change 2+235 | Coolie wall work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
|
|