Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UDRP/PWD/03/RD/094 Agreement signed
Project: UDRP-RB Package No.: 105 Package Name: UDRP/PWD/03/RD/094 Sanction Cost: 661.19  lakhs
District: Rudraprayag Block: August Muni Constituency: Rudraprayag Circle: Rudraprayag WB Circle
DEA: DEA Guptkashi DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision No.of Sub project : 3
Subproject in this package
1  2510   Raintoli-Dungra Motor Road (3.000 KM.) (completed)
2  2527   Kandai-Barangana Motor Road (4.400 KM.) (completed)
3  2529   Khedakhal- Navasu-Hariyali Motor Road (2.000 KM.) (completed)
Procurement:
Package No.: 105        Package Name: UDRP/PWD/03/RD/094        Tender Date: 18-03-2015        Current Status: Agreement signed        Achieved on Date: 21-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/03/RD/094        Contractor Name: Rajendra Singh Kuldeep Singh       
Start Date: 28-09-2015        Intended Completion Date: 31-08-2017        Original End Date:  27-12-2016
Total Bond Cost: 60882905.22 (608.83 lakhs)        Variation Cost: 3951257.62 (39.51 lakhs)     Hence Total Bond Cost is   64834162.84 (648.34 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2404839 for 79 days        LD Analysis for Milestone2: calculated LD is Rs 5418498 for 178 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works1460.00 m129.401460.00 m1460.00 m26.02129.40
2.GSB/RBI/G-14.10 KM35.014.10 KM4.10 KM5.9335.01
3.G-211.70 KM53.2311.70 KM11.70 KM10.1853.23
4.G-37.90 KM67.747.90 KM7.90 KM12.9367.74
5.PC/CC i/c Prime Coat, Tack Coat8.80 KM126.838.80 KM8.80 KM24.22126.83
6.Culverts/Scupper 24.00 No26.6224.00 No24.00 No4.9826.62
7.longitudinal Drain8575.00 m28.058575.00 m8575.00 m5.3528.05
8.Crash Barrier478.00 m5.93478.00 m478.00 m1.055.93
9.Parapet255.00 No8.22255.00 No255.00 No1.478.22
10.Road Furniture71.00 No19.6671.00 No71.00 No3.2819.66
11.Hill side Cutting & Slip clearence4.00 KM16.854.00 KM4.00 KM3.6116.85
12.Cause Way2.00 No4.552.00 No2.00 No0.974.55
Total Amount: 522.09 100   522.09
Remarks: No Remarks       Work Program Made On: 17-11-2015       Updation of work program on: 25-09-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.07-November-201511.29  lakhs
2.28-November-201516.09  lakhs
3.29-February-201621.06  lakhs
4.18-July-201625.59  lakhs
5.30-August-201621.65  lakhs
6.25-September-201615.02  lakhs
7.26-October-201614.05  lakhs
8.24-December-201630.57  lakhs
9.28-February-201758.63  lakhs
10.30-March-201747.23  lakhs
11.18-May-201754.95  lakhs
12.25-May-201733.84  lakhs
13.07-July-201723.07  lakhs
14.31-July-201759.52  lakhs
15.23-September-201743.91  lakhs
16.18-November-201748.73  lakhs
17.26-December-201518.47  lakhs
18.28-January-201622.35  lakhs
19.25-May-201636.22  lakhs
20.29-June-201645.87  lakhs
Total 648.11  lakhs
% Payment 99.96 %
Advance Amount:  104.19  lakhs        Recovered Amount:  104.19  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 267     No. of Test Done : 298      No. of Test Passed : 280      No. of Test Failed : 18   Test report of this package
Number of Pics Available on Web Repository: 222
Number of Notice(s) issued: 71

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.09-11-20170+950Work completedPrashant KumarQCDSC WB SPW Rudraprayag See Pic
2.05-08-20173+200SrmdPrashant KumarQCDSC WB SPW Rudraprayag See Pic
3.01-07-20170+100Geologist inspection at kandai barangna motor road with QC and AENaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
4.15-05-2017Chainage 1+080Laying of premix carpetParvindar SinghJEUDRP R&B Guptkashi See Pic
5.08-05-2017Chainage 1+920Laying of sealcoat type CParvindar SinghJEUDRP R&B Guptkashi See Pic
6.06-05-20171+400Seal coat layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
7.06-05-20171+550Rolling of premix carpetNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
8.05-05-2017Chainage 1+320Laying of premix carpetParvindar SinghJEUDRP R&B Guptkashi See Pic
9.05-05-2017Chainage 2+220Laying of premix carpetParvindar SinghJEUDRP R&B Guptkashi See Pic
10.29-04-2017Chainage 2+350Laying of sealcoatParvindar SinghJEUDRP R&B Guptkashi See Pic
11.29-04-20172+300Laying of pcParvindar SinghJEUDRP R&B Guptkashi See Pic
12.27-04-20172+700Seal coat laying and rollingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
13.18-04-2017Chainage 2+580Laying and compaction of wbm grading-3Parvindar SinghJEUDRP R&B Guptkashi See Pic
14.18-04-2017Change 1+330Laying of premix carpetParvindar SinghJEUDRP R&B Guptkashi See Pic
15.04-04-2017Chainage 1+300Laying of premix carpetParvindar SinghJEUDRP R&B Guptkashi See Pic
16.01-04-2017Chainage 1+970Laying of premix carpetParvindar SinghJEUDRP R&B Guptkashi See Pic
17.31-03-20171+620Premix carpet layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
18.30-03-20171+550Seal coat layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
19.30-03-20171+750Premix carpet layingNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic
20.29-03-2017Labour hutsSE sir inspection at labour hutsNaresh Kumar RathorAEUDRP R&B Guptkashi See Pic