                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C35 Agreement signed
Project: UEAP-RB Package No.: 1038 Package Name: UEAP/PWD/C35 Sanction Cost: 1386.00  lakhs
District: Pauri Block: Pauri Constituency: Pauri Circle:
DEA: DEA UEAP Pauri DSC: DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5502   Buwakhal-Pauri-Devprayag-Gaja-Jajal (45.000 KM.) (in prorgress)
Procurement:
Package No.: 1038        Package Name: UEAP/PWD/C35        Tender Date: 08-04-2014        Current Status: Agreement signed        Achieved on Date: 13-10-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C35        Contractor Name: Bharat Construction       
Start Date: 20-10-2014        Intended Completion Date: 19-04-2016       
Total Bond Cost: 134093812 (1340.94 lakhs)        Variation Cost: 3365211.98 (33.65 lakhs)     Hence Total Bond Cost is   137459023.98 (1374.59 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 5028525 for 75 days        LD Analysis for Milestone2: calculated LD is Rs 10392285 for 155 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence8.56 KM19.618.56 KM8.56 KM1.4219.61
2.R/Wall, B/ Wall Type Protection works1970.00 m56.471970.00 m1970.00 m4.0856.47
3.GSB/RBI/G-10.10 KM0.280.10 KM0.10 KM0.020.28
4.G-20.10 KM0.130.05 KM0.05 KM0.010.13
5.G-30.19 KM0.910.25 KM0.25 KM0.070.91
6.BM i/c Prime Coat, Tack Coat1.93 KM57.571.93 KM1.93 KM4.1657.57
7.SDBC i/c Tackcoat41.45 KM930.4834.00 KM34.00 KM67.3930.48
8.Cause Way3.00 No6.333.00 No3.00 No0.466.33
9.Culverts/Scupper 2.00 No7.992.00 No0.00 No00.00
10.longitudinal Drain91750.00 m87.7383450.00 m83450.00 m6.3587.73
11.Crash Barrier2830.00 m99.022830.00 m2830.00 m7.1699.02
12.Road Furniture2800.00 No79.163000.00 No2800.00 No5.3473.89
13.Other Allied Works & Finishing Work 1.00 Job36.931.00 Job0.00 Job00.00
Total Amount: 1382.61 96.37   1332.42
Remarks: No Remarks       Work Program Made On: 28-03-2015       Updation of work program on: 28-06-2017      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.21-January-201527.35  lakhs
2.17-March-201510.41  lakhs
3.30-March-201514.49  lakhs
4.23-May-2015113.01  lakhs
5.08-June-201559.38  lakhs
6.20-October-2015225.51  lakhs
7.09-November-201574.83  lakhs
8.15-January-201684.21  lakhs
9.22-March-201640.55  lakhs
10.30-March-2016214.85  lakhs
11.30-April-2016291.25  lakhs
12.15-May-2016174.03  lakhs
13.07-February-201744.71  lakhs
Total 1374.58  lakhs
% Payment 100 %
Advance Amount:  260.20  lakhs        Recovered Amount:  260.20  lakhs        Balance to be Recovered  -0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Buwakhal-Pauri-Devprayag-Gaja-Jajal(5502) project information board, DG set
Detailed report of this Package
Quality
No. of Test Required : 337     No. of Test Done : 438      No. of Test Passed : 437      No. of Test Failed : 1   Test report of this package
Number of Pics Available on Web Repository: 119
Number of Notice(s) issued: 76

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-03-2017Km 35Site visitAlok JainAEUEAP R&B and CA Pauri See Pic
2.16-03-2016Ch 47.925Sdbc in progressAlok JainAEUEAP R&B and CA Pauri See Pic
3.16-03-2016Km 48SDBC in progressAlok JainAEUEAP R&B and CA Pauri See Pic
4.16-03-2016Km 46Pucca drain in progressAlok JainAEUEAP R&B and CA Pauri See Pic
5.16-03-201627.532Core sample takenAlok JainAEUEAP R&B and CA Pauri See Pic
6.16-02-2016Km 44Const of R.WallAlok JainAEUEAP R&B and CA Pauri See Pic
7.25-11-2015Plant site km44Sdbc in progressAlok JainAEUEAP R&B and CA Pauri See Pic
8.09-11-2015C35, Buakhal-Devpryag RdLaying & rolling in progressCol M S Bisht (Retd)REDSC2 See Pic
9.07-11-2015C35,Buakhal-Devpryag, KM18Laying & Rolling in progressCol M S Bisht (Retd)REDSC2 See Pic
10.07-11-2015C35, Buakhal-Devpryag Rd, KM18SDBC rolling in progressCol M S Bisht (Retd)REDSC2 See Pic
11.07-11-2015C35, Buakhal-Devpryag Rd,Km 18,Rolling in progressCol M S Bisht (Retd)REDSC2 See Pic
12.07-11-2015C35, Buakhal-Devpryag, KM18Laying & Rolling in progressCol M S Bisht (Retd)REDSC2 See Pic
13.07-11-2015C35,17+210,Buakhal-Devpryag RdRoad surface cleaning before layingCol M S Bisht (Retd)REDSC2 See Pic
14.05-11-2015Ch 32.755Causeway in progressAlok JainAEUEAP R&B and CA Pauri See Pic
15.28-10-201517.770Sdbc work in progressAlok JainAEUEAP R&B and CA Pauri See Pic
16.28-10-2015Ch 17.830Sdbc work in progressAlok JainAEUEAP R&B and CA Pauri See Pic
17.16-10-2015C35 KM22, Buakhal Devpryag RdLaying & rolling SDBCCol M S Bisht (Retd)REDSC2 See Pic
18.15-10-2015Km 22SDBC work in progressAlok JainAEUEAP R&B and CA Pauri See Pic
19.15-10-2015Km 22SDBC in progressAlok JainAEUEAP R&B and CA Pauri See Pic
20.12-10-2015C35,KM 22+950,Buakhal-Drvpryag RdRolling work SDBC in progressCol M S Bisht (Retd)REDSC2 See Pic