UEAP/PWD/C34
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1037 |
Package Name: |
UEAP/PWD/C34 |
Sanction Cost: |
234.00 lakhs |
District: |
Chamoli |
Block: |
Dasholi |
Constituency: |
Badrinath |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
|
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5109 Reconstruction of Internal Roads of Nagarpalika Gopeshwar (4.800 KM.) (in prorgress) |
|
Procurement: |
Package No.: 1037
Package Name: UEAP/PWD/C34
Tender Date: 07-04-2014
Current Status: Agreement signed
Achieved on Date: 01-12-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C34
Contractor Name: Rami Construction
|
Start Date: 10-12-2014
Intended Completion Date: 30-06-2017
Original End Date: 09-03-2016
|
Total Bond Cost: 23869139.5 (238.69 lakhs)
Variation Cost: 11554617.80 (115.55 lakhs) Hence Total Bond Cost is 35423757.3 (354.24 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1802185 for +151 days
LD Analysis for Milestone2: calculated LD is Rs 2184105 for 183 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | G-3 | 1.05 KM | 7.08 | 1.05 KM | 0.04 KM | 0.08 | 0.27 | 2. | BM i/c Prime Coat, Tack Coat | 4.80 KM | 126.21 | 4.80 KM | 4.20 KM | 31.91 | 110.43 | 3. | SDBC i/c Tackcoat | 4.80 KM | 81.94 | 4.80 KM | 4.20 KM | 20.71 | 71.70 | 4. | Culverts/Scupper | 2.00 No | 1.27 | 2.00 No | 0.00 No | 0 | 0.00 | 5. | longitudinal Drain | 1210.00 m | 12.10 | 0.40 m | 0.38 m | 3.32 | 11.50 | 6. | Parapet | 65.00 No | 1.81 | 65.00 No | 65.00 No | 0.52 | 1.81 | 7. | Road Furniture | 1000.00 No | 8.26 | 1000.00 No | 880.00 No | 2.1 | 7.27 | 8. | Other Allied Works & Finishing Work | 3.00 Job | 107.45 | 3.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
346.12 |
|
58.64 |
202.98 |
|
Remarks:
No Remarks
Work Program Made On:
11-02-2017
Updation of work program on:
26-02-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 17-October-2015 | 5.17 lakhs |
2. | 08-November-2015 | 38.18 lakhs |
3. | 03-December-2015 | 36.43 lakhs |
4. | 30-March-2016 | 33.73 lakhs |
5. | 20-April-2016 | 12.66 lakhs |
6. | 20-May-2016 | 12.24 lakhs |
7. | 22-June-2016 | 15.19 lakhs |
8. | 04-August-2016 | 57.70 lakhs |
9. | 16-October-2016 | 24.99 lakhs |
10. | 26-October-2016 | 15.42 lakhs |
11. | 12-December-2016 | 19.32 lakhs |
12. | 10-March-2017 | 18.69 lakhs |
Total |
289.72 lakhs |
% Payment |
81.79 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | PUC vehicles | Environment & Social Compliances(Sub Project level): | Reconstruction of Internal Roads of Nagarpalika Gopeshwar(5109) | No Pending Issue |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 131 |
Number of Notice(s) issued: 69 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 01-12-2016 | Infront of kedarnath wildlife /0+840 | Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwar | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
2. | 01-12-2016 | Infront of government library /0+830 | Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwar | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
3. | 30-11-2016 | Gov't liberary /0+820 | Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwar | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
4. | 30-11-2016 | Kedar nath wildlife office /0+880 | Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwar | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
5. | 29-11-2016 | DM Quarter /1+000 | Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwar | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
6. | 27-11-2016 | DM Quarter /1+010 | Interlocking tiles fixing and laying work in progress for internal road of nagar palika gopeshwar. | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
7. | 21-10-2016 | Badrinath forest office /1+020 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
8. | 21-10-2016 | Kund colony /1+240 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
9. | 17-10-2016 | Forest office/ 1+070 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
10. | 17-10-2016 | Rami plant / gigran road | Interlocking tiles face makings work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
11. | 15-10-2016 | Kund colony / 1+350 | Slopes checked for interlocking tiles fixing and laying. | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
12. | 15-10-2016 | Rami plant / gigran road | Interlocking tiles casting work in progress. | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
13. | 15-10-2016 | Kund colony /1+360 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
14. | 14-10-2016 | Kund colony /1+370 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
15. | 12-10-2016 | Kund colony /1+400 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
16. | 08-10-2016 | Kund colony /1+590 | Water curing on cc for interlocking tiles fixing in gap | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
17. | 05-10-2016 | Kund colony /1+700 | Pcc fill between road edge & interlocking tiles work progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
18. | 29-09-2016 | Kund colony 1+ 780 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
19. | 29-09-2016 | Kund colony /1+670 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
20. | 29-09-2016 | Kund colony /1+630 | Interlocking tiles fixing and laying work in progress | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
|
|