UDRP/PWD/03/RD/094
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
105 |
Package Name: |
UDRP/PWD/03/RD/094 |
Sanction Cost: |
661.19 lakhs |
District: |
Rudraprayag |
Block: |
August Muni |
Constituency: |
Rudraprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Guptkashi |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
No.of Sub project : |
3 |
Subproject in this package |
1 2510 Raintoli-Dungra Motor Road (3.000 KM.) (completed) | 2 2527 Kandai-Barangana Motor Road (4.400 KM.) (completed) | 3 2529 Khedakhal- Navasu-Hariyali Motor Road (2.000 KM.) (completed) |
|
Procurement: |
Package No.: 105
Package Name: UDRP/PWD/03/RD/094
Tender Date: 18-03-2015
Current Status: Agreement signed
Achieved on Date: 21-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/03/RD/094
Contractor Name: Rajendra Singh Kuldeep Singh
|
Start Date: 28-09-2015
Intended Completion Date: 31-08-2017
Original End Date: 27-12-2016
|
Total Bond Cost: 60882905.22 (608.83 lakhs)
Variation Cost: 3951257.62 (39.51 lakhs) Hence Total Bond Cost is 64834162.84 (648.34 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2404839 for 79 days
LD Analysis for Milestone2: calculated LD is Rs 5418498 for 178 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 1460.00 m | 129.40 | 1460.00 m | 1460.00 m | 26.02 | 129.40 | 2. | GSB/RBI/G-1 | 4.10 KM | 35.01 | 4.10 KM | 4.10 KM | 5.93 | 35.01 | 3. | G-2 | 11.70 KM | 53.23 | 11.70 KM | 11.70 KM | 10.18 | 53.23 | 4. | G-3 | 7.90 KM | 67.74 | 7.90 KM | 7.90 KM | 12.93 | 67.74 | 5. | PC/CC i/c Prime Coat, Tack Coat | 8.80 KM | 126.83 | 8.80 KM | 8.80 KM | 24.22 | 126.83 | 6. | Culverts/Scupper | 24.00 No | 26.62 | 24.00 No | 24.00 No | 4.98 | 26.62 | 7. | longitudinal Drain | 8575.00 m | 28.05 | 8575.00 m | 8575.00 m | 5.35 | 28.05 | 8. | Crash Barrier | 478.00 m | 5.93 | 478.00 m | 478.00 m | 1.05 | 5.93 | 9. | Parapet | 255.00 No | 8.22 | 255.00 No | 255.00 No | 1.47 | 8.22 | 10. | Road Furniture | 71.00 No | 19.66 | 71.00 No | 71.00 No | 3.28 | 19.66 | 11. | Hill side Cutting & Slip clearence | 4.00 KM | 16.85 | 4.00 KM | 4.00 KM | 3.61 | 16.85 | 12. | Cause Way | 2.00 No | 4.55 | 2.00 No | 2.00 No | 0.97 | 4.55 |
Total Amount: |
522.09 |
|
100 |
522.09 |
|
Remarks:
No Remarks
Work Program Made On:
17-11-2015
Updation of work program on:
25-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 07-November-2015 | 11.29 lakhs |
2. | 28-November-2015 | 16.09 lakhs |
3. | 29-February-2016 | 21.06 lakhs |
4. | 18-July-2016 | 25.59 lakhs |
5. | 30-August-2016 | 21.65 lakhs |
6. | 25-September-2016 | 15.02 lakhs |
7. | 26-October-2016 | 14.05 lakhs |
8. | 24-December-2016 | 30.57 lakhs |
9. | 28-February-2017 | 58.63 lakhs |
10. | 30-March-2017 | 47.23 lakhs |
11. | 18-May-2017 | 54.95 lakhs |
12. | 25-May-2017 | 33.84 lakhs |
13. | 07-July-2017 | 23.07 lakhs |
14. | 31-July-2017 | 59.52 lakhs |
15. | 23-September-2017 | 43.91 lakhs |
16. | 18-November-2017 | 48.73 lakhs |
17. | 26-December-2015 | 18.47 lakhs |
18. | 28-January-2016 | 22.35 lakhs |
19. | 25-May-2016 | 36.22 lakhs |
20. | 29-June-2016 | 45.87 lakhs |
Total |
648.11 lakhs |
% Payment |
99.96 % |
|
Advance Amount: 104.19 lakhs
Recovered Amount: 104.19 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 222 |
Number of Notice(s) issued: 71 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 09-11-2017 | 0+950 | Work completed | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
2. | 05-08-2017 | 3+200 | Srmd | Prashant Kumar | QC | DSC WB SPW Rudraprayag | See Pic |
3. | 01-07-2017 | 0+100 | Geologist inspection at kandai barangna motor road with QC and AE | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
4. | 15-05-2017 | Chainage 1+080 | Laying of premix carpet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
5. | 08-05-2017 | Chainage 1+920 | Laying of sealcoat type C | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
6. | 06-05-2017 | 1+400 | Seal coat laying | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
7. | 06-05-2017 | 1+550 | Rolling of premix carpet | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
8. | 05-05-2017 | Chainage 1+320 | Laying of premix carpet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
9. | 05-05-2017 | Chainage 2+220 | Laying of premix carpet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
10. | 29-04-2017 | Chainage 2+350 | Laying of sealcoat | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
11. | 29-04-2017 | 2+300 | Laying of pc | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
12. | 27-04-2017 | 2+700 | Seal coat laying and rolling | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
13. | 18-04-2017 | Chainage 2+580 | Laying and compaction of wbm grading-3 | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
14. | 18-04-2017 | Change 1+330 | Laying of premix carpet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
15. | 04-04-2017 | Chainage 1+300 | Laying of premix carpet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
16. | 01-04-2017 | Chainage 1+970 | Laying of premix carpet | Parvindar Singh | JE | UDRP R&B Guptkashi | See Pic |
17. | 31-03-2017 | 1+620 | Premix carpet laying | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
18. | 30-03-2017 | 1+550 | Seal coat laying | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
19. | 30-03-2017 | 1+750 | Premix carpet laying | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
20. | 29-03-2017 | Labour huts | SE sir inspection at labour huts | Naresh Kumar Rathor | AE | UDRP R&B Guptkashi | See Pic |
|
|