UDRP/PWD/07/15/RD/093
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
104 |
Package Name: |
UDRP/PWD/07/15/RD/093 |
Sanction Cost: |
668.57 lakhs |
District: |
Pithoragarh |
Block: |
Pithoragarh(Bin) |
Constituency: |
Pithoragarh |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Askot |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 2370 Acholi jaakh (8.000 KM.) (completed) | 2 2419 jaakh meladungari (7.000 KM.) (completed) |
|
Procurement: |
Package No.: 104
Package Name: UDRP/PWD/07/15/RD/093
Tender Date: 18-02-2015
Current Status: Agreement signed
Achieved on Date: 01-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/07/15/RD/093
Contractor Name: M & P Infrastructure
|
Start Date: 08-07-2015
Intended Completion Date: 01-11-2018
Original End Date: 07-10-2016
|
Total Bond Cost: 66856998.32 (668.57 lakhs)
Variation Cost: 3385916.26 (33.86 lakhs) Hence Total Bond Cost is 70242914.58 (702.43 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 3409656 for 102 days
LD Analysis for Milestone2: calculated LD is Rs 8390428 for 251 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 4.24 KM | 57.44 | 4.24 KM | 4.24 KM | 8.46 | 57.44 | 2. | R/Wall, B/ Wall Type Protection works | 1467.35 m | 146.54 | 1644.00 m | 1644.00 m | 21.07 | 146.54 | 3. | G-2 | 2.60 KM | 37.92 | 1.30 KM | 1.30 KM | 5.15 | 37.92 | 4. | G-3 | 7.50 KM | 47.75 | 7.50 KM | 7.50 KM | 6.5 | 47.75 | 5. | BM i/c Prime Coat, Tack Coat | 1.00 KM | 32.37 | 0.94 KM | 0.94 KM | 5.19 | 32.37 | 6. | SDBC i/c Tackcoat | 7.70 KM | 114.96 | 7.58 KM | 7.58 KM | 18.43 | 114.96 | 7. | Cause Way | 2.00 No | 12.84 | 2.00 No | 2.00 No | 2.06 | 12.84 | 8. | Culverts/Scupper | 14.00 No | 33.43 | 12.00 No | 12.00 No | 4.94 | 33.43 | 9. | longitudinal Drain | 13275.80 m | 24.92 | 13786.80 m | 13786.80 m | 3.76 | 24.92 | 10. | Crash Barrier | 650.00 m | 31.57 | 2640.00 m | 2640.00 m | 4.62 | 31.57 | 11. | Parapet | 400.00 No | 6.22 | 104.00 No | 104.00 No | 0.92 | 6.22 | 12. | Road Furniture | 236.00 No | 17.27 | 236.00 No | 236.00 No | 2.58 | 17.27 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 15.18 | 1.00 Job | 1.00 Job | 2.43 | 15.18 | 14. | PC/CC i/c Prime Coat, Tack Coat | 6.50 KM | 102.21 | 6.50 KM | 6.50 KM | 13.88 | 102.21 |
Total Amount: |
680.62 |
|
100 |
680.62 |
|
Remarks:
No Remarks
Work Program Made On:
28-09-2015
Updation of work program on:
16-05-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-October-2015 | 12.39 lakhs |
2. | 23-December-2015 | 16.77 lakhs |
3. | 12-April-2016 | 16.44 lakhs |
4. | 13-May-2016 | 9.65 lakhs |
5. | 30-June-2016 | 16.22 lakhs |
6. | 20-July-2016 | 19.88 lakhs |
7. | 03-September-2016 | 24.25 lakhs |
8. | 27-October-2016 | 18.66 lakhs |
9. | 05-December-2016 | 14.71 lakhs |
10. | 19-December-2016 | 62.67 lakhs |
11. | 31-December-2016 | 65.23 lakhs |
12. | 31-January-2017 | 9.48 lakhs |
13. | 28-February-2017 | 6.72 lakhs |
14. | 31-March-2017 | 6.13 lakhs |
15. | 31-May-2017 | 9.71 lakhs |
16. | 18-June-2017 | 54.15 lakhs |
17. | 11-July-2017 | 21.32 lakhs |
18. | 25-August-2017 | 14.10 lakhs |
19. | 25-October-2017 | 7.37 lakhs |
20. | 16-February-2018 | 78.90 lakhs |
21. | 07-March-2018 | 21.55 lakhs |
22. | 31-May-2018 | 25.35 lakhs |
23. | 23-August-2018 | 35.45 lakhs |
24. | 29-October-2018 | 20.15 lakhs |
25. | 01-November-2018 | 8.00 lakhs |
26. | 30-November-2018 | 15.09 lakhs |
27. | 09-March-2019 | 38.29 lakhs |
28. | 03-November-2017 | 12.58 lakhs |
29. | 17-November-2017 | 20.72 lakhs |
30. | 26-November-2017 | 26.04 lakhs |
31. | 30-November-2017 | 18.19 lakhs |
Total |
726.16 lakhs |
% Payment |
103.38 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 131 |
Number of Notice(s) issued: 83 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-05-2018 | Ch 1.400 | Meeting with gram pradhan by world bank team | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
2. | 16-03-2018 | Cha.4+450 | SDBC core thickness checking third party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
3. | 16-03-2018 | 4+850 | Rolling work progress in PC work | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
4. | 15-03-2018 | Chainage 3+575 | PC & WBM G-3 sample collection for third party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
5. | 15-03-2018 | Chainage 09+475 | WBM G-3 sample collection for third party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
6. | 15-03-2018 | 7+400 | SDBC sample core cutting for third party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
7. | 15-03-2018 | Chainage 4+450 | SDBC sample core cutting for third party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
8. | 15-03-2018 | Chainage 2+500 | SDBC Sample core cutting for third party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
9. | 15-03-2018 | Chainage 1+450 | SDBC sample core cutting for third party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
10. | 15-03-2018 | Chainage 0+500 | SDBC sampal core cutting for thired party test | Tej Singh Kunwar | JE | UDRP R&B Askot | See Pic |
11. | 24-12-2017 | 0+400 | Labour Health checkup | Harish Singh Rajwar | JE | UDRP R&B Askot | See Pic |
12. | 01-12-2017 | 0+400 | Labour Health checkup | Harish Singh Rajwar | JE | UDRP R&B Askot | See Pic |
13. | 01-12-2017 | HMP | Bitumen content of seal coat material Testing at HMP. Found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
14. | 30-11-2017 | HMP | Bitumen content of PC material Testing at HMP | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
15. | 28-11-2017 | Plant site | Preparing PC material by plant | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
16. | 28-11-2017 | Plant site | Checking of bitumen content of PC material | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
17. | 28-11-2017 | Plant site | Finding bitumen content | Satendra Mohan Upadhyay | AE | UDRP R&B Askot | See Pic |
18. | 28-11-2017 | Ch.0+650 | Rolling of PC Laying | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
19. | 26-11-2017 | HMP | Bitumen content of PC material Testing at HMP. Found OK | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
20. | 26-11-2017 | HMP | Bitumen content of PC material Testing at HMP | Abid Ali Siddequee | QC | DSC4 R&B WB Pithoragarh | See Pic |
|
|