UEAP/PWD/C36
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1039 |
Package Name: |
UEAP/PWD/C36 |
Sanction Cost: |
917.00 lakhs |
District: |
Tehri |
Block: |
Jakhanidhar |
Constituency: |
Pratapnagar |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
|
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5303 Pratapnagar-Tehri (30.000 KM.) (in prorgress) |
|
Procurement: |
Package No.: 1039
Package Name: UEAP/PWD/C36
Tender Date: 16-10-2014
Current Status: Agreement signed
Achieved on Date: 23-02-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C36
Contractor Name: ESPAN Infrastructure Ltd
|
Start Date: 19-03-2015
Intended Completion Date: 04-10-2016
|
Total Bond Cost: 64955326.7 (649.55 lakhs)
Variation Cost: 22926045.00 (229.26 lakhs) Hence Total Bond Cost is 87881371.7 (878.81 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2143548 for 66 days
LD Analysis for Milestone2: calculated LD is Rs 389736 for 12 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 3.17 KM | 12.31 | 3.17 KM | 3.17 KM | 2.02 | 12.31 | 2. | R/Wall, B/ Wall Type Protection works | 1665.00 m | 145.24 | 1665.00 m | 1665.00 m | 23.78 | 145.24 | 3. | GSB/RBI/G-1 | 4.05 KM | 5.09 | 4.05 KM | 4.05 KM | 0.83 | 5.09 | 4. | G-2 | 4.10 KM | 5.30 | 4.10 KM | 4.10 KM | 0.87 | 5.30 | 5. | G-3 | 5.61 KM | 15.08 | 5.61 KM | 5.61 KM | 2.47 | 15.08 | 6. | BM i/c Prime Coat, Tack Coat | 9.00 KM | 83.44 | 9.00 KM | 9.00 KM | 13.66 | 83.44 | 7. | SDBC i/c Tackcoat | 19.69 KM | 175.08 | 19.69 KM | 19.69 KM | 28.66 | 175.08 | 8. | Cause Way | 2.00 No | 9.82 | 2.00 No | 2.00 No | 1.61 | 9.82 | 9. | Culverts/Scupper | 17.00 No | 2.88 | 17.00 No | 17.00 No | 0.47 | 2.88 | 10. | longitudinal Drain | 11500.00 m | 13.25 | 11500.00 m | 11500.00 m | 2.17 | 13.25 | 11. | Crash Barrier | 3230.00 m | 74.29 | 3230.00 m | 3230.00 m | 12.16 | 74.29 | 12. | Parapet | 1170.00 No | 57.90 | 1170.00 No | 1100.00 No | 8.91 | 54.44 | 13. | Road Furniture | 1367.00 No | 11.15 | 1367.00 No | 0.00 No | 0 | 0.00 |
Total Amount: |
610.83 |
|
97.61 |
596.22 |
|
Remarks:
No Remarks
Work Program Made On:
09-08-2015
Updation of work program on:
09-01-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 24-March-2015 | 0.10 lakhs |
2. | 20-June-2015 | 22.50 lakhs |
3. | 08-October-2015 | 34.26 lakhs |
4. | 22-January-2016 | 150.61 lakhs |
5. | 29-March-2016 | 33.55 lakhs |
6. | 29-April-2016 | 195.32 lakhs |
7. | 02-June-2016 | 49.93 lakhs |
8. | 25-October-2016 | 108.51 lakhs |
9. | 17-December-2016 | 152.61 lakhs |
10. | 28-March-2017 | 45.28 lakhs |
11. | 21-April-2017 | 28.07 lakhs |
12. | 17-June-2017 | 41.96 lakhs |
Total |
862.7 lakhs |
% Payment |
98.17 % |
|
Advance Amount: 65.00 lakhs
Recovered Amount: 65.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | PUC vehicles | Environment & Social Compliances(Sub Project level): | Pratapnagar-Tehri(5303) | Sanitation Facility, DG set |
Detailed report of this Package
|
|
Quality
|
Test Information not Available. |
No Pics Available. |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
( last 20 Pics) |
No Pic uploaded. |
|