UEAP/PWD/C62
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1066 |
Package Name: |
UEAP/PWD/C62 |
Sanction Cost: |
1313.00 lakhs |
District: |
Almora |
Block: |
Chaukhutiya |
Constituency: |
Dwarahat |
Circle: |
|
DEA: |
DEA UEAP Almora |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5821 Ganai-Jorasi Motor Road (0.000 KM.) (completed) |
|
Procurement: |
Package No.: 1066
Package Name:  UEAP/PWD/C62
Tender Date: 28-10-2014
Current Status: Agreement signed
Achieved on Date: 12-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C62
Contractor Name: Jagdish Saran
|
Start Date: 06-03-2015
Intended Completion Date: 05-09-2016
|
Total Bond Cost: 107050979.04 (1070.51 lakhs)
Variation Cost: 15534323.84 (155.34 lakhs) Hence Total Bond Cost is 122585302.88 (1225.85 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 5138400 for 96 days
LD Analysis for Milestone2: calculated LD is Rs 1873375 for 35 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 4.00 KM | 4.27 | 4.00 KM | 4.00 KM | 0.35 | 4.27 | 2. | R/Wall, B/ Wall Type Protection works | 950.00 m | 223.39 | 950.00 m | 950.00 m | 18.22 | 223.39 | 3. | GSB/RBI/G-1 | 0.12 KM | 1.84 | 0.12 KM | 0.12 KM | 0.15 | 1.84 | 4. | G-2 | 0.12 KM | 1.31 | 0.12 KM | 0.12 KM | 0.11 | 1.31 | 5. | G-3 | 5.54 KM | 17.64 | 5.54 KM | 5.54 KM | 1.44 | 17.64 | 6. | PC/CC i/c Prime Coat, Tack Coat | 0.90 KM | 9.77 | 0.90 KM | 0.90 KM | 0.8 | 9.77 | 7. | BM i/c Prime Coat, Tack Coat | 18.87 KM | 277.85 | 18.87 KM | 18.87 KM | 22.67 | 277.85 | 8. | SDBC i/c Tackcoat | 23.12 KM | 334.51 | 23.12 KM | 23.12 KM | 27.29 | 334.51 | 9. | Cause Way | 17.00 No | 56.18 | 17.00 No | 17.00 No | 4.58 | 56.18 | 10. | Culverts/Scupper | 16.00 No | 32.11 | 16.00 No | 16.00 No | 2.62 | 32.11 | 11. | longitudinal Drain | 23120.00 m | 56.63 | 23120.00 m | 23120.00 m | 4.62 | 56.63 | 12. | Crash Barrier | 3360.00 m | 50.36 | 3360.00 m | 3360.00 m | 4.11 | 50.36 | 13. | Parapet | 650.00 No | 110.37 | 650.00 No | 650.00 No | 9 | 110.37 | 14. | Road Furniture | 75.00 No | 30.89 | 75.00 No | 75.00 No | 2.52 | 30.89 | 15. | Other Allied Works & Finishing Work | 1.00 Job | 18.74 | 1.00 Job | 1.00 Job | 1.53 | 18.74 |
Total Amount: |
1225.86 |
|
100 |
1225.86 |
|
Remarks:
Work Completed.
Work Program Made On:
24-08-2015
Updation of work program on:
25-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 27-August-2015 | 29.04 lakhs |
2. | 29-September-2015 | 32.06 lakhs |
3. | 29-October-2015 | 30.55 lakhs |
4. | 30-November-2015 | 105.47 lakhs |
5. | 30-January-2016 | 107.63 lakhs |
6. | 29-February-2016 | 70.92 lakhs |
7. | 26-March-2016 | 45.61 lakhs |
8. | 30-April-2016 | 264.00 lakhs |
9. | 01-June-2016 | 169.88 lakhs |
10. | 10-June-2016 | 190.47 lakhs |
11. | 09-August-2016 | 64.71 lakhs |
12. | 25-October-2016 | 25.35 lakhs |
13. | 25-November-2016 | 11.24 lakhs |
14. | 20-June-2017 | 78.93 lakhs |
Total |
1225.86 lakhs |
% Payment |
100 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 92 |
Number of Notice(s) issued: 63 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 01-06-2016 | Chainage- 0+200 | BM work in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
2. | 29-05-2016 | Chainage 4.550 | BM work | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
3. | 22-05-2016 | Chainage-12.720 | BC Work | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
4. | 22-05-2016 | Chainage-12.895 | BC surface after compaction | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
5. | 22-05-2016 | Chainage12.850 | Rolling of BC surface | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
6. | 22-05-2016 | Chainage-12.850 | BC work is in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
7. | 20-05-2016 | Chainage-12.00 | Rolling of BM work | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
8. | 19-05-2016 | 12.860 | BM laying in progress | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
9. | 19-05-2016 | Ch 12.800 | B M laying in progress | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
10. | 16-05-2016 | Ch 14.425 | E E sir visit | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
11. | 16-05-2016 | Ch 14.300 | E.E sir visit at B C laying site | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
12. | 16-05-2016 | Ch 14.400 | Ch 14.400 | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
13. | 16-05-2016 | Ch 14.450 | BC laying in progress | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
14. | 16-05-2016 | Ch 4.550 | Plum massonary in progress | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
15. | 16-05-2016 | At plant | Aggregates grading test | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
16. | 16-05-2016 | At plant | Bitumin extraction test | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
17. | 16-05-2016 | At plant | B C PRODUCTION IN PROGRESS | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
18. | 09-05-2016 | Ch 16.400 | E.E. sir visit | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
19. | 09-05-2016 | Ch 16.500 | B C laying in progress | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
20. | 09-05-2016 | Ch 16.600 | B C LAYING IN PROGRESS | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
|
|