Package Profile Report

UDPR/PWD/03/RD/096 Agreement signed
Project: UDRP-RB Package No.: 107 Package Name: UDPR/PWD/03/RD/096 Sanction Cost: 468.26  lakhs
District: Chamoli Block: Pokhari Constituency: Badrinath Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision No.of Sub project : 3
Subproject in this package
1  1210   Nagnath Link MR (1.650 KM.) (completed)
2  1269   Semi Bend to Siwai Motor Road (3.000 KM.) (completed)
3  1273   Sarmola Motor Road (1.400 KM.) (completed)
Procurement:
Package No.: 107        Package Name: UDPR/PWD/03/RD/096        Tender Date: 23-05-2015        Current Status: Agreement signed        Achieved on Date: 03-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDPR/PWD/03/RD/096        Contractor Name: Hindustan Construction       
Start Date: 10-09-2015        Intended Completion Date: 15-05-2017        Original End Date:  09-12-2016
Total Bond Cost: 38802100 (388.02 lakhs)        Variation Cost: 2853664.64 (28.54 lakhs)     Hence Total Bond Cost is   41655764.64 (416.56 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence4.65 KM19.914.65 KM4.65 KM5.8519.91
2.R/Wall, B/ Wall Type Protection works1905.00 m57.911905.00 m1905.00 m16.6157.91
3.G-26.05 KM46.216.05 KM6.05 KM13.6946.21
4.G-36.05 KM36.466.05 KM6.05 KM10.6136.46
5.PC/CC i/c Prime Coat, Tack Coat6.05 KM71.276.05 KM6.05 KM20.9471.27
6.Culverts/Scupper 19.00 No56.4219.00 No19.00 No17.1756.42
7.longitudinal Drain5865.00 m14.275865.00 m5865.00 m4.3614.27
8.Parapet175.00 No4.86215.00 No215.00 No1.354.86
9.Road Furniture129.00 No2.01129.00 No129.00 No0.62.01
10.GSB/RBI/G-14.40 KM26.844.40 KM4.40 KM7.2926.84
11.Cause Way2.00 No3.945.00 No5.00 No1.113.94
12.Crash Barrier70.00 m1.5580.00 m80.00 m0.441.55
Total Amount: 341.65 100   341.65
Remarks: No Remarks       Work Program Made On: 25-09-2015       Updation of work program on: 06-06-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-December-201542.17  lakhs
2.21-March-201647.57  lakhs
3.03-April-20160.84  lakhs
4.11-May-201619.67  lakhs
5.30-June-201637.75  lakhs
6.31-August-201612.94  lakhs
7.27-October-201617.27  lakhs
8.28-November-201631.33  lakhs
9.31-March-201722.12  lakhs
10.31-October-201537.47  lakhs
11.31-January-201613.71  lakhs
12.04-March-201613.43  lakhs
13.25-January-20173.70  lakhs
14.20-May-201759.77  lakhs
15.14-July-201726.01  lakhs
16.28-April-201830.88  lakhs
Total 416.63  lakhs
% Payment 100.02 %
Advance Amount:  38.00  lakhs        Recovered Amount:  5.70  lakhs        Balance to be Recovered  32.30  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 209     No. of Test Done : 233      No. of Test Passed : 213      No. of Test Failed : 20   Test report of this package
Number of Pics Available on Web Repository: 322
Number of Notice(s) issued: 70

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.04-07-2017Ch.0+050Joint inspection for road handing with Pwd pokhari staffSohanbir SinghJEUDRP R&B Chamoli See Pic
2.27-05-2017Ch.1+950SE Sir site visitSohanbir SinghJEUDRP R&B Chamoli See Pic
3.04-05-2017Ch. 0+675Joint inspection with Pwd staff for Road handing overSohanbir SinghJEUDRP R&B Chamoli See Pic
4.16-04-2017Ch. 0+075OGPC Work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
5.14-04-2017Ch 0.075Thickness checking of G2 G3Kirti Vardhan NegiAEDEA WB Gopeshwar See Pic
6.14-04-2017Ch 1.350Gradation of G3Kirti Vardhan NegiAEDEA WB Gopeshwar See Pic
7.14-04-2017Ch 1.350AIV test of G3 found 20.91percent. PassedKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
8.14-04-2017Ch 2.100Superelevation at hp band found 10 percentKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
9.14-04-2017Ch 2.350Checking of superelevationKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
10.14-04-2017Ch 2.800Thickness checking of pc found 22 mmKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
11.06-04-2017Ch.0+075AIV TestSohanbir SinghJEUDRP R&B Chamoli See Pic
12.06-04-2017ch.2+420Pc thickness checked by Ex. Er. sir found 23 mmSohanbir SinghJEUDRP R&B Chamoli See Pic
13.06-04-2017ch. 2+320Scupper width ch. by Ex. Er. sir found 8.3 mSohanbir SinghJEUDRP R&B Chamoli See Pic
14.06-04-2017Ch. 0+050Road width measured by Ex. Er. sirSohanbir SinghJEUDRP R&B Chamoli See Pic
15.06-04-2017Ch. 0+075Discussion with contractor regarding the label of Wbm & Rcc ScupperSohanbir SinghJEUDRP R&B Chamoli See Pic
16.04-04-2017Ch. 2+075Seal coat Rolling workSohanbir SinghJEUDRP R&B Chamoli See Pic
17.28-03-2017Ch.2+225Patri filling workSohanbir SinghJEUDRP R&B Chamoli See Pic
18.24-03-2017Ch. 0+275Causeway casting work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
19.14-02-2017ch. 1+350AIV Test for G-2 stone found 11.62%Sohanbir SinghJEUDRP R&B Chamoli See Pic
20.18-01-2017Change 2+235Coolie wall work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic