Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C51 Agreement signed
Project: UEAP-RB Package No.: 1054 Package Name: UEAP/PWD/C51 Sanction Cost: 582.00  lakhs
District: Chamoli Block: Pokhari Constituency: Badrinath Circle:
DEA: DEA UEAP Chamoli DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  5119   Pokhri-Gopeshwar Motor Road ( KM.) (in prorgress)
Procurement:
Package No.: 1054        Package Name:  UEAP/PWD/C51        Tender Date: 16-10-2014        Current Status: Agreement signed        Achieved on Date: 13-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C51        Contractor Name: R.G. Buildwell.       
Start Date: 05-03-2015        Intended Completion Date: 15-03-2017        Original End Date:  04-09-2016
Total Bond Cost: 49371747 (493.72 lakhs)       
LD Analysis for Milestone1: calculated LD is Rs 1258986 for 51 days        LD Analysis for Milestone2: calculated LD is Rs 5653094 for 229 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.25 KM0.570.25 KM0.00 KM00.00
2.R/Wall, B/ Wall Type Protection works1246.00 m164.123746.00 m1100.00 m9.9642.55
3.GSB/RBI/G-10.02 KM0.190.03 KM0.02 KM0.030.13
4.G-20.06 KM0.400.07 KM0.06 KM0.070.34
5.G-30.78 KM5.290.78 KM0.78 KM1.095.29
6.BM i/c Prime Coat, Tack Coat0.84 KM24.290.84 KM0.84 KM5.0224.29
7.SDBC i/c Tackcoat2.62 KM50.883.30 KM2.62 KM8.3540.39
8.Cause Way23.00 No136.9823.00 No0.00 No00.00
9.Culverts/Scupper 79.00 No7.2379.00 No60.00 No1.135.49
10.longitudinal Drain24000.00 m41.012800.00 m2800.00 m8.4841.01
11.Crash Barrier585.00 m18.72585.00 m585.00 m3.8718.72
12.Road Furniture1146.00 No23.381148.00 No700.00 No2.958.71
13.Other Allied Works & Finishing Work 3.00 Job10.763.00 Job0.00 Job00.00
Total Amount: 483.82 40.95   186.92
Remarks: No Remarks       Work Program Made On: 26-02-2015       Updation of work program on: 15-03-2017      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.03-June-201517.33  lakhs
2.21-July-201518.51  lakhs
3.28-August-201517.08  lakhs
4.05-November-201554.43  lakhs
5.11-March-201612.47  lakhs
6.04-August-201653.86  lakhs
7.24-October-201677.19  lakhs
8.10-December-201667.51  lakhs
9.07-February-201750.64  lakhs
10.24-March-201726.13  lakhs
11.29-April-201748.25  lakhs
Total 443.4  lakhs
% Payment 89.81 %
Advance Amount:  49.37  lakhs        Recovered Amount:  36.18  lakhs        Balance to be Recovered  13.19  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): workmen Insurance
Environment & Social Compliances(Sub Project level):
Pokhri-Gopeshwar Motor Road(5119)No Pending Issue
Detailed report of this Package
Quality
No. of Test Required : 62     No. of Test Done : 92      No. of Test Passed : 92      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 49
Number of Notice(s) issued: 68

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.13-09-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Gabbion channel work in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
2.13-09-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12RCC wall completedRachna BahugunaJEUEAP R&B Chamoli See Pic
3.13-09-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Gabbion channel work in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
4.13-09-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Gabbion channel work in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
5.26-07-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Gabbion work over PCC block in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
6.26-07-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Gabbion work over PCC block in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
7.05-06-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Gabbion work in progress for Toe DamRachna BahugunaJEUEAP R&B Chamoli See Pic
8.05-06-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12PCC block completed for Gabbion wallRachna BahugunaJEUEAP R&B Chamoli See Pic
9.24-05-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12RCC work in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
10.24-05-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Reinforcement completed for RCC wallRachna BahugunaJEUEAP R&B Chamoli See Pic
11.13-05-2017Slip zone/km12 from pokhariReinforcements cheking for RCC Wall.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
12.13-05-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Reinforcement in progress for RCC wallRachna BahugunaJEUEAP R&B Chamoli See Pic
13.13-05-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12Self driven soil anchor in progress for nala stopperRachna BahugunaJEUEAP R&B Chamoli See Pic
14.06-05-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 12PCC for RCC retaining wallRachna BahugunaJEUEAP R&B Chamoli See Pic
15.02-05-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 1230m gabbion stopper work in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
16.29-04-2017Chronic slip zone Rudrprayag Pokhari Gopeshwar km 1230m gabbion stopper work in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
17.26-04-2017Chronic slip zone km 12Gabbion toe Dam in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
18.26-04-2017Chronic slip zone km 12Excavation for 30m gabbion stopper in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
19.13-04-2017Chronic slip zoneExcavation for Gabbion toe Dam in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
20.24-03-2017Chronic slip zone near village SalnaExcavation for RCC wallRachna BahugunaJEUEAP R&B Chamoli See Pic