UEAP/PWD/C61
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1065 |
Package Name: |
UEAP/PWD/C61 |
Sanction Cost: |
1469.00 lakhs |
District: |
Almora |
Block: |
Bhikiyasain |
Constituency: |
Dwarahat |
Circle: |
|
DEA: |
DEA UEAP Almora |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 5819 Bhatrojkhan Bhikiyasain Chokhutiya Motor road ( KM.) (completed) | 2 5820 Bhikiyasain Deghat Bungidhar Bachuwaban Mehalchori Chaukhutiya Motor Road ( KM.) (completed) |
|
Procurement: |
Package No.: 1065
Package Name:  UEAP/PWD/C61
Tender Date: 28-10-2014
Current Status: Agreement signed
Achieved on Date: 12-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C61
Contractor Name: Jagdish Saran
|
Start Date: 07-03-2015
Intended Completion Date: 21-12-2016
Original End Date: 06-09-2016
|
Total Bond Cost: 119197725.82 (1191.98 lakhs)
Variation Cost: 23156147.76 (231.56 lakhs) Hence Total Bond Cost is 142353873.58 (1423.54 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 6377093 for 107 days
LD Analysis for Milestone2: calculated LD is Rs 5542707 for 93 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 10.00 KM | 17.91 | 10.00 KM | 10.00 KM | 1.33 | 17.91 | 2. | R/Wall, B/ Wall Type Protection works | 2600.00 m | 339.63 | 2600.00 m | 2600.00 m | 29.24 | 339.63 | 3. | G-2 | 4.00 KM | 14.69 | 4.00 KM | 4.00 KM | 0.68 | 14.69 | 4. | G-3 | 11.00 KM | 32.34 | 11.00 KM | 11.00 KM | 2.5 | 32.34 | 5. | PC/CC i/c Prime Coat, Tack Coat | 7.83 KM | 124.53 | 7.23 KM | 7.23 KM | 18.8 | 124.53 | 6. | BM i/c Prime Coat, Tack Coat | 20.00 KM | 266.39 | 20.00 KM | 20.00 KM | 12.27 | 266.39 | 7. | SDBC i/c Tackcoat | 20.00 KM | 281.56 | 20.00 KM | 20.00 KM | 12.97 | 281.56 | 8. | Cause Way | 6.00 No | 12.10 | 6.00 No | 6.00 No | 1.33 | 12.10 | 9. | Culverts/Scupper | 22.00 No | 50.07 | 22.00 No | 22.00 No | 2.97 | 50.07 | 10. | longitudinal Drain | 27700.00 m | 76.31 | 27700.00 m | 27700.00 m | 5.41 | 76.31 | 11. | Crash Barrier | 3771.00 m | 82.30 | 4720.00 m | 4720.00 m | 5.04 | 82.30 | 12. | Parapet | 1140.00 No | 35.53 | 1140.00 No | 1140.00 No | 2.05 | 35.53 | 13. | Road Furniture | 222.00 No | 33.31 | 141.00 No | 141.00 No | 2.11 | 33.31 | 14. | Other Allied Works & Finishing Work | 2.00 Job | 36.35 | 2.00 Job | 2.00 Job | 3.29 | 36.35 |
Total Amount: |
1403.02 |
|
100 |
1403.02 |
|
Remarks:
Work Completed.
Work Program Made On:
24-08-2015
Updation of work program on:
25-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-August-2015 | 37.35 lakhs |
2. | 26-October-2015 | 49.54 lakhs |
3. | 30-December-2015 | 102.94 lakhs |
4. | 29-February-2016 | 158.10 lakhs |
5. | 13-April-2016 | 77.80 lakhs |
6. | 30-April-2016 | 25.49 lakhs |
7. | 01-June-2016 | 41.58 lakhs |
8. | 25-June-2016 | 144.32 lakhs |
9. | 04-August-2016 | 76.20 lakhs |
10. | 05-October-2016 | 195.89 lakhs |
11. | 10-October-2016 | 96.82 lakhs |
12. | 25-October-2016 | 133.42 lakhs |
13. | 25-November-2016 | 56.59 lakhs |
14. | 28-February-2017 | 108.74 lakhs |
15. | 25-April-2017 | 10.52 lakhs |
16. | 31-May-2017 | 21.20 lakhs |
17. | 20-June-2017 | 25.13 lakhs |
18. | 30-September-2015 | 16.45 lakhs |
19. | 28-October-2015 | 45.44 lakhs |
Total |
1423.52 lakhs |
% Payment |
100 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 84 |
Number of Notice(s) issued: 64 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 29-11-2016 | Chainage-31+400 | Shoulder protection work | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
2. | 12-11-2016 | Chainage- 40+700 | PC work at deghat bungidhar road | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
3. | 12-11-2016 | Chainage-40+700 | PC work in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
4. | 12-11-2016 | Chainage-41.640 | PC work package C-61deghat bungidhar road | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
5. | 12-11-2016 | Hot mix plant | Bitumen extraction test for BC | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
6. | 20-10-2016 | 42.800 | Bm laying work in progress at pacakge c61 | Pooja Garg | JE | UEAP R&B Almora | See Pic |
7. | 20-10-2016 | Package C61 | Traffic sign board fixing | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
8. | 20-10-2016 | Chainage-39.500 | PC work deghat bungidhar road package-C61 | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
9. | 20-10-2016 | Chainage-39.650 | PC work in progress pacakge C-61 deghat bungidhar road | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
10. | 20-10-2016 | Chainage-42.800 | BM rolling in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
11. | 18-10-2016 | 35.740 | Bm laying work in progress at c61 bhikiyashain masi motor road | Pooja Garg | JE | UEAP R&B Almora | See Pic |
12. | 18-10-2016 | 35.750 | Bm laying work in progress at c61 bhikiyashain masi motor road | Pooja Garg | JE | UEAP R&B Almora | See Pic |
13. | 18-10-2016 | 34.350 | BC work laying in progress at c61 bhikiyashain masi motor road | Pooja Garg | JE | UEAP R&B Almora | See Pic |
14. | 18-10-2016 | 34.350 | BC laying work in progress at c61 bhikiyashain masi motor road | Pooja Garg | JE | UEAP R&B Almora | See Pic |
15. | 18-10-2016 | 33.800 | BC laying work in progress at c61 bhikiyashain masi motor road | Pooja Garg | JE | UEAP R&B Almora | See Pic |
16. | 11-10-2016 | Chainage-39.650 | BC rolling in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
17. | 11-10-2016 | Chainage-39.300 | BC work in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
18. | 11-10-2016 | Chainage-39.200 | BM work in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
19. | 11-10-2016 | Chainage-38+250 | BC rolling in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
20. | 02-10-2016 | Chainage-37.550 | BM work in progress | Kuldeep Giri | AE | UEAP R&B Almora | See Pic |
|
|