Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C37 Agreement signed
Project: UEAP-RB Package No.: 1040 Package Name: UEAP/PWD/C37 Sanction Cost: 845.00  lakhs
District: Uttarkashi Block: Puraula Constituency: Purola Circle:
DEA: DEA UEAP Uttarkashi DSC: Royal Haskoning DHV DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5003   Tyuni-Mori-Purola-Naugaon (32.000 KM.) (completed)
Procurement:
Package No.: 1040        Package Name: UEAP/PWD/C37        Tender Date: 16-10-2014        Current Status: Agreement signed        Achieved on Date: 16-03-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C37        Contractor Name: SS Infratech       
Start Date: 06-04-2015        Intended Completion Date: 26-05-2017        Original End Date:  05-10-2016
Total Bond Cost: 83662453.21 (836.62 lakhs)        Variation Cost: 602840.20 (6.03 lakhs)     Hence Total Bond Cost is   84265293.41 (842.65 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 7613242 for +182 days        LD Analysis for Milestone2: calculated LD is Rs 8826341 for 211 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.45 KM0.990.45 KM0.45 KM0.120.99
2.R/Wall, B/ Wall Type Protection works600.00 m55.02600.00 m600.00 m6.5355.02
3.GSB/RBI/G-10.13 KM0.470.13 KM0.13 KM0.060.47
4.G-20.75 KM0.800.75 KM0.75 KM0.10.80
5.G-30.75 KM0.640.75 KM0.75 KM0.080.64
6.BM i/c Prime Coat, Tack Coat1.50 KM2.821.50 KM1.50 KM0.332.82
7.SDBC i/c Tackcoat32.00 KM474.8832.00 KM32.00 KM56.37474.88
8.longitudinal Drain3250.00 m33.153250.00 m3250.00 m3.9433.15
9.Crash Barrier500.00 m13.19500.00 m500.00 m1.5713.19
10.Parapet1250.00 No163.841250.00 No1250.00 No19.45163.84
11.Road Furniture4020.00 No74.304020.00 No4020.00 No8.8274.30
12.Other Allied Works & Finishing Work 1.00 Job22.411.00 Job1.00 Job2.6622.41
Total Amount: 842.51 100   842.51
Remarks:        Work Program Made On: 13-06-2015       Updation of work program on: 25-07-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.25-June-201524.55  lakhs
2.28-October-201523.10  lakhs
3.30-November-201536.65  lakhs
4.22-January-201612.03  lakhs
5.31-March-201619.23  lakhs
6.29-April-20168.72  lakhs
7.17-May-2016116.25  lakhs
8.17-June-201676.76  lakhs
9.20-October-201648.68  lakhs
10.28-October-201641.93  lakhs
11.07-December-201675.94  lakhs
12.27-February-201722.19  lakhs
13.16-May-201755.12  lakhs
14.09-June-2017111.18  lakhs
15.27-June-201753.78  lakhs
Total 726.11  lakhs
% Payment 86.17 %
Advance Amount:  38.66  lakhs        Recovered Amount:  38.66  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1768     No. of Test Done : 1755      No. of Test Passed : 1754      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 13
Number of Notice(s) issued: 69

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.18-06-201521+415R/wall completedBheem Singh MeharJEDEA ADB Uttarkashi See Pic
2.18-06-201522+740RR dry with two plum completed.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
3.18-06-201524+635 to 645R/wall with plum completed.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
4.18-06-201530+225R/W completed with plumBheem Singh MeharJEDEA ADB Uttarkashi See Pic
5.18-06-201526+925 to 944RR dry completed.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
6.17-06-201522+825RR dry with 4 no plum completed.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
7.02-05-201523+260Construction of plum concrete.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
8.02-05-201520+400Plum concrete in progressBheem Singh MeharJEDEA ADB Uttarkashi See Pic
9.02-05-201524+780R/wall in complete.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
10.02-05-201530+910Protection work in complete.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
11.20-04-201523+340Excavation of R/wallBheem Singh MeharJEDEA ADB Uttarkashi See Pic
12.20-04-201530+110R/wall in progressBheem Singh MeharJEDEA ADB Uttarkashi See Pic
13.14-04-201523+24Construction of R/wallBheem Singh MeharJEDEA ADB Uttarkashi See Pic