Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C34 Agreement signed
Project: UEAP-RB Package No.: 1037 Package Name: UEAP/PWD/C34 Sanction Cost: 234.00  lakhs
District: Chamoli Block: Dasholi Constituency: Badrinath Circle:
DEA: DEA UEAP Chamoli DSC: DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5109   Reconstruction of Internal Roads of Nagarpalika Gopeshwar (4.800 KM.) (in prorgress)
Procurement:
Package No.: 1037        Package Name: UEAP/PWD/C34        Tender Date: 07-04-2014        Current Status: Agreement signed        Achieved on Date: 01-12-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C34        Contractor Name: Rami Construction       
Start Date: 10-12-2014        Intended Completion Date: 30-06-2017        Original End Date:  09-03-2016
Total Bond Cost: 23869139.5 (238.69 lakhs)        Variation Cost: 11554617.80 (115.55 lakhs)     Hence Total Bond Cost is   35423757.3 (354.24 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 1802185 for +151 days        LD Analysis for Milestone2: calculated LD is Rs 2184105 for 183 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.G-31.05 KM7.081.05 KM0.04 KM0.080.27
2.BM i/c Prime Coat, Tack Coat4.80 KM126.214.80 KM4.20 KM31.91110.43
3.SDBC i/c Tackcoat4.80 KM81.944.80 KM4.20 KM20.7171.70
4.Culverts/Scupper 2.00 No1.272.00 No0.00 No00.00
5.longitudinal Drain1210.00 m12.100.40 m0.38 m3.3211.50
6.Parapet65.00 No1.8165.00 No65.00 No0.521.81
7.Road Furniture1000.00 No8.261000.00 No880.00 No2.17.27
8.Other Allied Works & Finishing Work 3.00 Job107.453.00 Job0.00 Job00.00
Total Amount: 346.12 58.64   202.98
Remarks: No Remarks       Work Program Made On: 11-02-2017       Updation of work program on: 26-02-2017      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.17-October-20155.17  lakhs
2.08-November-201538.18  lakhs
3.03-December-201536.43  lakhs
4.30-March-201633.73  lakhs
5.20-April-201612.66  lakhs
6.20-May-201612.24  lakhs
7.22-June-201615.19  lakhs
8.04-August-201657.70  lakhs
9.16-October-201624.99  lakhs
10.26-October-201615.42  lakhs
11.12-December-201619.32  lakhs
12.10-March-201718.69  lakhs
Total 289.72  lakhs
% Payment 81.79 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level):
Reconstruction of Internal Roads of Nagarpalika Gopeshwar(5109)No Pending Issue
Detailed report of this Package
Quality
No. of Test Required : 105     No. of Test Done : 185      No. of Test Passed : 185      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 131
Number of Notice(s) issued: 69

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.01-12-2016Infront of kedarnath wildlife /0+840Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwarSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
2.01-12-2016Infront of government library /0+830Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwarSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
3.30-11-2016Gov't liberary /0+820Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwarSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
4.30-11-2016Kedar nath wildlife office /0+880Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwarSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
5.29-11-2016DM Quarter /1+000Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwarSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
6.27-11-2016DM Quarter /1+010Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwar.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
7.21-10-2016Badrinath forest office /1+020Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
8.21-10-2016Kund colony /1+240Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
9.17-10-2016Forest office/ 1+070Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
10.17-10-2016Rami plant / gigran roadInterlocking tiles face makings work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
11.15-10-2016Kund colony / 1+350Slopes checked for interlocking tiles fixing and laying.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
12.15-10-2016Rami plant / gigran roadInterlocking tiles casting work in progress.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
13.15-10-2016Kund colony /1+360Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
14.14-10-2016Kund colony /1+370Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
15.12-10-2016Kund colony /1+400Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
16.08-10-2016Kund colony /1+590Water curing on cc for interlocking tiles fixing in gapSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
17.05-10-2016Kund colony /1+700Pcc fill between road edge & interlocking tiles work progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
18.29-09-2016Kund colony 1+ 780Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
19.29-09-2016Kund colony /1+670Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
20.29-09-2016Kund colony /1+630Interlocking tiles fixing and laying work in progressSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic