UEAP/PWD/C59
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1063 |
Package Name: |
UEAP/PWD/C59 |
Sanction Cost: |
990.00 lakhs |
District: |
Tehri |
Block: |
Jakhanidhar |
Constituency: |
Tehri |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 5330 Tehri-Hindolakhal-Devprayag Motor Road (ic Tipri Roaddhar Motor Road) ( KM.) (in prorgress) | 2 5331 Tehri-Hindolakhal-Devprayag Motor Road ( KM.) (in prorgress) |
|
Procurement: |
Package No.: 1063
Package Name:  UEAP/PWD/C59
Tender Date: 20-09-2014
Current Status: Agreement signed
Achieved on Date: 13-04-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C59
Contractor Name: Maa Bhagwati Construction company
|
Start Date: 19-03-2015
Intended Completion Date: 06-09-2016
|
Total Bond Cost: 84181618.77 (841.82 lakhs)
Variation Cost: 8055000.74 (80.55 lakhs) Hence Total Bond Cost is 92236619.51 (922.37 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 4335373 for 103 days
LD Analysis for Milestone2: calculated LD is Rs 5219284 for +124 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 4.39 KM | 9.05 | 4.39 KM | 4.39 KM | 1.39 | 9.05 | 2. | R/Wall, B/ Wall Type Protection works | 3780.00 m | 80.55 | 2910.00 m | 2910.00 m | 12.02 | 80.55 | 3. | G-2 | 0.50 KM | 3.36 | 0.50 KM | 0.00 KM | 0 | 0.00 | 4. | G-3 | 0.50 KM | 3.39 | 0.23 KM | 0.03 KM | 0.42 | 2.01 | 5. | BM i/c Prime Coat, Tack Coat | 5.14 KM | 127.97 | 5.44 KM | 5.27 KM | 24.18 | 125.08 | 6. | SDBC i/c Tackcoat | 5.46 KM | 97.34 | 5.44 KM | 5.27 KM | 18.3 | 95.04 | 7. | Cause Way | 12.00 No | 29.82 | 13.00 No | 6.00 No | 1.96 | 11.26 | 8. | longitudinal Drain | 4420.00 m | 126.57 | 5420.00 m | 5420.00 m | 24.25 | 126.57 | 9. | Crash Barrier | 730.00 m | 15.70 | 280.45 m | 280.45 m | 2.65 | 15.70 | 10. | Parapet | 550.00 No | 18.22 | 503.00 No | 326.00 No | 2.29 | 11.82 | 11. | Road Furniture | 2027.00 No | 23.32 | 2027.00 No | 1712.00 No | 3.73 | 19.87 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 10.88 | 1.00 Job | 1.00 Job | 1.55 | 10.88 |
Total Amount: |
546.17 |
|
92.76 |
507.83 |
|
Remarks:
No Remarks
Work Program Made On:
31-07-2015
Updation of work program on:
03-08-2017
|
|
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 13-October-2015 | 61.94 lakhs |
2. | 20-January-2016 | 71.88 lakhs |
3. | 17-March-2016 | 74.33 lakhs |
4. | 16-June-2016 | 152.91 lakhs |
5. | 05-October-2016 | 33.96 lakhs |
6. | 25-November-2016 | 162.52 lakhs |
7. | 10-March-2017 | 71.73 lakhs |
8. | 26-May-2017 | 38.33 lakhs |
9. | 18-June-2017 | 36.11 lakhs |
10. | 19-September-2017 | 47.56 lakhs |
11. | 24-September-2017 | 55.12 lakhs |
Total |
806.39 lakhs |
% Payment |
87.43 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | PUC vehicles | Environment & Social Compliances(Sub Project level): | Tehri-Hindolakhal-Devprayag Motor Road (ic Tipri Roaddhar Motor Road)(5330) | Sanitation Facility, Query, DG set | Tehri-Hindolakhal-Devprayag Motor Road(5331) | Sanitation Facility, Borrow pits, DG set |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 49 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-05-2017 | 0+300 | Parapet walls & Thermoplastic paint& BC surface. | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
2. | 10-02-2017 | 7+505 | Drain work | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
3. | 10-02-2017 | 3+750 | Parapet work | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
4. | 10-02-2017 | 38+40 | Exacavation | Kishan Singh Rawat | JE | UEAP R&B Tehri | See Pic |
5. | 17-11-2016 | 24+450 | Rolling on BC work is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
6. | 17-11-2016 | 24+450 | Laying of BC on BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
7. | 17-11-2016 | 24+300 | Finishing of BC surface | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
8. | 25-10-2016 | 38+450 | Sprading Tack coat for BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
9. | 25-10-2016 | 37+835 | Laying of BM work is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
10. | 25-10-2016 | 37+825 | Compaction of BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
11. | 25-10-2016 | 37+825 | Measure thickness of BM & found satisfactory | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
12. | 25-10-2016 | 37+800 | Laying of BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
13. | 25-10-2016 | 32+640 | Laying of BM work is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
14. | 25-10-2016 | 32+625 | Compaction of BM work is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
15. | 25-10-2016 | 31+400 | Tack coat is in progress for BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
16. | 25-10-2016 | 31+300 | Compaction by roller on BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
17. | 25-10-2016 | 31+300 | Measure thickness of BM & found satisfactory | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
18. | 25-10-2016 | 31+300 | Laying of BM is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
19. | 25-10-2016 | 31+350 | Tack coat for BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
20. | 25-10-2016 | 31+200 | Compaction by Rollar on BM work | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
|
|