UEAP/PWD/C51
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1054 |
Package Name: |
UEAP/PWD/C51 |
Sanction Cost: |
582.00 lakhs |
District: |
Chamoli |
Block: |
Pokhari |
Constituency: |
Badrinath |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5119 Pokhri-Gopeshwar Motor Road ( KM.) (in prorgress) |
|
Procurement: |
Package No.: 1054
Package Name:  UEAP/PWD/C51
Tender Date: 16-10-2014
Current Status: Agreement signed
Achieved on Date: 13-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C51
Contractor Name: R.G. Buildwell.
|
Start Date: 05-03-2015
Intended Completion Date: 15-03-2017
Original End Date: 04-09-2016
|
Total Bond Cost: 49371747 (493.72 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1258986 for 51 days
LD Analysis for Milestone2: calculated LD is Rs 5653094 for 229 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.25 KM | 0.57 | 0.25 KM | 0.00 KM | 0 | 0.00 | 2. | R/Wall, B/ Wall Type Protection works | 1246.00 m | 164.12 | 3746.00 m | 1100.00 m | 9.96 | 42.55 | 3. | GSB/RBI/G-1 | 0.02 KM | 0.19 | 0.03 KM | 0.02 KM | 0.03 | 0.13 | 4. | G-2 | 0.06 KM | 0.40 | 0.07 KM | 0.06 KM | 0.07 | 0.34 | 5. | G-3 | 0.78 KM | 5.29 | 0.78 KM | 0.78 KM | 1.09 | 5.29 | 6. | BM i/c Prime Coat, Tack Coat | 0.84 KM | 24.29 | 0.84 KM | 0.84 KM | 5.02 | 24.29 | 7. | SDBC i/c Tackcoat | 2.62 KM | 50.88 | 3.30 KM | 2.62 KM | 8.35 | 40.39 | 8. | Cause Way | 23.00 No | 136.98 | 23.00 No | 0.00 No | 0 | 0.00 | 9. | Culverts/Scupper | 79.00 No | 7.23 | 79.00 No | 60.00 No | 1.13 | 5.49 | 10. | longitudinal Drain | 24000.00 m | 41.01 | 2800.00 m | 2800.00 m | 8.48 | 41.01 | 11. | Crash Barrier | 585.00 m | 18.72 | 585.00 m | 585.00 m | 3.87 | 18.72 | 12. | Road Furniture | 1146.00 No | 23.38 | 1148.00 No | 700.00 No | 2.95 | 8.71 | 13. | Other Allied Works & Finishing Work | 3.00 Job | 10.76 | 3.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
483.82 |
|
40.95 |
186.92 |
|
Remarks:
No Remarks
Work Program Made On:
26-02-2015
Updation of work program on:
15-03-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 03-June-2015 | 17.33 lakhs |
2. | 21-July-2015 | 18.51 lakhs |
3. | 28-August-2015 | 17.08 lakhs |
4. | 05-November-2015 | 54.43 lakhs |
5. | 11-March-2016 | 12.47 lakhs |
6. | 04-August-2016 | 53.86 lakhs |
7. | 24-October-2016 | 77.19 lakhs |
8. | 10-December-2016 | 67.51 lakhs |
9. | 07-February-2017 | 50.64 lakhs |
10. | 24-March-2017 | 26.13 lakhs |
11. | 29-April-2017 | 48.25 lakhs |
Total |
443.4 lakhs |
% Payment |
89.81 % |
|
Advance Amount: 49.37 lakhs
Recovered Amount: 36.18 lakhs
Balance to be Recovered 13.19 lakhs
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | workmen Insurance | Environment & Social Compliances(Sub Project level): | Pokhri-Gopeshwar Motor Road(5119) | No Pending Issue |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 49 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 13-09-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | Gabbion channel work in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
2. | 13-09-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | RCC wall completed | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
3. | 13-09-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | Gabbion channel work in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
4. | 13-09-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | Gabbion channel work in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
5. | 26-07-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | Gabbion work over PCC block in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
6. | 26-07-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | Gabbion work over PCC block in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
7. | 05-06-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | Gabbion work in progress for Toe Dam | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
8. | 05-06-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | PCC block completed for Gabbion wall | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
9. | 24-05-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | RCC work in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
10. | 24-05-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | Reinforcement completed for RCC wall | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
11. | 13-05-2017 | Slip zone/km12 from pokhari | Reinforcements cheking for RCC Wall. | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
12. | 13-05-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | Reinforcement in progress for RCC wall | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
13. | 13-05-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | Self driven soil anchor in progress for nala stopper | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
14. | 06-05-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | PCC for RCC retaining wall | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
15. | 02-05-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | 30m gabbion stopper work in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
16. | 29-04-2017 | Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12 | 30m gabbion stopper work in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
17. | 26-04-2017 | Chronic slip zone km 12 | Gabbion toe Dam in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
18. | 26-04-2017 | Chronic slip zone km 12 | Excavation for 30m gabbion stopper in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
19. | 13-04-2017 | Chronic slip zone | Excavation for Gabbion toe Dam in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
20. | 24-03-2017 | Chronic slip zone near village Salna | Excavation for RCC wall | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
|
|