Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C54 Agreement signed
Project: UEAP-RB Package No.: 1057 Package Name: UEAP/PWD/C54 Sanction Cost: 725.00  lakhs
District: Uttarkashi Block: Naugaon Constituency: Yamunotri Circle:
DEA: DEA UEAP Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design and Supervision No.of Sub project : 2
Subproject in this package
1  5012   Naogaon Paunti Rajgadi Motor Road (24.000 KM.) (completed)
2  5013   Damta Kandari Motor Raod (6.000 KM.) (completed)
Procurement:
Package No.: 1057        Package Name:  UEAP/PWD/C54        Tender Date: 16-10-2014        Current Status: Agreement signed        Achieved on Date: 25-05-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C54        Contractor Name: R K Gupta Contractor       
Start Date: 15-06-2015        Intended Completion Date: 31-05-2017        Original End Date:  14-12-2016
Total Bond Cost: 61166275.95 (611.66 lakhs)        Variation Cost: 7370825.78 (73.71 lakhs)     Hence Total Bond Cost is   68537101.73 (685.37 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 1682065 for 55 days        LD Analysis for Milestone2: calculated LD is Rs 672826 for 22 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence12.32 KM0.6312.32 KM12.32 KM0.090.63
2.R/Wall, B/ Wall Type Protection works1350.00 m157.121350.00 m1350.00 m22.69157.12
3.G-21.00 KM15.751.00 KM1.00 KM2.2315.75
4.G-31.00 KM7.981.00 KM1.00 KM1.137.98
5.BM i/c Prime Coat, Tack Coat4.00 KM83.844.00 KM4.00 KM11.8683.84
6.SDBC i/c Tackcoat4.00 KM64.694.00 KM4.00 KM9.1564.69
7.Cause Way15.00 No64.8115.00 No15.00 No9.2264.81
8.Culverts/Scupper 4.00 No34.704.00 No4.00 No4.9134.70
9.longitudinal Drain10420.00 m159.5110416.00 m10416.00 m23.1159.51
10.Crash Barrier450.00 m13.39450.00 m450.00 m1.9413.39
11.Parapet115.00 No11.90115.00 No115.00 No1.6811.90
12.Road Furniture3152.00 No23.873152.00 No3152.00 No3.4423.87
13.Other Allied Works & Finishing Work 3.00 Job58.403.00 Job3.00 Job8.5658.40
Total Amount: 696.59 100   696.59
Remarks:        Work Program Made On: 14-10-2015       Updation of work program on: 24-07-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.20-October-201540.72  lakhs
2.15-December-201546.29  lakhs
3.31-January-201636.82  lakhs
4.29-February-201633.62  lakhs
5.31-March-201649.89  lakhs
6.29-April-201618.53  lakhs
7.28-May-201652.83  lakhs
8.18-June-201629.67  lakhs
9.09-September-201686.92  lakhs
10.26-October-201620.41  lakhs
11.23-February-201742.59  lakhs
12.06-April-201717.74  lakhs
13.27-June-201747.31  lakhs
Total 523.34  lakhs
% Payment 76.36 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1570     No. of Test Done : 1571      No. of Test Passed : 1570      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 25
Number of Notice(s) issued: 77

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.10-09-20169.600Parapet work done at c 48Pooja GargJEUEAP R&B Almora See Pic
2.10-09-20169.800Parapet work done c48 jalikhan nobaraPooja GargJEUEAP R&B Almora See Pic
3.10-09-201610.050Parapet completed at c 48 jalikhan nobaraPooja GargJEUEAP R&B Almora See Pic
4.10-09-201610.200Parapet work done at package c 48 jalikhan nobaraPooja GargJEUEAP R&B Almora See Pic
5.10-09-201611.000PC work at c 48Pooja GargJEUEAP R&B Almora See Pic
6.17-02-2016Ch 6.300Excavation for KC DrainChetan BhattJEUEAP R&B Almora See Pic
7.17-02-2016Ch 0.800KC drain completeChetan BhattJEUEAP R&B Almora See Pic
8.17-02-2016Chainage 18.350B C laying in progressChetan BhattJEUEAP R&B Almora See Pic
9.26-01-201619+900R/wall in completeBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
10.26-01-201618+100R/wall with plum in progressBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
11.26-01-201618.00R/wall in completeBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
12.21-12-20150+700Drain work in progressBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
13.21-12-20150+890CausewayBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
14.21-12-20150+900R/wall in completeBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
15.21-12-20150+850R/wall in completeBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
16.07-11-20150.800Runing r/wallAjeet SinghAEUEAP R&B Uttarkashi See Pic
17.04-11-201594.020Bm laying in progressAjeet SinghAEUEAP R&B Uttarkashi See Pic
18.04-11-201594.060Cleaning surface before b.m.Ajeet SinghAEUEAP R&B Uttarkashi See Pic
19.14-09-20153+00Construction of causewayBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
20.14-09-20150+175R/wall in progressBheem Singh MeharJEUEAP R&B Uttarkashi See Pic