Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C65 Agreement signed
Project: UEAP-RB Package No.: 1069 Package Name: UEAP/PWD/C65 Sanction Cost: 1383.00  lakhs
District: Pauri Block: Pabo Constituency: Srinagar Circle:
DEA: DEA UEAP Pauri DSC: DSC Scope: Design and Supervision No.of Sub project : 2
Subproject in this package
1  5511   Khirsu-Musagli-Damdevel Motor Raod ( KM.) (in prorgress)
2  5512   Bhugadi-Develgadh-Chamdhar Motor Road ( KM.) (in prorgress)
Procurement:
Package No.: 1069        Package Name:  UEAP/PWD/C65        Tender Date: 28-10-2014        Current Status: Agreement signed        Achieved on Date: 13-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C65        Contractor Name: Rajshree company       
Start Date: 12-02-2015        Intended Completion Date: 11-08-2016       
Total Bond Cost: 133704695.04 (1337.05 lakhs)        Variation Cost: 1963076.25 (19.63 lakhs)     Hence Total Bond Cost is   135667771.29 (1356.68 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2607228 for 39 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.52 KM9.340.52 KM0.52 KM0.669.34
2.R/Wall, B/ Wall Type Protection works2012.00 m253.091685.00 m1685.00 m18.89253.09
3.G-22.59 KM4.121.03 KM1.03 KM0.314.12
4.G-33.33 KM13.152.38 KM2.38 KM0.9713.15
5.BM i/c Prime Coat, Tack Coat15.12 KM329.8014.97 KM14.97 KM24.91329.80
6.SDBC i/c Tackcoat29.97 KM515.3229.82 KM29.82 KM36.89515.32
7.Cause Way5.00 No31.205.00 No5.00 No2.3431.20
8.Culverts/Scupper 2.00 No11.242.00 No2.00 No0.7611.24
9.longitudinal Drain28080.00 m20.7928110.00 m28080.00 m1.4820.77
10.Crash Barrier2297.00 m74.772310.00 m2297.00 m5.4174.37
11.Parapet240.00 No9.45240.00 No0.00 No00.00
12.Road Furniture2447.00 No54.232405.00 No2291.00 No3.6951.34
13.Other Allied Works & Finishing Work 2.00 Job37.832.00 Job0.00 Job00.00
14.GSB/RBI/G-10.50 KM1.770.49 KM0.49 KM0.141.77
Total Amount: 1366.1 96.45   1315.51
Remarks: No Remarks       Work Program Made On: 25-03-2015       Updation of work program on: 24-07-2017      
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired.
Financial Progress
SNo. Date Payment
1.30-March-20159.61  lakhs
2.23-May-201538.65  lakhs
3.17-June-201535.08  lakhs
4.29-June-201592.89  lakhs
5.04-September-201523.76  lakhs
6.03-October-2015116.83  lakhs
7.17-October-2015235.14  lakhs
8.06-November-2015248.77  lakhs
9.07-December-2015126.92  lakhs
10.15-January-2016131.08  lakhs
11.09-February-201690.98  lakhs
12.29-February-201657.84  lakhs
13.31-March-201659.23  lakhs
14.30-April-201640.82  lakhs
15.10-March-201731.85  lakhs
16.28-June-201617.20  lakhs
Total 1356.65  lakhs
% Payment 100 %
Advance Amount:  174.97  lakhs        Recovered Amount:  174.97  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 256     No. of Test Done : 510      No. of Test Passed : 510      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 1
Number of Notice(s) issued: 68

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-02-2017Km 12R.Wall damage & stone collection for recontructionAlok JainAEUEAP R&B and CA Pauri See Pic