UEAP/PWD/C54
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1057 |
Package Name: |
UEAP/PWD/C54 |
Sanction Cost: |
725.00 lakhs |
District: |
Uttarkashi |
Block: |
Naugaon |
Constituency: |
Yamunotri |
Circle: |
|
DEA: |
DEA UEAP Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 5012 Naogaon Paunti Rajgadi Motor Road (24.000 KM.) (completed) | 2 5013 Damta Kandari Motor Raod (6.000 KM.) (completed) |
|
Procurement: |
Package No.: 1057
Package Name:  UEAP/PWD/C54
Tender Date: 16-10-2014
Current Status: Agreement signed
Achieved on Date: 25-05-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C54
Contractor Name: R K Gupta Contractor
|
Start Date: 15-06-2015
Intended Completion Date: 31-05-2017
Original End Date: 14-12-2016
|
Total Bond Cost: 61166275.95 (611.66 lakhs)
Variation Cost: 7370825.78 (73.71 lakhs) Hence Total Bond Cost is 68537101.73 (685.37 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1682065 for 55 days
LD Analysis for Milestone2: calculated LD is Rs 672826 for 22 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 12.32 KM | 0.63 | 12.32 KM | 12.32 KM | 0.09 | 0.63 | 2. | R/Wall, B/ Wall Type Protection works | 1350.00 m | 157.12 | 1350.00 m | 1350.00 m | 22.69 | 157.12 | 3. | G-2 | 1.00 KM | 15.75 | 1.00 KM | 1.00 KM | 2.23 | 15.75 | 4. | G-3 | 1.00 KM | 7.98 | 1.00 KM | 1.00 KM | 1.13 | 7.98 | 5. | BM i/c Prime Coat, Tack Coat | 4.00 KM | 83.84 | 4.00 KM | 4.00 KM | 11.86 | 83.84 | 6. | SDBC i/c Tackcoat | 4.00 KM | 64.69 | 4.00 KM | 4.00 KM | 9.15 | 64.69 | 7. | Cause Way | 15.00 No | 64.81 | 15.00 No | 15.00 No | 9.22 | 64.81 | 8. | Culverts/Scupper | 4.00 No | 34.70 | 4.00 No | 4.00 No | 4.91 | 34.70 | 9. | longitudinal Drain | 10420.00 m | 159.51 | 10416.00 m | 10416.00 m | 23.1 | 159.51 | 10. | Crash Barrier | 450.00 m | 13.39 | 450.00 m | 450.00 m | 1.94 | 13.39 | 11. | Parapet | 115.00 No | 11.90 | 115.00 No | 115.00 No | 1.68 | 11.90 | 12. | Road Furniture | 3152.00 No | 23.87 | 3152.00 No | 3152.00 No | 3.44 | 23.87 | 13. | Other Allied Works & Finishing Work | 3.00 Job | 58.40 | 3.00 Job | 3.00 Job | 8.56 | 58.40 |
Total Amount: |
696.59 |
|
100 |
696.59 |
|
Remarks:
Work Program Made On:
14-10-2015
Updation of work program on:
24-07-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 20-October-2015 | 40.72 lakhs |
2. | 15-December-2015 | 46.29 lakhs |
3. | 31-January-2016 | 36.82 lakhs |
4. | 29-February-2016 | 33.62 lakhs |
5. | 31-March-2016 | 49.89 lakhs |
6. | 29-April-2016 | 18.53 lakhs |
7. | 28-May-2016 | 52.83 lakhs |
8. | 18-June-2016 | 29.67 lakhs |
9. | 09-September-2016 | 86.92 lakhs |
10. | 26-October-2016 | 20.41 lakhs |
11. | 23-February-2017 | 42.59 lakhs |
12. | 06-April-2017 | 17.74 lakhs |
13. | 27-June-2017 | 47.31 lakhs |
Total |
523.34 lakhs |
% Payment |
76.36 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Bill should be issued |
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 25 |
Number of Notice(s) issued: 77 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 10-09-2016 | 9.600 | Parapet work done at c 48 | Pooja Garg | JE | UEAP R&B Almora | See Pic |
2. | 10-09-2016 | 9.800 | Parapet work done c48 jalikhan nobara | Pooja Garg | JE | UEAP R&B Almora | See Pic |
3. | 10-09-2016 | 10.050 | Parapet completed at c 48 jalikhan nobara | Pooja Garg | JE | UEAP R&B Almora | See Pic |
4. | 10-09-2016 | 10.200 | Parapet work done at package c 48 jalikhan nobara | Pooja Garg | JE | UEAP R&B Almora | See Pic |
5. | 10-09-2016 | 11.000 | PC work at c 48 | Pooja Garg | JE | UEAP R&B Almora | See Pic |
6. | 17-02-2016 | Ch 6.300 | Excavation for KC Drain | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
7. | 17-02-2016 | Ch 0.800 | KC drain complete | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
8. | 17-02-2016 | Chainage 18.350 | B C laying in progress | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
9. | 26-01-2016 | 19+900 | R/wall in complete | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
10. | 26-01-2016 | 18+100 | R/wall with plum in progress | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
11. | 26-01-2016 | 18.00 | R/wall in complete | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
12. | 21-12-2015 | 0+700 | Drain work in progress | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
13. | 21-12-2015 | 0+890 | Causeway | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
14. | 21-12-2015 | 0+900 | R/wall in complete | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
15. | 21-12-2015 | 0+850 | R/wall in complete | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
16. | 07-11-2015 | 0.800 | Runing r/wall | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
17. | 04-11-2015 | 94.020 | Bm laying in progress | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
18. | 04-11-2015 | 94.060 | Cleaning surface before b.m. | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
19. | 14-09-2015 | 3+00 | Construction of causeway | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
20. | 14-09-2015 | 0+175 | R/wall in progress | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
|
|