UEAP/PWD/C56
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1060 |
Package Name: |
UEAP/PWD/C56 |
Sanction Cost: |
1095.00 lakhs |
District: |
Tehri |
Block: |
Jaunpur |
Constituency: |
Dhanaulti |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 5323 Raipur-Kaddukhal Motor Road ( KM.) (in prorgress) | 2 5324 Suwakholi-Bhawaan-Sarot chapra-Nagum Motor Raod ( KM.) (completed) |
|
Procurement: |
Package No.: 1060
Package Name:  UEAP/PWD/C56
Tender Date: 20-09-2014
Current Status: Agreement signed
Achieved on Date: 12-01-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C56
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 03-02-2015
Intended Completion Date: 11-07-2016
|
Total Bond Cost: 91997972.9 (919.98 lakhs)
Variation Cost: 12444241.30 (124.44 lakhs) Hence Total Bond Cost is 104442214.2 (1044.42 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1379970 for 30 days
LD Analysis for Milestone2: calculated LD is Rs 3035934 for 66 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 2.63 KM | 9.14 | 2.63 KM | 2.63 KM | 1.01 | 9.14 | 2. | R/Wall, B/ Wall Type Protection works | 2587.00 m | 342.96 | 2587.00 m | 2587.00 m | 38.24 | 342.96 | 3. | G-2 | 0.20 KM | 1.41 | 0.20 KM | 0.10 KM | 0.08 | 0.71 | 4. | G-3 | 0.20 KM | 1.44 | 0.20 KM | 0.10 KM | 0.08 | 0.72 | 5. | BM i/c Prime Coat, Tack Coat | 4.09 KM | 73.80 | 4.09 KM | 4.09 KM | 8.19 | 73.80 | 6. | SDBC i/c Tackcoat | 15.35 KM | 178.20 | 15.35 KM | 15.35 KM | 19.65 | 178.20 | 7. | Cause Way | 54.00 No | 116.49 | 38.00 No | 38.00 No | 12.92 | 116.49 | 8. | longitudinal Drain | 15548.00 m | 111.45 | 15548.00 m | 15548.00 m | 12.34 | 111.45 | 9. | Crash Barrier | 245.00 m | 7.84 | 245.00 m | 245.00 m | 0.86 | 7.84 | 10. | Parapet | 606.00 No | 32.60 | 606.00 No | 606.00 No | 3.6 | 32.60 | 11. | Road Furniture | 707.00 No | 26.09 | 707.00 No | 707.00 No | 2.87 | 26.09 |
Total Amount: |
901.42 |
|
99.84 |
900 |
|
Remarks:
No Remarks
Work Program Made On:
11-06-2015
Updation of work program on:
10-01-2017
|
|
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 06-June-2015 | 44.96 lakhs |
2. | 26-August-2015 | 135.19 lakhs |
3. | 20-October-2015 | 48.31 lakhs |
4. | 19-February-2016 | 15.26 lakhs |
5. | 25-May-2016 | 101.37 lakhs |
6. | 30-August-2016 | 28.53 lakhs |
7. | 08-December-2016 | 147.47 lakhs |
8. | 31-May-2017 | 51.86 lakhs |
9. | 30-June-2017 | 26.21 lakhs |
10. | 29-July-2017 | 42.03 lakhs |
11. | 25-September-2017 | 73.25 lakhs |
12. | 07-October-2015 | 158.84 lakhs |
13. | 07-November-2015 | 25.36 lakhs |
14. | 17-March-2016 | 21.64 lakhs |
15. | 06-July-2016 | 95.64 lakhs |
16. | 16-November-2016 | 13.37 lakhs |
Total |
1029.29 lakhs |
% Payment |
98.55 % |
|
Advance Amount: 91.00 lakhs
Recovered Amount: 91.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Raipur-Kaddukhal Motor Road(5323) | Sanitation Facility, debris disposal, Query, DG set |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 25 |
Number of Notice(s) issued: 73 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 07-10-2016 | Ch. 72+00 | Temperature checking | Asha Rawat | JE | UEAP R&B Tehri | See Pic |
2. | 07-10-2016 | Km72 | BM LAYING | Asha Rawat | JE | UEAP R&B Tehri | See Pic |
3. | 21-09-2015 | 17.525 | Plant site visit by SE sir | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
4. | 21-09-2015 | Km18( CH.17+825) | R/w work in progress | Asha rawat | JE | DEA ADB Dehradun | See Pic |
5. | 28-08-2015 | 54.700 | HP Stone filling in progress | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
6. | 28-08-2015 | CH.49+000 | Causeway | Asha rawat | JE | DEA ADB Dehradun | See Pic |
7. | 28-08-2015 | 45+275 | Completed kuccha drain. | Asha rawat | JE | DEA ADB Dehradun | See Pic |
8. | 28-08-2015 | 29+575 | Completed R/W(RR 1:5) | Asha rawat | JE | DEA ADB Dehradun | See Pic |
9. | 28-08-2015 | 58.775 | Construction of KC drain in progress | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
10. | 28-08-2015 | Ch.59+450 | K.c drain. | Asha rawat | JE | DEA ADB Dehradun | See Pic |
11. | 27-08-2015 | 17.300 | G2 layer for Causeway has been completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
12. | 27-08-2015 | 18.025 | Completed R.W. mts. are being taken | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
13. | 05-08-2015 | 61.100 | Causeway Completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
14. | 05-08-2015 | 61.100 | Causeway Completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
15. | 04-08-2015 | 54.000 | RW Completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
16. | 03-08-2015 | Ch19+075 | Causeway with R/W | Asha rawat | JE | DEA ADB Dehradun | See Pic |
17. | 03-08-2015 | 54.00 | RW Completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
18. | 17-07-2015 | 21.650 | R.W. mts. are going on | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
19. | 17-07-2015 | 16.750 | R.W.is being constructed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
20. | 17-07-2015 | 16.700 | R.W. Completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
|
|