UEAP/PWD/C48
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1051 |
Package Name: |
UEAP/PWD/C48 |
Sanction Cost: |
90.00 lakhs |
District: |
Almora |
Block: |
Bhikiyasain |
Constituency: |
Dwarahat |
Circle: |
|
DEA: |
DEA UEAP Almora |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5808 Jalikhan-Nobara (11.330 KM.) (in prorgress) |
|
Procurement: |
Package No.: 1051
Package Name: UEAP/PWD/C48
Tender Date: 03-05-2014
Current Status: Agreement signed
Achieved on Date: 15-09-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C48
Contractor Name: Zender Engineers Ltd
|
Start Date: 17-12-2014
Intended Completion Date: 16-12-2015
|
Total Bond Cost: 7008289 (70.08 lakhs)
Variation Cost: 1560354.83 (15.6 lakhs) Hence Total Bond Cost is 8568643.83 (85.69 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 150672 for 43 days
LD Analysis for Milestone2: calculated LD is Rs 406464 for 116 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 1.00 KM | 0.31 | 1.00 KM | 0.00 KM | 0 | 0.00 | 2. | R/Wall, B/ Wall Type Protection works | 3500.00 m | 48.84 | 3500.00 m | 3500.00 m | 56.88 | 48.84 | 3. | GSB/RBI/G-1 | 0.15 KM | 0.57 | 0.15 KM | 0.15 KM | 0.66 | 0.57 | 4. | G-2 | 0.15 KM | 0.58 | 0.15 KM | 0.14 KM | 0.63 | 0.54 | 5. | G-3 | 0.15 KM | 1.18 | 0.15 KM | 0.14 KM | 1.28 | 1.10 | 6. | PC/CC i/c Prime Coat, Tack Coat | 0.14 KM | 7.03 | 0.14 KM | 0.00 KM | 0 | 0.00 | 7. | Culverts/Scupper | 4.00 No | 10.75 | 4.00 No | 4.00 No | 12.52 | 10.75 | 8. | longitudinal Drain | 4500.00 m | 4.75 | 4500.00 m | 4500.00 m | 5.53 | 4.75 | 9. | Parapet | 200.00 No | 10.92 | 200.00 No | 200.00 No | 12.72 | 10.92 | 10. | Other Allied Works & Finishing Work | 1.00 Job | 0.94 | 1.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
85.87 |
|
90.22 |
77.47 |
|
Remarks:
Work Program Made On:
05-04-2017
Updation of work program on:
20-09-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2015 | 9.63 lakhs |
2. | 29-September-2015 | 13.35 lakhs |
3. | 26-November-2015 | 8.82 lakhs |
4. | 01-June-2016 | 41.03 lakhs |
Total |
72.83 lakhs |
% Payment |
85 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Jalikhan-Nobara(5808) | debris disposal, Query |
Detailed report of this Package
|
|
Quality
|
No. of Test Required : 116 No. of Test Done : 120 No. of Test Passed : 91 No. of Test Failed : 0 No. of Test Result Awaited : 27
Test report of this package
|
|
Number of Pics Available on Web Repository: 13 |
Number of Notice(s) issued: 74 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 24-08-2016 | 18+400 | Cousway working in progress | Anil Kumar | JE | UEAP R&B Nainital | See Pic |
2. | 05-05-2016 | Ch 3.100 | Catch pit | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
3. | 05-05-2016 | Ch 2.200 | R/wall and parapet work | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
4. | 04-05-2016 | Ch 5.050 | R/Wall and parapet | Chetan Bhatt | JE | UEAP R&B Almora | See Pic |
5. | 23-04-2015 | Ch8.100of Jalikhan NobaraM/Road | B/Wall in Progress | Ravi Shankar Joshi | AE | UEAB R&B Almora | See Pic |
6. | 23-04-2015 | Ch3.200of Jali khan Nobara M/R | C/O Of Scupper is in progress | Ravi Shankar Joshi | AE | UEAB R&B Almora | See Pic |
7. | 09-03-2015 | Ch.2.525 | Edge wall work in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
8. | 09-03-2015 | Ch.4.500 | Edge Wall work in Progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
9. | 09-03-2015 | Ch.3.125 | Scupper work in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
10. | 08-03-2015 | Ch.8.050 | R/wall work Completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
11. | 08-03-2015 | Ch. 9.870 | R/wall work in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
12. | 08-03-2015 | Ch.2.550 | Scupper Work in Progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
13. | 08-03-2015 | 2.425 | R/wall work Completed | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
|
|