Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C32 Agreement signed
Project: UEAP-RB Package No.: 1035 Package Name: UEAP/PWD/C32 Sanction Cost: 305.00  lakhs
District: Chamoli Block: Pokhari Constituency: Badrinath Circle:
DEA: DEA UEAP Chamoli DSC: DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5107   Rudraprayag Pokahri Karnprayag (10.000 KM.) (in prorgress)
Procurement:
Package No.: 1035        Package Name: UEAP/PWD/C32        Tender Date: 08-04-2014        Current Status: Agreement signed        Achieved on Date: 17-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C32        Contractor Name: R.G. Buildwell.       
Start Date: 09-12-2014        Intended Completion Date: 08-06-2016       
Total Bond Cost: 32121149 (321.21 lakhs)        Variation Cost: 51038.46 (0.51 lakhs)     Hence Total Bond Cost is   32172187.46 (321.72 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 80305 for 5 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.00 KM0.000.00 KM0.00 KM00.00
2.R/Wall, B/ Wall Type Protection works410.00 m45.34945.00 m410.00 m6.2419.67
3.GSB/RBI/G-10.18 KM1.780.26 KM0.26 KM0.561.78
4.G-20.18 KM1.420.35 KM0.35 KM0.451.42
5.G-30.18 KM1.530.45 KM0.45 KM0.491.53
6.BM i/c Prime Coat, Tack Coat2.48 KM73.112.83 KM2.83 KM23.1973.11
7.SDBC i/c Tackcoat3.00 KM48.633.43 KM3.42 KM15.3848.49
8.Cause Way1.00 No1.543.00 No1.90 No0.310.98
9.Culverts/Scupper 0.00 No0.000.00 No0.00 No00.00
10.longitudinal Drain11304.00 m16.8718525.00 m16304.00 m4.7114.85
11.Crash Barrier2808.00 m81.431900.00 m1900.00 m25.8381.43
12.Parapet600.00 No10.18665.00 No600.00 No2.919.18
13.Road Furniture1388.00 No11.791369.00 No1352.00 No3.6911.65
14.Other Allied Works & Finishing Work 2.00 Job21.682.00 Job0.00 Job00.00
Total Amount: 315.3 83.76   264.09
Remarks: No Remarks       Work Program Made On: 26-02-2015       Updation of work program on: 26-02-2017      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.21-May-20157.90  lakhs
2.06-June-201576.37  lakhs
3.17-October-201512.86  lakhs
4.08-January-201690.74  lakhs
5.30-March-201626.75  lakhs
6.08-July-201632.34  lakhs
7.07-October-201651.95  lakhs
8.17-June-201722.83  lakhs
Total 321.74  lakhs
% Payment 100.01 %
Advance Amount:  32.12  lakhs        Recovered Amount:  32.19  lakhs        Balance to be Recovered  -0.07  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Rudraprayag Pokahri Karnprayag(5107) Borrow pits, DG set
Detailed report of this Package
Quality
No. of Test Required : 20     No. of Test Done : 57      No. of Test Passed : 57      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 106
Number of Notice(s) issued: 68

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.13-09-201622+400Rrsm r/wll work is on progress...Prabhansh SrivastavaJEUEAP R&B Chamoli See Pic
2.01-09-201643+510Third party core cutting by alpha test housePrabhansh SrivastavaJEUEAP R&B Chamoli See Pic
3.30-08-2016Km 68.520, Rudraprayag Pokhari Karnprayag motor road.Construction of Katcha drain work in progress.Atul ShandilyaAEUEAP R&B Chamoli See Pic
4.14-07-201660+220/RUDRAPRAYAG pokhriParapet (road safety)work in progressAkhilesh SharmaREDSC2 R&B ADB Chamoli See Pic
5.08-06-2016Thala bendWire crates constructionAkhilesh SharmaREDSC2 R&B ADB Chamoli See Pic
6.06-06-2016Thala bend c32 pokhri karan pryagWbm & wire creat in progressNaresh KumarTechnical OfficerDSC2 R&B ADB Chamoli See Pic
7.06-06-2016Thala bend 47+150 c 32 pokhari karan paryagWbm & wire creat in progressNaresh KumarTechnical OfficerDSC2 R&B ADB Chamoli See Pic
8.02-04-2016Ch. 47.240,Culvert under construction.Atul ShandilyaAEUEAP R&B Chamoli See Pic
9.02-04-2016Ch. 47.240, Rudraprayag Pokhari Karnprayag motor road.Constrution work at Thala bend.Atul ShandilyaAEUEAP R&B Chamoli See Pic
10.27-03-201647+200 ThalaBandThalaBand protection work in progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
11.12-03-201647+100ThalaBand wire create work in Progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic
12.07-03-2016C7Mohan khal/ch44+00Public Consultation by Dr Bhattacharya Social Expert Dsc2.Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
13.07-03-2016C32 (Semi-Gwad)/Ch74+600Public Consultation by Dr Bhattacharya Social expert Dsc2.Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
14.22-02-20160+700Exca. Work for raft Foundation at bridge site.Anurag RawatJEUEAP R&B Chamoli See Pic
15.15-02-201647+180Wire create in ProgressSubhash ChandraQCDSC2 R&B WB Tehri See Pic
16.12-02-2016Thala bendWire crate in progressAkhilesh SharmaREDSC2 R&B ADB Chamoli See Pic
17.11-02-2016Ch. 47.190, Rudraprayag Pokhari Karnprayag motor road.Sinking zone Thala bend work in progress.Atul ShandilyaAEUEAP R&B Chamoli See Pic
18.11-02-2016Ch. 47.220, Rudraprayag Pokhari Karnprayag motor road.Work in progress of sinking zone Thala Bend.Atul ShandilyaAEUEAP R&B Chamoli See Pic
19.08-02-201647+220C32 ThalaBand work started/wire creteSubhash ChandraQCDSC2 R&B WB Tehri See Pic
20.16-01-201673+150Parapet Casting in Progress.Subhash ChandraQCDSC2 R&B WB Tehri See Pic