Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C36 Agreement signed
Project: UEAP-RB Package No.: 1039 Package Name: UEAP/PWD/C36 Sanction Cost: 917.00  lakhs
District: Tehri Block: Jakhanidhar Constituency: Pratapnagar Circle:
DEA: DEA UEAP Tehri DSC: DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5303   Pratapnagar-Tehri (30.000 KM.) (in prorgress)
Procurement:
Package No.: 1039        Package Name: UEAP/PWD/C36        Tender Date: 16-10-2014        Current Status: Agreement signed        Achieved on Date: 23-02-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C36        Contractor Name: ESPAN Infrastructure Ltd       
Start Date: 19-03-2015        Intended Completion Date: 04-10-2016       
Total Bond Cost: 64955326.7 (649.55 lakhs)        Variation Cost: 22926045.00 (229.26 lakhs)     Hence Total Bond Cost is   87881371.7 (878.81 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2143548 for 66 days        LD Analysis for Milestone2: calculated LD is Rs 389736 for 12 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence3.17 KM12.313.17 KM3.17 KM2.0212.31
2.R/Wall, B/ Wall Type Protection works1665.00 m145.241665.00 m1665.00 m23.78145.24
3.GSB/RBI/G-14.05 KM5.094.05 KM4.05 KM0.835.09
4.G-24.10 KM5.304.10 KM4.10 KM0.875.30
5.G-35.61 KM15.085.61 KM5.61 KM2.4715.08
6.BM i/c Prime Coat, Tack Coat9.00 KM83.449.00 KM9.00 KM13.6683.44
7.SDBC i/c Tackcoat19.69 KM175.0819.69 KM19.69 KM28.66175.08
8.Cause Way2.00 No9.822.00 No2.00 No1.619.82
9.Culverts/Scupper 17.00 No2.8817.00 No17.00 No0.472.88
10.longitudinal Drain11500.00 m13.2511500.00 m11500.00 m2.1713.25
11.Crash Barrier3230.00 m74.293230.00 m3230.00 m12.1674.29
12.Parapet1170.00 No57.901170.00 No1100.00 No8.9154.44
13.Road Furniture1367.00 No11.151367.00 No0.00 No00.00
Total Amount: 610.83 97.61   596.22
Remarks: No Remarks       Work Program Made On: 09-08-2015       Updation of work program on: 09-01-2017      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.24-March-20150.10  lakhs
2.20-June-201522.50  lakhs
3.08-October-201534.26  lakhs
4.22-January-2016150.61  lakhs
5.29-March-201633.55  lakhs
6.29-April-2016195.32  lakhs
7.02-June-201649.93  lakhs
8.25-October-2016108.51  lakhs
9.17-December-2016152.61  lakhs
10.28-March-201745.28  lakhs
11.21-April-201728.07  lakhs
12.17-June-201741.96  lakhs
Total 862.7  lakhs
% Payment 98.17 %
Advance Amount:  65.00  lakhs        Recovered Amount:  65.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level):
Pratapnagar-Tehri(5303) Sanitation Facility, DG set
Detailed report of this Package
Quality
Test Information not Available.
No Pics Available.
Number of Notice(s) issued: 68

Mobile Pic Upload

( last 20 Pics)
No Pic uploaded.