Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/03/RD/095 Agreement signed
Project: UDRP-RB Package No.: 106 Package Name: UDRP/PWD/03/RD/095 Sanction Cost: 671.25  lakhs
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 4
Subproject in this package
1  2511   Bansu-Tyuri MR (1.500 KM.) (completed)
2  2524   Jakhdhar-Dewar MR (3.000 KM.) (completed)
3  2530   Khujeer bend to Chauki Barsil Motor Road (1.000 KM.) (completed)
4  2543   Suryaprayag- Mussadung Motor Road (5.500 KM.) (completed)
Procurement:
Package No.: 106        Package Name: UDRP/PWD/03/RD/095        Tender Date: 04-07-2015        Current Status: Agreement signed        Achieved on Date: 03-10-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/RD/095        Contractor Name: Vinod Kumar Chauhan       
Start Date: 10-10-2015        Intended Completion Date: 06-06-2017        Original End Date:  09-01-2017
Total Bond Cost: 55718387.81 (557.18 lakhs)        Variation Cost: 9792705.36 (97.93 lakhs)     Hence Total Bond Cost is   65511093.17 (655.11 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works780.00 m71.81780.00 m780.00 m12.3371.81
2.GSB/RBI/G-14.50 KM34.224.50 KM4.50 KM5.9434.22
3.G-29.60 KM55.809.60 KM9.60 KM9.6955.80
4.G-37.05 KM49.897.05 KM7.05 KM8.6649.89
5.PC/CC i/c Prime Coat, Tack Coat11.05 KM136.6411.05 KM11.05 KM23.23136.64
6.Culverts/Scupper 20.00 No49.6120.00 No20.00 No8.449.61
7.longitudinal Drain10880.00 m42.9810880.00 m10880.00 m7.3842.98
8.Crash Barrier1498.00 m39.821498.00 m1498.00 m6.8939.82
9.Parapet345.00 No6.24345.00 No345.00 No1.096.24
10.Road Furniture90.00 No0.5590.00 No90.00 No0.090.55
11.Other Allied Works & Finishing Work 2.00 Job24.842.00 Job2.00 Job4.3124.84
12.Hill side Cutting & Slip clearence6.50 KM15.326.50 KM6.50 KM2.5715.32
13.Cause Way6.00 No57.296.00 No6.00 No9.4357.29
Total Amount: 585.01 100   585.01
Remarks: No Remarks       Work Program Made On: 17-11-2015       Updation of work program on: 02-06-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-March-201646.95  lakhs
2.02-May-201677.19  lakhs
3.18-May-201647.62  lakhs
4.07-June-201633.14  lakhs
5.28-June-201625.84  lakhs
6.11-September-201614.35  lakhs
7.24-October-201628.77  lakhs
8.24-December-201617.47  lakhs
9.30-March-201731.74  lakhs
10.18-May-2017126.51  lakhs
11.27-July-201720.74  lakhs
12.30-November-201521.97  lakhs
13.28-January-201634.71  lakhs
14.28-February-20177.47  lakhs
15.26-December-201529.61  lakhs
16.26-February-201656.81  lakhs
17.22-June-201716.18  lakhs
Total 637.07  lakhs
% Payment 97.25 %
Advance Amount:  4.54  lakhs        Recovered Amount:  4.54  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 316     No. of Test Done : 349      No. of Test Passed : 334      No. of Test Failed : 15   Test report of this package
Number of Pics Available on Web Repository: 364
Number of Notice(s) issued: 72

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-06-20175+235R/W damage and heavy land slide due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
2.08-06-20175+275Parapet base wash-out due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
3.08-06-20175+300Land slide and chauked scupper due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
4.08-06-20175+375Land slides and full patri damage due to heavy run off water heavy rainfal. 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
5.08-06-20175+420R/W damage due to heavy run off water heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
6.08-06-20175+420Road and R/W damage due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
7.08-06-20175+275Land slides and road damage due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
8.08-06-20175+150Land slide due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
9.08-06-20175+000Slip cleaning work due to land slide heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
10.08-06-20174+975Old R/W damage due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
11.08-06-20173+025Slip cleaning work in progressVineet KumarJEUDRP R&B Guptkashi See Pic
12.08-06-20173+025Old r/w demage bottom of causeway due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
13.08-06-20172+100Road opening work in progress due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
14.08-06-20172+100R/W demage old due to heavy rainfall 05-06-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
15.08-06-20175+175Land slides road block in rainfall 27-05-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
16.08-06-20175+275Land slides due to rainfall on date 27-05-2017Vineet KumarJEUDRP R&B Guptkashi See Pic
17.17-05-20175+300II layer wire crate fixing work in progressVineet KumarJEUDRP R&B Guptkashi See Pic
18.12-05-20175+175Wire crate fixing work in progress.Vineet KumarJEUDRP R&B Guptkashi See Pic
19.08-05-20171.000Premix carpet laying Bansu Tyuri Motor RoadSiddharth RangharJEUDRP R&B Guptkashi See Pic
20.08-05-20171.350Seal coat rolling under process Bansu TyuriSiddharth RangharJEUDRP R&B Guptkashi See Pic