UEAP/PWD/C49
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1052 |
Package Name: |
UEAP/PWD/C49 |
Sanction Cost: |
1646.00 lakhs |
District: |
Chamoli |
Block: |
Karnaprayag |
Constituency: |
Karanprayag |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 5115 Karanprayag- Nauti- Paithani Motor Road ( KM.) (in prorgress) | 2 5116 Gauchar-Sidoli Motor Raod (23.400 KM.) (in prorgress) |
|
Procurement: |
Package No.: 1052
Package Name: UEAP/PWD/C49
Tender Date: 26-09-2014
Current Status: Agreement signed
Achieved on Date: 22-04-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C49
Contractor Name: R.G. Buildwell.
|
Start Date: 01-05-2015
Intended Completion Date: 15-03-2017
Original End Date: 31-10-2016
|
Total Bond Cost: 160361906 (1603.62 lakhs)
Variation Cost: 42216626.00 (422.17 lakhs) Hence Total Bond Cost is 202578532 (2025.79 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 7216290 for 90 days
LD Analysis for Milestone2: calculated LD is Rs 320724 for 4 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 1.56 KM | 15.51 | 1.56 KM | 0.25 KM | 0.08 | 1.29 | 2. | R/Wall, B/ Wall Type Protection works | 1615.00 m | 244.84 | 1822.00 m | 1625.00 m | 10.68 | 218.05 | 3. | GSB/RBI/G-1 | 2.01 KM | 18.56 | 2.01 KM | 1.89 KM | 0.87 | 17.45 | 4. | G-2 | 5.26 KM | 32.24 | 5.26 KM | 5.09 KM | 1.57 | 31.20 | 5. | G-3 | 10.95 KM | 74.24 | 10.95 KM | 10.22 KM | 3.6 | 69.29 | 6. | BM i/c Prime Coat, Tack Coat | 30.76 KM | 700.47 | 27.81 KM | 25.80 KM | 32.37 | 651.01 | 7. | SDBC i/c Tackcoat | 30.76 KM | 560.52 | 30.76 KM | 28.21 KM | 26.4 | 515.38 | 8. | Cause Way | 11.00 No | 94.50 | 11.00 No | 11.00 No | 4.71 | 94.50 | 9. | Culverts/Scupper | 104.00 No | 13.35 | 102.00 No | 81.00 No | 0.53 | 10.55 | 10. | longitudinal Drain | 32760.00 m | 73.45 | 32760.00 m | 28190.00 m | 3.24 | 63.38 | 11. | Crash Barrier | 2075.00 m | 66.40 | 2075.00 m | 2075.00 m | 3.63 | 66.40 | 12. | Road Furniture | 1878.00 No | 76.55 | 1878.00 No | 1250.00 No | 2.79 | 52.25 | 13. | Other Allied Works & Finishing Work | 4.00 Job | 16.95 | 4.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
1987.58 |
|
90.47 |
1790.75 |
|
Remarks:
No Remarks
Work Program Made On:
11-02-2017
Updation of work program on:
26-02-2017
|
|
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 18-October-2015 | 104.98 lakhs |
2. | 08-November-2015 | 35.45 lakhs |
3. | 08-January-2016 | 18.28 lakhs |
4. | 09-June-2016 | 105.40 lakhs |
5. | 08-July-2016 | 89.07 lakhs |
6. | 22-November-2016 | 75.81 lakhs |
7. | 07-February-2017 | 41.42 lakhs |
8. | 29-April-2017 | 76.58 lakhs |
9. | 09-November-2015 | 98.60 lakhs |
10. | 05-December-2015 | 42.68 lakhs |
11. | 20-February-2016 | 41.80 lakhs |
12. | 11-March-2016 | 175.04 lakhs |
13. | 21-March-2016 | 78.93 lakhs |
14. | 28-April-2016 | 106.31 lakhs |
15. | 09-May-2016 | 155.66 lakhs |
16. | 23-October-2016 | 199.65 lakhs |
17. | 17-January-2017 | 94.32 lakhs |
18. | 07-March-2017 | 36.49 lakhs |
19. | 24-March-2017 | 113.27 lakhs |
20. | 06-June-2017 | 97.45 lakhs |
21. | 17-June-2017 | 10.51 lakhs |
Total |
1797.7 lakhs |
% Payment |
88.74 % |
|
Advance Amount: 41.65 lakhs
Recovered Amount: 115.73 lakhs
Balance to be Recovered -74.08 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | PUC vehicles, workmen Insurance | Environment & Social Compliances(Sub Project level): | Karanprayag- Nauti- Paithani Motor Road(5115) | No Pending Issue | Gauchar-Sidoli Motor Raod(5116) | No Pending Issue |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 32 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-12-2016 | C49 (Gauchar Sidoli)/13+00 v/s | PCC M15 work in progress in cc Road. | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
2. | 05-12-2016 | Km 13 ( Ch. 12+720), Gauchar Sidoli motor road. | Concrete work in CC road. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
3. | 02-12-2016 | C49 (gauchar siddoli | R.c.c. M15 work in progress in cc road at chainage12+730. | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
4. | 18-11-2016 | 15+500 | Excavation work is on progress | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
5. | 16-11-2016 | C49/15+500 | Excavation work in progress | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
6. | 11-11-2016 | 39+750 | Bush cutting work is on progress | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
7. | 11-11-2016 | 39+610 | Thermoplastic has been completed | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
8. | 09-11-2016 | C49 Gauchar Sidoli/6+100 | Crash barrier work in progress above chainage. | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
9. | 09-11-2016 | 12+500 | Tree guard fixed at site | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
10. | 05-11-2016 | C49 Gauchar Sidoli (Gwad)/22+560 | Road cutting work in progress Hillside. | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
11. | 04-11-2016 | Km 23 (CH. 22+500 approx.), Gauchar Sidoli motor road. | Hill side cutting work in progress. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
12. | 20-10-2016 | 40+400 | Take measurement of bm | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
13. | 16-10-2016 | Km 41.100, Karnprayag Nauti Paithani motor road. | BC work in progress freshly laid surface. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
14. | 16-10-2016 | Km 41.020, Karnprayag Nauti Paithani motor road. | BC work laid surface thickness checking by SE UEAP Srinagar. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
15. | 16-10-2016 | Km 40.950, Karnprayag Nauti Paithani motor road. | BM work laid surface thickness checking by SE UEAP Srinagar. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
16. | 16-10-2016 | 41+025 | Site visit of cp singh se sir | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
17. | 16-10-2016 | 41+000 | Site vistit of se sir and BC work is on progress....! | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
18. | 15-10-2016 | 41+500 | Bc work at curve | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
19. | 08-10-2016 | Km 1.550, Gauchar Sidoli motor road. | Breast wall under construction. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
20. | 07-10-2016 | C49 K.N.P./41+150 | B.M. work in progress. | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
|
|