Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C56 Agreement signed
Project: UEAP-RB Package No.: 1060 Package Name: UEAP/PWD/C56 Sanction Cost: 1095.00  lakhs
District: Tehri Block: Jaunpur Constituency: Dhanaulti Circle:
DEA: DEA UEAP Tehri DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 2
Subproject in this package
1  5323   Raipur-Kaddukhal Motor Road ( KM.) (in prorgress)
2  5324   Suwakholi-Bhawaan-Sarot chapra-Nagum Motor Raod ( KM.) (completed)
Procurement:
Package No.: 1060        Package Name:  UEAP/PWD/C56        Tender Date: 20-09-2014        Current Status: Agreement signed        Achieved on Date: 12-01-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C56        Contractor Name: Woodhill Infrastructure Ltd       
Start Date: 03-02-2015        Intended Completion Date: 11-07-2016       
Total Bond Cost: 91997972.9 (919.98 lakhs)        Variation Cost: 12444241.30 (124.44 lakhs)     Hence Total Bond Cost is   104442214.2 (1044.42 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 1379970 for 30 days        LD Analysis for Milestone2: calculated LD is Rs 3035934 for 66 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence2.63 KM9.142.63 KM2.63 KM1.019.14
2.R/Wall, B/ Wall Type Protection works2587.00 m342.962587.00 m2587.00 m38.24342.96
3.G-20.20 KM1.410.20 KM0.10 KM0.080.71
4.G-30.20 KM1.440.20 KM0.10 KM0.080.72
5.BM i/c Prime Coat, Tack Coat4.09 KM73.804.09 KM4.09 KM8.1973.80
6.SDBC i/c Tackcoat15.35 KM178.2015.35 KM15.35 KM19.65178.20
7.Cause Way54.00 No116.4938.00 No38.00 No12.92116.49
8.longitudinal Drain15548.00 m111.4515548.00 m15548.00 m12.34111.45
9.Crash Barrier245.00 m7.84245.00 m245.00 m0.867.84
10.Parapet606.00 No32.60606.00 No606.00 No3.632.60
11.Road Furniture707.00 No26.09707.00 No707.00 No2.8726.09
Total Amount: 901.42 99.84   900
Remarks: No Remarks       Work Program Made On: 11-06-2015       Updation of work program on: 10-01-2017      
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired.
Financial Progress
SNo. Date Payment
1.06-June-201544.96  lakhs
2.26-August-2015135.19  lakhs
3.20-October-201548.31  lakhs
4.19-February-201615.26  lakhs
5.25-May-2016101.37  lakhs
6.30-August-201628.53  lakhs
7.08-December-2016147.47  lakhs
8.31-May-201751.86  lakhs
9.30-June-201726.21  lakhs
10.29-July-201742.03  lakhs
11.25-September-201773.25  lakhs
12.07-October-2015158.84  lakhs
13.07-November-201525.36  lakhs
14.17-March-201621.64  lakhs
15.06-July-201695.64  lakhs
16.16-November-201613.37  lakhs
Total 1029.29  lakhs
% Payment 98.55 %
Advance Amount:  91.00  lakhs        Recovered Amount:  91.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Raipur-Kaddukhal Motor Road(5323) Sanitation Facility, debris disposal, Query, DG set
Detailed report of this Package
Quality
No. of Test Required : 520     No. of Test Done : 533      No. of Test Passed : 520      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 25
Number of Notice(s) issued: 73

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.07-10-2016Ch. 72+00Temperature checkingAsha RawatJEUEAP R&B Tehri See Pic
2.07-10-2016Km72BM LAYINGAsha RawatJEUEAP R&B Tehri See Pic
3.21-09-201517.525Plant site visit by SE sirAnuj Kumar SinghAEUEAP R&B Tehri See Pic
4.21-09-2015Km18( CH.17+825)R/w work in progressAsha rawatJEDEA ADB Dehradun See Pic
5.28-08-201554.700HP Stone filling in progressAnuj Kumar SinghAEUEAP R&B Tehri See Pic
6.28-08-2015CH.49+000CausewayAsha rawatJEDEA ADB Dehradun See Pic
7.28-08-201545+275Completed kuccha drain.Asha rawatJEDEA ADB Dehradun See Pic
8.28-08-201529+575Completed R/W(RR 1:5)Asha rawatJEDEA ADB Dehradun See Pic
9.28-08-201558.775Construction of KC drain in progressAnuj Kumar SinghAEUEAP R&B Tehri See Pic
10.28-08-2015Ch.59+450K.c drain.Asha rawatJEDEA ADB Dehradun See Pic
11.27-08-201517.300G2 layer for Causeway has been completedAnuj Kumar SinghAEUEAP R&B Tehri See Pic
12.27-08-201518.025Completed R.W. mts. are being takenAnuj Kumar SinghAEUEAP R&B Tehri See Pic
13.05-08-201561.100Causeway CompletedAnuj Kumar SinghAEUEAP R&B Tehri See Pic
14.05-08-201561.100Causeway CompletedAnuj Kumar SinghAEUEAP R&B Tehri See Pic
15.04-08-201554.000RW CompletedAnuj Kumar SinghAEUEAP R&B Tehri See Pic
16.03-08-2015Ch19+075Causeway with R/WAsha rawatJEDEA ADB Dehradun See Pic
17.03-08-201554.00RW CompletedAnuj Kumar SinghAEUEAP R&B Tehri See Pic
18.17-07-201521.650R.W. mts. are going onAnuj Kumar SinghAEUEAP R&B Tehri See Pic
19.17-07-201516.750R.W.is being constructedAnuj Kumar SinghAEUEAP R&B Tehri See Pic
20.17-07-201516.700R.W. CompletedAnuj Kumar SinghAEUEAP R&B Tehri See Pic