UEAP/PWD/C60
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1064 |
Package Name: |
UEAP/PWD/C60 |
Sanction Cost: |
3138.00 lakhs |
District: |
Almora |
Block: |
Hawal Bagh |
Constituency: |
Someshwar |
Circle: |
|
DEA: |
DEA UEAP Almora |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 5817 Kosi-Daulaghat Motor Raod (0.000 KM.) (completed) | 2 5818 Dwarahat-Binta Someshwar Motor Road ( KM.) (completed) |
|
Procurement: |
Package No.: 1064
Package Name:  UEAP/PWD/C60
Tender Date: 28-10-2014
Current Status: Agreement signed
Achieved on Date: 19-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C60
Contractor Name: Shiva Buildtech
|
Start Date: 13-03-2015
Intended Completion Date: 12-09-2016
|
Total Bond Cost: 204735793.42 (2047.36 lakhs)
Variation Cost: 61088958.28 (610.89 lakhs) Hence Total Bond Cost is 265824751.7 (2658.25 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 9315488 for 91 days
LD Analysis for Milestone2: calculated LD is Rs 5732608 for 56 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 9.00 KM | 11.82 | 9.00 KM | 9.00 KM | 0.45 | 11.82 | 2. | R/Wall, B/ Wall Type Protection works | 4000.00 m | 359.08 | 4000.00 m | 4000.00 m | 14.83 | 359.08 | 3. | GSB/RBI/G-1 | 0.05 KM | 0.13 | 0.05 KM | 0.05 KM | 0 | 0.13 | 4. | G-2 | 3.80 KM | 5.08 | 3.80 KM | 3.80 KM | 0.14 | 5.08 | 5. | G-3 | 13.26 KM | 23.14 | 13.26 KM | 13.26 KM | 0.67 | 23.14 | 6. | PC/CC i/c Prime Coat, Tack Coat | 11.90 KM | 8.91 | 11.90 KM | 11.90 KM | 0.24 | 8.91 | 7. | BM i/c Prime Coat, Tack Coat | 41.65 KM | 676.31 | 41.65 KM | 41.65 KM | 23.82 | 676.31 | 8. | SDBC i/c Tackcoat | 47.15 KM | 888.31 | 47.15 KM | 47.15 KM | 34.28 | 888.31 | 9. | Cause Way | 14.00 No | 39.33 | 13.00 No | 13.00 No | 1.51 | 39.33 | 10. | Culverts/Scupper | 38.00 No | 74.57 | 38.00 No | 38.00 No | 2.53 | 74.57 | 11. | longitudinal Drain | 44692.88 m | 148.60 | 48670.00 m | 48670.00 m | 5.76 | 148.60 | 12. | Crash Barrier | 6038.00 m | 204.53 | 3440.93 m | 3440.93 m | 7.51 | 204.53 | 13. | Parapet | 3435.00 No | 146.89 | 2876.00 No | 2876.00 No | 5.47 | 146.89 | 14. | Road Furniture | 353.00 No | 61.23 | 105.00 No | 105.00 No | 2.37 | 61.23 | 15. | Other Allied Works & Finishing Work | 2.00 Job | 10.01 | 2.00 Job | 2.00 Job | 0.42 | 10.01 |
Total Amount: |
2657.94 |
|
100 |
2657.94 |
|
Remarks:
Work Completed.
Work Program Made On:
23-07-2015
Updation of work program on:
20-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 04-July-2015 | 46.56 lakhs |
2. | 30-September-2015 | 49.80 lakhs |
3. | 07-November-2015 | 135.70 lakhs |
4. | 30-November-2015 | 135.45 lakhs |
5. | 30-December-2015 | 102.87 lakhs |
6. | 28-February-2016 | 16.16 lakhs |
7. | 29-February-2016 | 37.61 lakhs |
8. | 26-March-2016 | 224.26 lakhs |
9. | 30-April-2016 | 205.39 lakhs |
10. | 18-May-2016 | 154.76 lakhs |
11. | 30-May-2016 | 149.42 lakhs |
12. | 31-May-2016 | 149.62 lakhs |
13. | 22-June-2016 | 170.20 lakhs |
14. | 14-July-2016 | 126.66 lakhs |
15. | 11-August-2016 | 300.48 lakhs |
16. | 30-September-2016 | 130.36 lakhs |
17. | 26-October-2016 | 128.06 lakhs |
18. | 05-December-2016 | 75.45 lakhs |
19. | 23-February-2017 | 42.89 lakhs |
20. | 28-February-2017 | 170.18 lakhs |
21. | 31-May-2017 | 87.62 lakhs |
22. | 20-June-2017 | 17.76 lakhs |
Total |
2657.26 lakhs |
% Payment |
99.96 % |
|
Advance Amount: 211.14 lakhs
Recovered Amount: 211.14 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 216 |
Number of Notice(s) issued: 70 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-02-2017 | | Parapets ,edge line,BC work completed. | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
2. | 08-02-2017 | | Parapets edge line bc work completed | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
3. | 08-02-2017 | | Parapets work | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
4. | 08-02-2017 | | Crash barrier,edge line ,bc work completed | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
5. | 08-02-2017 | | Bc work completed | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
6. | 08-02-2017 | | Parapets ,edge line ,BC work completed | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
7. | 08-02-2017 | | Egde line ,BC work,signage board 5th km stone work completed | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
8. | 08-02-2017 | | Edge line, BC work, signage board work completed | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
9. | 08-02-2017 | | Edge line BC work parapets signage | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
10. | 08-02-2017 | | Parapets work completed | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
11. | 08-02-2017 | | Parapets edge line BC work.. | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
12. | 08-02-2017 | | Parapets edge line sign board and BC work | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
13. | 08-02-2017 | Starting point | Starting point kosi daulahat road at junction of NH 87E | Vibhor Gupta | AE | UEAP R&B Almora | See Pic |
14. | 09-10-2016 | Ch 20.600 | Edge line work is completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
15. | 09-10-2016 | Ch 13.070 | Core cutting for BM/SDBC work | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
16. | 09-10-2016 | Ch 13.220 | Core cutting for BM/SDBC | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
17. | 09-10-2016 | Ch 12.800 | B/wall work is in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
18. | 09-10-2016 | Ch 13.950 | Kc Drain and shoulder Protection work is completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
19. | 09-10-2016 | 13.850 | Shoulder protection and KC Drain work completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
20. | 09-10-2016 | Ch 14.600 | K.c.drain & soulder protection work is completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
|
|