UEAP/PWD/C50
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1053 |
Package Name: |
UEAP/PWD/C50 |
Sanction Cost: |
1664.00 lakhs |
District: |
Chamoli |
Block: |
Karnaprayag |
Constituency: |
Karanprayag |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5117 Karanprayag-Nainisen Motor Road (26.000 KM.) (in prorgress) |
|
Procurement: |
Package No.: 1053
Package Name:  UEAP/PWD/C50
Tender Date: 26-09-2014
Current Status: Agreement signed
Achieved on Date: 22-04-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C50
Contractor Name: R.G. Buildwell.
|
Start Date: 01-05-2015
Intended Completion Date: 20-03-2017
Original End Date: 31-10-2016
|
Total Bond Cost: 152362522 (1523.63 lakhs)
Variation Cost: 59430013.45 (594.3 lakhs) Hence Total Bond Cost is 211792535.45 (2117.93 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 10208254 for 134 days
LD Analysis for Milestone2: calculated LD is Rs 2437792 for 32 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.58 KM | 5.99 | 0.58 KM | 0.20 KM | 0.1 | 2.07 | 2. | R/Wall, B/ Wall Type Protection works | 3065.00 m | 466.09 | 3065.00 m | 2700.00 m | 19.58 | 410.58 | 3. | GSB/RBI/G-1 | 3.88 KM | 36.37 | 4.60 KM | 4.60 KM | 1.74 | 36.37 | 4. | G-2 | 7.90 KM | 55.05 | 8.60 KM | 6.00 KM | 1.83 | 29.17 | 5. | G-3 | 12.50 KM | 89.27 | 13.75 KM | 11.00 KM | 3.41 | 62.85 | 6. | BM i/c Prime Coat, Tack Coat | 25.50 KM | 632.69 | 25.50 KM | 25.50 KM | 30.17 | 632.69 | 7. | SDBC i/c Tackcoat | 25.50 KM | 469.62 | 25.50 KM | 25.50 KM | 22.4 | 469.62 | 8. | Cause Way | 23.00 No | 186.67 | 23.00 No | 8.00 No | 3.1 | 64.93 | 9. | Culverts/Scupper | 65.00 No | 16.35 | 65.00 No | 58.00 No | 0.7 | 14.59 | 10. | longitudinal Drain | 24775.00 m | 41.06 | 24775.00 m | 13550.00 m | 1.07 | 22.46 | 11. | Crash Barrier | 1390.00 m | 44.48 | 1390.00 m | 1390.00 m | 2.12 | 44.48 | 12. | Road Furniture | 1451.00 No | 51.69 | 1451.00 No | 600.00 No | 1.02 | 21.37 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 1.47 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
2096.8 |
|
87.23 |
1811.18 |
|
Remarks:
No Remarks
Work Program Made On:
11-02-2017
Updation of work program on:
26-02-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 22-July-2015 | 14.22 lakhs |
2. | 22-September-2015 | 46.08 lakhs |
3. | 19-October-2015 | 58.96 lakhs |
4. | 10-November-2015 | 11.34 lakhs |
5. | 11-February-2016 | 67.19 lakhs |
6. | 12-March-2016 | 103.59 lakhs |
7. | 31-March-2016 | 118.53 lakhs |
8. | 29-April-2016 | 163.52 lakhs |
9. | 18-May-2016 | 117.84 lakhs |
10. | 16-June-2016 | 119.40 lakhs |
11. | 17-July-2016 | 54.96 lakhs |
12. | 26-October-2016 | 341.79 lakhs |
13. | 10-December-2016 | 113.35 lakhs |
14. | 13-January-2017 | 88.65 lakhs |
15. | 07-March-2017 | 250.57 lakhs |
16. | 24-March-2017 | 64.05 lakhs |
17. | 29-April-2017 | 84.05 lakhs |
18. | 06-June-2017 | 33.60 lakhs |
19. | 19-June-2017 | 53.28 lakhs |
Total |
1904.97 lakhs |
% Payment |
89.94 % |
|
Advance Amount: 152.36 lakhs
Recovered Amount: 131.96 lakhs
Balance to be Recovered 20.40 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | PUC vehicles, workmen Insurance | Environment & Social Compliances(Sub Project level): | Karanprayag-Nainisen Motor Road(5117) | Land Owner Consent |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 86 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 25-08-2017 | 0+250 | SE Sir Srinagar site inspection along with TL,EE,RE,AE | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
2. | 03-03-2017 | 10+220 | MBCB, Road stud & thermoplastic paint in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
3. | 10-02-2017 | 6+550 | PCC work in progress for CC Road | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
4. | 30-11-2016 | Km 23 (Ch. 22+790), Karnprayag Nainisain motor road. | Road marking (Thermoplastic paint) work on motor road. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
5. | 30-11-2016 | Km 25 (Ch. 24+270), Karnprayag Nainisain motor road. | Road marking (Thermoplastic paint) work on motor road. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
6. | 18-11-2016 | C50(Gandhi Nagar)/0+220 | 0+220 | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
7. | 18-11-2016 | 0+500 | Completed rcc surface | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
8. | 18-11-2016 | 0+220 | Rcc work is on progress | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
9. | 04-11-2016 | Km 22 (Ch. 21+580), Karnprayag Nainisain motor road. | BC work laid surface along with Patri filling and katcha drain. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
10. | 26-10-2016 | 23+850 | Width of bc work checked by ae sir | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
11. | 26-10-2016 | 23+906 | Combined thickness of bm and bc checked by ae sir | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
12. | 22-10-2016 | Jashiyara village /20+900 | B.C. laying work in progress for karanprayag nanisen road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
13. | 22-10-2016 | Dhansari village/ 21+380 | B.C. Laying & rolling work in progress for karanprayag nanisen road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
14. | 22-10-2016 | Dhansari village /21+550 | B.C. laying & rolling work in progress for karanprayag nanisen road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
15. | 22-10-2016 | Dhansari village/ 21+600 | Thickness checked during B.C. laying at karanprayag nanisen road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
16. | 22-10-2016 | Dhansari village/ 21+620 | B.C. laying & rolling work in progress for karanprayag nanisen road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
17. | 20-10-2016 | Kandara village \22+550 | B.C. laying work in progress for karanprayag nanisen road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
18. | 20-10-2016 | Kandara village / 22+380 | B.C. laying work in progress for karanprayag nanisen road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
19. | 20-10-2016 | Kanadra village /22+480 | Thickness checked during B.C. laying at karanprayag nanisen road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
20. | 20-10-2016 | Kandara village /22+500 | B.C. laying work in progress for karanprayag nanisen road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
|
|