                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C49 Agreement signed
Project: UEAP-RB Package No.: 1052 Package Name: UEAP/PWD/C49 Sanction Cost: 1646.00  lakhs
District: Chamoli Block: Karnaprayag Constituency: Karanprayag Circle:
DEA: DEA UEAP Chamoli DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design and Supervision No.of Sub project : 2
Subproject in this package
1  5115   Karanprayag- Nauti- Paithani Motor Road ( KM.) (in prorgress)
2  5116   Gauchar-Sidoli Motor Raod (23.400 KM.) (in prorgress)
Procurement:
Package No.: 1052        Package Name: UEAP/PWD/C49        Tender Date: 26-09-2014        Current Status: Agreement signed        Achieved on Date: 22-04-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C49        Contractor Name: R.G. Buildwell.       
Start Date: 01-05-2015        Intended Completion Date: 15-03-2017        Original End Date:  31-10-2016
Total Bond Cost: 160361906 (1603.62 lakhs)        Variation Cost: 42216626.00 (422.17 lakhs)     Hence Total Bond Cost is   202578532 (2025.79 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 7216290 for 90 days        LD Analysis for Milestone2: calculated LD is Rs 320724 for 4 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence1.56 KM15.511.56 KM0.25 KM0.081.29
2.R/Wall, B/ Wall Type Protection works1615.00 m244.841822.00 m1625.00 m10.68218.05
3.GSB/RBI/G-12.01 KM18.562.01 KM1.89 KM0.8717.45
4.G-25.26 KM32.245.26 KM5.09 KM1.5731.20
5.G-310.95 KM74.2410.95 KM10.22 KM3.669.29
6.BM i/c Prime Coat, Tack Coat30.76 KM700.4727.81 KM25.80 KM32.37651.01
7.SDBC i/c Tackcoat30.76 KM560.5230.76 KM28.21 KM26.4515.38
8.Cause Way11.00 No94.5011.00 No11.00 No4.7194.50
9.Culverts/Scupper 104.00 No13.35102.00 No81.00 No0.5310.55
10.longitudinal Drain32760.00 m73.4532760.00 m28190.00 m3.2463.38
11.Crash Barrier2075.00 m66.402075.00 m2075.00 m3.6366.40
12.Road Furniture1878.00 No76.551878.00 No1250.00 No2.7952.25
13.Other Allied Works & Finishing Work 4.00 Job16.954.00 Job0.00 Job00.00
Total Amount: 1987.58 90.47   1790.75
Remarks: No Remarks       Work Program Made On: 11-02-2017       Updation of work program on: 26-02-2017      
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired.
Financial Progress
SNo. Date Payment
1.18-October-2015104.98  lakhs
2.08-November-201535.45  lakhs
3.08-January-201618.28  lakhs
4.09-June-2016105.40  lakhs
5.08-July-201689.07  lakhs
6.22-November-201675.81  lakhs
7.07-February-201741.42  lakhs
8.29-April-201776.58  lakhs
9.09-November-201598.60  lakhs
10.05-December-201542.68  lakhs
11.20-February-201641.80  lakhs
12.11-March-2016175.04  lakhs
13.21-March-201678.93  lakhs
14.28-April-2016106.31  lakhs
15.09-May-2016155.66  lakhs
16.23-October-2016199.65  lakhs
17.17-January-201794.32  lakhs
18.07-March-201736.49  lakhs
19.24-March-2017113.27  lakhs
20.06-June-201797.45  lakhs
21.17-June-201710.51  lakhs
Total 1797.7  lakhs
% Payment 88.74 %
Advance Amount:  41.65  lakhs        Recovered Amount:  115.73  lakhs        Balance to be Recovered  -74.08  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles, workmen Insurance
Environment & Social Compliances(Sub Project level):
Karanprayag- Nauti- Paithani Motor Road(5115)No Pending Issue
Gauchar-Sidoli Motor Raod(5116)No Pending Issue
Detailed report of this Package
Quality
No. of Test Required : 493     No. of Test Done : 652      No. of Test Passed : 652      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 32
Number of Notice(s) issued: 68

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.24-12-2016C49 (Gauchar Sidoli)/13+00 v/sPCC M15 work in progress in cc Road.Govind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
2.05-12-2016Km 13 ( Ch. 12+720), Gauchar Sidoli motor road.Concrete work in CC road.Atul ShandilyaAEUEAP R&B Chamoli See Pic
3.02-12-2016C49 (gauchar siddoliR.c.c. M15 work in progress in cc road at chainage12+730.Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
4.18-11-201615+500Excavation work is on progressPrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
5.16-11-2016C49/15+500Excavation work in progressGovind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
6.11-11-201639+750Bush cutting work is on progressPrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
7.11-11-201639+610Thermoplastic has been completedPrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
8.09-11-2016C49 Gauchar Sidoli/6+100Crash barrier work in progress above chainage.Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
9.09-11-201612+500Tree guard fixed at sitePrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
10.05-11-2016C49 Gauchar Sidoli (Gwad)/22+560Road cutting work in progress Hillside.Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
11.04-11-2016Km 23 (CH. 22+500 approx.), Gauchar Sidoli motor road.Hill side cutting work in progress.Atul ShandilyaAEUEAP R&B Chamoli See Pic
12.20-10-201640+400Take measurement of bmPrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
13.16-10-2016Km 41.100, Karnprayag Nauti Paithani motor road.BC work in progress freshly laid surface.Atul ShandilyaAEUEAP R&B Chamoli See Pic
14.16-10-2016Km 41.020, Karnprayag Nauti Paithani motor road.BC work laid surface thickness checking by SE UEAP Srinagar.Atul ShandilyaAEUEAP R&B Chamoli See Pic
15.16-10-2016Km 40.950, Karnprayag Nauti Paithani motor road.BM work laid surface thickness checking by SE UEAP Srinagar.Atul ShandilyaAEUEAP R&B Chamoli See Pic
16.16-10-201641+025Site visit of cp singh se sirPrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
17.16-10-201641+000Site vistit of se sir and BC work is on progress....!Prabhansh SrivastavaJEUEAP R&B Chamoli See Pic
18.15-10-201641+500Bc work at curvePrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
19.08-10-2016Km 1.550, Gauchar Sidoli motor road.Breast wall under construction.Atul ShandilyaAEUEAP R&B Chamoli See Pic
20.07-10-2016C49 K.N.P./41+150B.M. work in progress.Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic