UEAP/PWD/C39
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1042 |
Package Name: |
UEAP/PWD/C39 |
Sanction Cost: |
431.00 lakhs |
District: |
Tehri |
Block: |
Narendra Nagar |
Constituency: |
Narendra Nagar |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5304 Gaza-Nakot (16.000 KM.) (completed) |
|
Procurement: |
Package No.: 1042
Package Name: UEAP/PWD/C39
Tender Date: 26-04-2014
Current Status: Agreement signed
Achieved on Date: 20-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C39
Contractor Name: Shiv Shankar Construction Company
|
Start Date: 10-11-2014
Intended Completion Date: 09-05-2016
|
Total Bond Cost: 37684616 (376.85 lakhs)
Variation Cost: 5115499.58 (51.15 lakhs) Hence Total Bond Cost is 42800115.58 (428 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.51 KM | 3.47 | 0.51 KM | 0.51 KM | 0.93 | 3.47 | 2. | R/Wall, B/ Wall Type Protection works | 1482.00 m | 36.98 | 1482.00 m | 1482.00 m | 9.91 | 36.98 | 3. | GSB/RBI/G-1 | 0.13 KM | 0.57 | 0.13 KM | 0.13 KM | 0.15 | 0.57 | 4. | G-2 | 0.13 KM | 0.45 | 0.13 KM | 0.13 KM | 0.12 | 0.45 | 5. | G-3 | 0.13 KM | 0.48 | 0.13 KM | 0.13 KM | 0.13 | 0.48 | 6. | BM i/c Prime Coat, Tack Coat | 1.10 KM | 28.23 | 1.10 KM | 1.10 KM | 7.56 | 28.23 | 7. | SDBC i/c Tackcoat | 11.00 KM | 139.48 | 11.00 KM | 11.00 KM | 37.36 | 139.48 | 8. | Culverts/Scupper | 10.00 No | 20.99 | 10.00 No | 10.00 No | 5.62 | 20.99 | 9. | longitudinal Drain | 20000.00 m | 14.44 | 20000.00 m | 20000.00 m | 3.87 | 14.44 | 10. | Crash Barrier | 3750.00 m | 88.20 | 3750.00 m | 3750.00 m | 23.63 | 88.20 | 11. | Parapet | 475.00 No | 12.65 | 475.00 No | 475.00 No | 3.39 | 12.65 | 12. | Road Furniture | 1072.00 No | 27.39 | 1072.00 No | 1072.00 No | 7.34 | 27.39 |
Total Amount: |
373.33 |
|
100 |
373.33 |
|
Remarks:
No Remarks
Work Program Made On:
26-02-2015
Updation of work program on:
22-07-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-December-2014 | 7.97 lakhs |
2. | 10-February-2015 | 35.75 lakhs |
3. | 09-March-2015 | 49.42 lakhs |
4. | 26-March-2015 | 7.00 lakhs |
5. | 29-May-2015 | 190.23 lakhs |
6. | 26-June-2015 | 29.31 lakhs |
7. | 07-November-2015 | 12.63 lakhs |
8. | 15-January-2016 | 30.91 lakhs |
9. | 29-February-2016 | 23.21 lakhs |
10. | 05-May-2016 | 30.75 lakhs |
11. | 29-July-2017 | 2.23 lakhs |
Total |
419.41 lakhs |
% Payment |
97.99 % |
|
Advance Amount: 52.62 lakhs
Recovered Amount: 52.62 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 27 |
Number of Notice(s) issued: 75 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 14-01-2016 | ch.19+025 | Core cutting | Asha rawat | JE | DEA ADB Dehradun | See Pic |
2. | 09-05-2015 | 13+700 | Laying of B.M | Asha rawat | JE | DEA ADB Dehradun | See Pic |
3. | 09-05-2015 | km17 | Laying of Tack coat | Asha rawat | JE | DEA ADB Dehradun | See Pic |
4. | 09-05-2015 | Km17 | Laying of SDBC | Asha rawat | JE | DEA ADB Dehradun | See Pic |
5. | 24-04-2015 | 0+150 | Compaction for BM laying surface | Sudarshan kumar | PME | DSC3 ADB | See Pic |
6. | 24-04-2015 | C-39 ch. 0+350 | Cleaning by Compressor for SDBC laying | Sudarshan kumar | PME | DSC3 ADB | See Pic |
7. | 24-04-2015 | C-39 ghaza - nakot | SDBC laying in progress | Sudarshan kumar | PME | DSC3 ADB | See Pic |
8. | 24-04-2015 | Hot mix plant runing for BM/ SDBC | HMP | Sudarshan kumar | PME | DSC3 ADB | See Pic |
9. | 08-04-2015 | HMP | Materials for bituminous work at plant site in c-39 is satisfied | Jitendra Kumar | RE | DSC3 ADB | See Pic |
10. | 08-04-2015 | HMP | Installation of hmp has completed c-39 | Jitendra Kumar | RE | DSC3 ADB | See Pic |
11. | 08-04-2015 | HMP | Installation of hmp is ok in gaja nakot rd c-39 | Jitendra Kumar | RE | DSC3 ADB | See Pic |
12. | 02-04-2015 | Install of HMP in prog | Gaza- Nakot c-39 | Jitendra Kumar | RE | DSC3 ADB | See Pic |
13. | 02-04-2015 | Material collection in program at HMP camp | Gaza-Nakot C-39 | Jitendra Kumar | RE | DSC3 ADB | See Pic |
14. | 24-03-2015 | 6+560 to 7+000 | Excavation of foundation for MBC in prog. | Jitendra Kumar | RE | DSC3 ADB | See Pic |
15. | 24-03-2015 | 2+200to6+560 | Cement used for concrete mix in foundations of MBC | Jitendra Kumar | RE | DSC3 ADB | See Pic |
16. | 24-03-2015 | 2+200to6+560 | MBC work in gaza-Nakoi c39 | Jitendra Kumar | RE | DSC3 ADB | See Pic |
17. | 24-03-2015 | 6+280to6+560 | MBC in prog gaza-nakot c39 | Jitendra Kumar | RE | DSC3 ADB | See Pic |
18. | 24-03-2015 | 2+200to6+560 | MBC work in prog gaza-Nakot C-39 | Jitendra Kumar | RE | DSC3 ADB | See Pic |
19. | 23-03-2015 | HMP in km78 of NH-94 | HMP is established for gaza nakot m/road | Shankar Ram | SE | ADB Circle | See Pic |
20. | 09-03-2015 | Km-7 | Constn of parapets is in progress | Shankar Ram | SE | ADB Circle | See Pic |
|
|