Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C50 Agreement signed
Project: UEAP-RB Package No.: 1053 Package Name: UEAP/PWD/C50 Sanction Cost: 1664.00  lakhs
District: Chamoli Block: Karnaprayag Constituency: Karanprayag Circle:
DEA: DEA UEAP Chamoli DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision No.of Sub project : 1
Subproject in this package
1  5117   Karanprayag-Nainisen Motor Road (26.000 KM.) (in prorgress)
Procurement:
Package No.: 1053        Package Name:  UEAP/PWD/C50        Tender Date: 26-09-2014        Current Status: Agreement signed        Achieved on Date: 22-04-2015

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C50        Contractor Name: R.G. Buildwell.       
Start Date: 01-05-2015        Intended Completion Date: 20-03-2017        Original End Date:  31-10-2016
Total Bond Cost: 152362522 (1523.63 lakhs)        Variation Cost: 59430013.45 (594.3 lakhs)     Hence Total Bond Cost is   211792535.45 (2117.93 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 10208254 for 134 days        LD Analysis for Milestone2: calculated LD is Rs 2437792 for 32 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.58 KM5.990.58 KM0.20 KM0.12.07
2.R/Wall, B/ Wall Type Protection works3065.00 m466.093065.00 m2700.00 m19.58410.58
3.GSB/RBI/G-13.88 KM36.374.60 KM4.60 KM1.7436.37
4.G-27.90 KM55.058.60 KM6.00 KM1.8329.17
5.G-312.50 KM89.2713.75 KM11.00 KM3.4162.85
6.BM i/c Prime Coat, Tack Coat25.50 KM632.6925.50 KM25.50 KM30.17632.69
7.SDBC i/c Tackcoat25.50 KM469.6225.50 KM25.50 KM22.4469.62
8.Cause Way23.00 No186.6723.00 No8.00 No3.164.93
9.Culverts/Scupper 65.00 No16.3565.00 No58.00 No0.714.59
10.longitudinal Drain24775.00 m41.0624775.00 m13550.00 m1.0722.46
11.Crash Barrier1390.00 m44.481390.00 m1390.00 m2.1244.48
12.Road Furniture1451.00 No51.691451.00 No600.00 No1.0221.37
13.Other Allied Works & Finishing Work 1.00 Job1.471.00 Job0.00 Job00.00
Total Amount: 2096.8 87.23   1811.18
Remarks: No Remarks       Work Program Made On: 11-02-2017       Updation of work program on: 26-02-2017      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.22-July-201514.22  lakhs
2.22-September-201546.08  lakhs
3.19-October-201558.96  lakhs
4.10-November-201511.34  lakhs
5.11-February-201667.19  lakhs
6.12-March-2016103.59  lakhs
7.31-March-2016118.53  lakhs
8.29-April-2016163.52  lakhs
9.18-May-2016117.84  lakhs
10.16-June-2016119.40  lakhs
11.17-July-201654.96  lakhs
12.26-October-2016341.79  lakhs
13.10-December-2016113.35  lakhs
14.13-January-201788.65  lakhs
15.07-March-2017250.57  lakhs
16.24-March-201764.05  lakhs
17.29-April-201784.05  lakhs
18.06-June-201733.60  lakhs
19.19-June-201753.28  lakhs
Total 1904.97  lakhs
% Payment 89.94 %
Advance Amount:  152.36  lakhs        Recovered Amount:  131.96  lakhs        Balance to be Recovered  20.40  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles, workmen Insurance
Environment & Social Compliances(Sub Project level):
Karanprayag-Nainisen Motor Road(5117) Land Owner Consent
Detailed report of this Package
Quality
No. of Test Required : 315     No. of Test Done : 511      No. of Test Passed : 511      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 86
Number of Notice(s) issued: 68

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.25-08-20170+250SE Sir Srinagar site inspection along with TL,EE,RE,AERachna BahugunaJEUEAP R&B Chamoli See Pic
2.03-03-201710+220MBCB, Road stud & thermoplastic paint in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
3.10-02-20176+550PCC work in progress for CC RoadRachna BahugunaJEUEAP R&B Chamoli See Pic
4.30-11-2016Km 23 (Ch. 22+790), Karnprayag Nainisain motor road.Road marking (Thermoplastic paint) work on motor road.Atul ShandilyaAEUEAP R&B Chamoli See Pic
5.30-11-2016Km 25 (Ch. 24+270), Karnprayag Nainisain motor road.Road marking (Thermoplastic paint) work on motor road.Atul ShandilyaAEUEAP R&B Chamoli See Pic
6.18-11-2016C50(Gandhi Nagar)/0+2200+220Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
7.18-11-20160+500Completed rcc surfacePrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
8.18-11-20160+220Rcc work is on progressPrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
9.04-11-2016Km 22 (Ch. 21+580), Karnprayag Nainisain motor road.BC work laid surface along with Patri filling and katcha drain.Atul ShandilyaAEUEAP R&B Chamoli See Pic
10.26-10-201623+850Width of bc work checked by ae sirPrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
11.26-10-201623+906Combined thickness of bm and bc checked by ae sirPrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
12.22-10-2016Jashiyara village /20+900B.C. laying work in progress for karanprayag nanisen roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
13.22-10-2016Dhansari village/ 21+380B.C. Laying & rolling work in progress for karanprayag nanisen roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
14.22-10-2016Dhansari village /21+550B.C. laying & rolling work in progress for karanprayag nanisen roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
15.22-10-2016Dhansari village/ 21+600Thickness checked during B.C. laying at karanprayag nanisen roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
16.22-10-2016Dhansari village/ 21+620B.C. laying & rolling work in progress for karanprayag nanisen roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
17.20-10-2016Kandara village \22+550B.C. laying work in progress for karanprayag nanisen roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
18.20-10-2016Kandara village / 22+380B.C. laying work in progress for karanprayag nanisen roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
19.20-10-2016Kanadra village /22+480Thickness checked during B.C. laying at karanprayag nanisen roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
20.20-10-2016Kandara village /22+500B.C. laying work in progress for karanprayag nanisen roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic