Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C59 Agreement signed
Project: UEAP-RB Package No.: 1063 Package Name: UEAP/PWD/C59 Sanction Cost: 990.00  lakhs
District: Tehri Block: Jakhanidhar Constituency: Tehri Circle:
DEA: DEA UEAP Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 2
Subproject in this package
1  5330   Tehri-Hindolakhal-Devprayag Motor Road (ic Tipri Roaddhar Motor Road) ( KM.) (in prorgress)
2  5331   Tehri-Hindolakhal-Devprayag Motor Road ( KM.) (in prorgress)
Procurement:
Package No.: 1063        Package Name:  UEAP/PWD/C59        Tender Date: 20-09-2014        Current Status: Agreement signed        Achieved on Date: 13-04-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C59        Contractor Name: Maa Bhagwati Construction company       
Start Date: 19-03-2015        Intended Completion Date: 06-09-2016       
Total Bond Cost: 84181618.77 (841.82 lakhs)        Variation Cost: 8055000.74 (80.55 lakhs)     Hence Total Bond Cost is   92236619.51 (922.37 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 4335373 for 103 days        LD Analysis for Milestone2: calculated LD is Rs 5219284 for +124 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence4.39 KM9.054.39 KM4.39 KM1.399.05
2.R/Wall, B/ Wall Type Protection works3780.00 m80.552910.00 m2910.00 m12.0280.55
3.G-20.50 KM3.360.50 KM0.00 KM00.00
4.G-30.50 KM3.390.23 KM0.03 KM0.422.01
5.BM i/c Prime Coat, Tack Coat5.14 KM127.975.44 KM5.27 KM24.18125.08
6.SDBC i/c Tackcoat5.46 KM97.345.44 KM5.27 KM18.395.04
7.Cause Way12.00 No29.8213.00 No6.00 No1.9611.26
8.longitudinal Drain4420.00 m126.575420.00 m5420.00 m24.25126.57
9.Crash Barrier730.00 m15.70280.45 m280.45 m2.6515.70
10.Parapet550.00 No18.22503.00 No326.00 No2.2911.82
11.Road Furniture2027.00 No23.322027.00 No1712.00 No3.7319.87
12.Other Allied Works & Finishing Work 1.00 Job10.881.00 Job1.00 Job1.5510.88
Total Amount: 546.17 92.76   507.83
Remarks: No Remarks       Work Program Made On: 31-07-2015       Updation of work program on: 03-08-2017      
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired.
Financial Progress
SNo. Date Payment
1.13-October-201561.94  lakhs
2.20-January-201671.88  lakhs
3.17-March-201674.33  lakhs
4.16-June-2016152.91  lakhs
5.05-October-201633.96  lakhs
6.25-November-2016162.52  lakhs
7.10-March-201771.73  lakhs
8.26-May-201738.33  lakhs
9.18-June-201736.11  lakhs
10.19-September-201747.56  lakhs
11.24-September-201755.12  lakhs
Total 806.39  lakhs
% Payment 87.43 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level):
Tehri-Hindolakhal-Devprayag Motor Road (ic Tipri Roaddhar Motor Road)(5330) Sanitation Facility, Query, DG set
Tehri-Hindolakhal-Devprayag Motor Road(5331) Sanitation Facility, Borrow pits, DG set
Detailed report of this Package
Quality
No. of Test Required : 588     No. of Test Done : 613      No. of Test Passed : 588      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 49
Number of Notice(s) issued: 68

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-05-20170+300Parapet walls & Thermoplastic paint& BC surface.Kishan Singh RawatJEUEAP R&B Tehri See Pic
2.10-02-20177+505Drain workKishan Singh RawatJEUEAP R&B Tehri See Pic
3.10-02-20173+750Parapet workKishan Singh RawatJEUEAP R&B Tehri See Pic
4.10-02-201738+40ExacavationKishan Singh RawatJEUEAP R&B Tehri See Pic
5.17-11-201624+450Rolling on BC work is in progressShivendra PrakashAEUEAP- CA Tehri See Pic
6.17-11-201624+450Laying of BC on BM workShivendra PrakashAEUEAP- CA Tehri See Pic
7.17-11-201624+300Finishing of BC surfaceShivendra PrakashAEUEAP- CA Tehri See Pic
8.25-10-201638+450Sprading Tack coat for BM workShivendra PrakashAEUEAP- CA Tehri See Pic
9.25-10-201637+835Laying of BM work is in progressShivendra PrakashAEUEAP- CA Tehri See Pic
10.25-10-201637+825Compaction of BM workShivendra PrakashAEUEAP- CA Tehri See Pic
11.25-10-201637+825Measure thickness of BM & found satisfactoryShivendra PrakashAEUEAP- CA Tehri See Pic
12.25-10-201637+800Laying of BM workShivendra PrakashAEUEAP- CA Tehri See Pic
13.25-10-201632+640Laying of BM work is in progressShivendra PrakashAEUEAP- CA Tehri See Pic
14.25-10-201632+625Compaction of BM work is in progressShivendra PrakashAEUEAP- CA Tehri See Pic
15.25-10-201631+400Tack coat is in progress for BM workShivendra PrakashAEUEAP- CA Tehri See Pic
16.25-10-201631+300Compaction by roller on BM workShivendra PrakashAEUEAP- CA Tehri See Pic
17.25-10-201631+300Measure thickness of BM & found satisfactoryShivendra PrakashAEUEAP- CA Tehri See Pic
18.25-10-201631+300Laying of BM is in progressShivendra PrakashAEUEAP- CA Tehri See Pic
19.25-10-201631+350Tack coat for BM workShivendra PrakashAEUEAP- CA Tehri See Pic
20.25-10-201631+200Compaction by Rollar on BM workShivendra PrakashAEUEAP- CA Tehri See Pic