Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C62 Agreement signed
Project: UEAP-RB Package No.: 1066 Package Name: UEAP/PWD/C62 Sanction Cost: 1313.00  lakhs
District: Almora Block: Chaukhutiya Constituency: Dwarahat Circle:
DEA: DEA UEAP Almora DSC: CCEE Group India Pvt.Ltd DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  5821   Ganai-Jorasi Motor Road (0.000 KM.) (completed)
Procurement:
Package No.: 1066        Package Name:  UEAP/PWD/C62        Tender Date: 28-10-2014        Current Status: Agreement signed        Achieved on Date: 12-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C62        Contractor Name: Jagdish Saran       
Start Date: 06-03-2015        Intended Completion Date: 05-09-2016       
Total Bond Cost: 107050979.04 (1070.51 lakhs)        Variation Cost: 15534323.84 (155.34 lakhs)     Hence Total Bond Cost is   122585302.88 (1225.85 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 5138400 for 96 days        LD Analysis for Milestone2: calculated LD is Rs 1873375 for 35 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence4.00 KM4.274.00 KM4.00 KM0.354.27
2.R/Wall, B/ Wall Type Protection works950.00 m223.39950.00 m950.00 m18.22223.39
3.GSB/RBI/G-10.12 KM1.840.12 KM0.12 KM0.151.84
4.G-20.12 KM1.310.12 KM0.12 KM0.111.31
5.G-35.54 KM17.645.54 KM5.54 KM1.4417.64
6.PC/CC i/c Prime Coat, Tack Coat0.90 KM9.770.90 KM0.90 KM0.89.77
7.BM i/c Prime Coat, Tack Coat18.87 KM277.8518.87 KM18.87 KM22.67277.85
8.SDBC i/c Tackcoat23.12 KM334.5123.12 KM23.12 KM27.29334.51
9.Cause Way17.00 No56.1817.00 No17.00 No4.5856.18
10.Culverts/Scupper 16.00 No32.1116.00 No16.00 No2.6232.11
11.longitudinal Drain23120.00 m56.6323120.00 m23120.00 m4.6256.63
12.Crash Barrier3360.00 m50.363360.00 m3360.00 m4.1150.36
13.Parapet650.00 No110.37650.00 No650.00 No9110.37
14.Road Furniture75.00 No30.8975.00 No75.00 No2.5230.89
15.Other Allied Works & Finishing Work 1.00 Job18.741.00 Job1.00 Job1.5318.74
Total Amount: 1225.86 100   1225.86
Remarks: Work Completed.       Work Program Made On: 24-08-2015       Updation of work program on: 25-09-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.27-August-201529.04  lakhs
2.29-September-201532.06  lakhs
3.29-October-201530.55  lakhs
4.30-November-2015105.47  lakhs
5.30-January-2016107.63  lakhs
6.29-February-201670.92  lakhs
7.26-March-201645.61  lakhs
8.30-April-2016264.00  lakhs
9.01-June-2016169.88  lakhs
10.10-June-2016190.47  lakhs
11.09-August-201664.71  lakhs
12.25-October-201625.35  lakhs
13.25-November-201611.24  lakhs
14.20-June-201778.93  lakhs
Total 1225.86  lakhs
% Payment 100 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 804     No. of Test Done : 847      No. of Test Passed : 802      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 92
Number of Notice(s) issued: 63

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-06-2016Chainage- 0+200BM work in progressKuldeep GiriAEUEAP R&B Almora See Pic
2.29-05-2016Chainage 4.550BM workKuldeep GiriAEUEAP R&B Almora See Pic
3.22-05-2016Chainage-12.720BC WorkKuldeep GiriAEUEAP R&B Almora See Pic
4.22-05-2016Chainage-12.895BC surface after compactionKuldeep GiriAEUEAP R&B Almora See Pic
5.22-05-2016Chainage12.850Rolling of BC surfaceKuldeep GiriAEUEAP R&B Almora See Pic
6.22-05-2016Chainage-12.850BC work is in progressKuldeep GiriAEUEAP R&B Almora See Pic
7.20-05-2016Chainage-12.00Rolling of BM workKuldeep GiriAEUEAP R&B Almora See Pic
8.19-05-201612.860BM laying in progressChetan BhattJEUEAP R&B Almora See Pic
9.19-05-2016Ch 12.800B M laying in progressChetan BhattJEUEAP R&B Almora See Pic
10.16-05-2016Ch 14.425E E sir visitChetan BhattJEUEAP R&B Almora See Pic
11.16-05-2016Ch 14.300E.E sir visit at B C laying siteChetan BhattJEUEAP R&B Almora See Pic
12.16-05-2016Ch 14.400Ch 14.400Chetan BhattJEUEAP R&B Almora See Pic
13.16-05-2016Ch 14.450BC laying in progressChetan BhattJEUEAP R&B Almora See Pic
14.16-05-2016Ch 4.550Plum massonary in progressChetan BhattJEUEAP R&B Almora See Pic
15.16-05-2016At plantAggregates grading testChetan BhattJEUEAP R&B Almora See Pic
16.16-05-2016At plantBitumin extraction testChetan BhattJEUEAP R&B Almora See Pic
17.16-05-2016At plantB C PRODUCTION IN PROGRESSChetan BhattJEUEAP R&B Almora See Pic
18.09-05-2016Ch 16.400E.E. sir visitChetan BhattJEUEAP R&B Almora See Pic
19.09-05-2016Ch 16.500B C laying in progressChetan BhattJEUEAP R&B Almora See Pic
20.09-05-2016Ch 16.600B C LAYING IN PROGRESSChetan BhattJEUEAP R&B Almora See Pic