UEAP/PWD/C65
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1069 |
Package Name: |
UEAP/PWD/C65 |
Sanction Cost: |
1383.00 lakhs |
District: |
Pauri |
Block: |
Pabo |
Constituency: |
Srinagar |
Circle: |
|
DEA: |
DEA UEAP Pauri |
DSC: |
|
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 5511 Khirsu-Musagli-Damdevel Motor Raod ( KM.) (in prorgress) | 2 5512 Bhugadi-Develgadh-Chamdhar Motor Road ( KM.) (in prorgress) |
|
Procurement: |
Package No.: 1069
Package Name:  UEAP/PWD/C65
Tender Date: 28-10-2014
Current Status: Agreement signed
Achieved on Date: 13-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C65
Contractor Name: Rajshree company
|
Start Date: 12-02-2015
Intended Completion Date: 11-08-2016
|
Total Bond Cost: 133704695.04 (1337.05 lakhs)
Variation Cost: 1963076.25 (19.63 lakhs) Hence Total Bond Cost is 135667771.29 (1356.68 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2607228 for 39 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.52 KM | 9.34 | 0.52 KM | 0.52 KM | 0.66 | 9.34 | 2. | R/Wall, B/ Wall Type Protection works | 2012.00 m | 253.09 | 1685.00 m | 1685.00 m | 18.89 | 253.09 | 3. | G-2 | 2.59 KM | 4.12 | 1.03 KM | 1.03 KM | 0.31 | 4.12 | 4. | G-3 | 3.33 KM | 13.15 | 2.38 KM | 2.38 KM | 0.97 | 13.15 | 5. | BM i/c Prime Coat, Tack Coat | 15.12 KM | 329.80 | 14.97 KM | 14.97 KM | 24.91 | 329.80 | 6. | SDBC i/c Tackcoat | 29.97 KM | 515.32 | 29.82 KM | 29.82 KM | 36.89 | 515.32 | 7. | Cause Way | 5.00 No | 31.20 | 5.00 No | 5.00 No | 2.34 | 31.20 | 8. | Culverts/Scupper | 2.00 No | 11.24 | 2.00 No | 2.00 No | 0.76 | 11.24 | 9. | longitudinal Drain | 28080.00 m | 20.79 | 28110.00 m | 28080.00 m | 1.48 | 20.77 | 10. | Crash Barrier | 2297.00 m | 74.77 | 2310.00 m | 2297.00 m | 5.41 | 74.37 | 11. | Parapet | 240.00 No | 9.45 | 240.00 No | 0.00 No | 0 | 0.00 | 12. | Road Furniture | 2447.00 No | 54.23 | 2405.00 No | 2291.00 No | 3.69 | 51.34 | 13. | Other Allied Works & Finishing Work | 2.00 Job | 37.83 | 2.00 Job | 0.00 Job | 0 | 0.00 | 14. | GSB/RBI/G-1 | 0.50 KM | 1.77 | 0.49 KM | 0.49 KM | 0.14 | 1.77 |
Total Amount: |
1366.1 |
|
96.45 |
1315.51 |
|
Remarks:
No Remarks
Work Program Made On:
25-03-2015
Updation of work program on:
24-07-2017
|
|
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2015 | 9.61 lakhs |
2. | 23-May-2015 | 38.65 lakhs |
3. | 17-June-2015 | 35.08 lakhs |
4. | 29-June-2015 | 92.89 lakhs |
5. | 04-September-2015 | 23.76 lakhs |
6. | 03-October-2015 | 116.83 lakhs |
7. | 17-October-2015 | 235.14 lakhs |
8. | 06-November-2015 | 248.77 lakhs |
9. | 07-December-2015 | 126.92 lakhs |
10. | 15-January-2016 | 131.08 lakhs |
11. | 09-February-2016 | 90.98 lakhs |
12. | 29-February-2016 | 57.84 lakhs |
13. | 31-March-2016 | 59.23 lakhs |
14. | 30-April-2016 | 40.82 lakhs |
15. | 10-March-2017 | 31.85 lakhs |
16. | 28-June-2016 | 17.20 lakhs |
Total |
1356.65 lakhs |
% Payment |
100 % |
|
Advance Amount: 174.97 lakhs
Recovered Amount: 174.97 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 1 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-02-2017 | Km 12 | R.Wall damage & stone collection for recontruction | Alok Jain | AE | UEAP R&B and CA Pauri | See Pic |
|
|