UEAP/PWD/C32
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1035 |
Package Name: |
UEAP/PWD/C32 |
Sanction Cost: |
305.00 lakhs |
District: |
Chamoli |
Block: |
Pokhari |
Constituency: |
Badrinath |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
|
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5107 Rudraprayag Pokahri Karnprayag (10.000 KM.) (in prorgress) |
|
Procurement: |
Package No.: 1035
Package Name: UEAP/PWD/C32
Tender Date: 08-04-2014
Current Status: Agreement signed
Achieved on Date: 17-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C32
Contractor Name: R.G. Buildwell.
|
Start Date: 09-12-2014
Intended Completion Date: 08-06-2016
|
Total Bond Cost: 32121149 (321.21 lakhs)
Variation Cost: 51038.46 (0.51 lakhs) Hence Total Bond Cost is 32172187.46 (321.72 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: calculated LD is Rs 80305 for 5 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 2. | R/Wall, B/ Wall Type Protection works | 410.00 m | 45.34 | 945.00 m | 410.00 m | 6.24 | 19.67 | 3. | GSB/RBI/G-1 | 0.18 KM | 1.78 | 0.26 KM | 0.26 KM | 0.56 | 1.78 | 4. | G-2 | 0.18 KM | 1.42 | 0.35 KM | 0.35 KM | 0.45 | 1.42 | 5. | G-3 | 0.18 KM | 1.53 | 0.45 KM | 0.45 KM | 0.49 | 1.53 | 6. | BM i/c Prime Coat, Tack Coat | 2.48 KM | 73.11 | 2.83 KM | 2.83 KM | 23.19 | 73.11 | 7. | SDBC i/c Tackcoat | 3.00 KM | 48.63 | 3.43 KM | 3.42 KM | 15.38 | 48.49 | 8. | Cause Way | 1.00 No | 1.54 | 3.00 No | 1.90 No | 0.31 | 0.98 | 9. | Culverts/Scupper | 0.00 No | 0.00 | 0.00 No | 0.00 No | 0 | 0.00 | 10. | longitudinal Drain | 11304.00 m | 16.87 | 18525.00 m | 16304.00 m | 4.71 | 14.85 | 11. | Crash Barrier | 2808.00 m | 81.43 | 1900.00 m | 1900.00 m | 25.83 | 81.43 | 12. | Parapet | 600.00 No | 10.18 | 665.00 No | 600.00 No | 2.91 | 9.18 | 13. | Road Furniture | 1388.00 No | 11.79 | 1369.00 No | 1352.00 No | 3.69 | 11.65 | 14. | Other Allied Works & Finishing Work | 2.00 Job | 21.68 | 2.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
315.3 |
|
83.76 |
264.09 |
|
Remarks:
No Remarks
Work Program Made On:
26-02-2015
Updation of work program on:
26-02-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 21-May-2015 | 7.90 lakhs |
2. | 06-June-2015 | 76.37 lakhs |
3. | 17-October-2015 | 12.86 lakhs |
4. | 08-January-2016 | 90.74 lakhs |
5. | 30-March-2016 | 26.75 lakhs |
6. | 08-July-2016 | 32.34 lakhs |
7. | 07-October-2016 | 51.95 lakhs |
8. | 17-June-2017 | 22.83 lakhs |
Total |
321.74 lakhs |
% Payment |
100.01 % |
|
Advance Amount: 32.12 lakhs
Recovered Amount: 32.19 lakhs
Balance to be Recovered -0.07 lakhs
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Rudraprayag Pokahri Karnprayag(5107) | Borrow pits, DG set |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 106 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 13-09-2016 | 22+400 | Rrsm r/wll work is on progress... | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
2. | 01-09-2016 | 43+510 | Third party core cutting by alpha test house | Prabhansh Srivastava | JE | UEAP R&B Chamoli | See Pic |
3. | 30-08-2016 | Km 68.520, Rudraprayag Pokhari Karnprayag motor road. | Construction of Katcha drain work in progress. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
4. | 14-07-2016 | 60+220/RUDRAPRAYAG pokhri | Parapet (road safety)work in progress | Akhilesh Sharma | RE | DSC2 R&B ADB Chamoli | See Pic |
5. | 08-06-2016 | Thala bend | Wire crates construction | Akhilesh Sharma | RE | DSC2 R&B ADB Chamoli | See Pic |
6. | 06-06-2016 | Thala bend c32 pokhri karan pryag | Wbm & wire creat in progress | Naresh Kumar | Technical Officer | DSC2 R&B ADB Chamoli | See Pic |
7. | 06-06-2016 | Thala bend 47+150 c 32 pokhari karan paryag | Wbm & wire creat in progress | Naresh Kumar | Technical Officer | DSC2 R&B ADB Chamoli | See Pic |
8. | 02-04-2016 | Ch. 47.240, | Culvert under construction. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
9. | 02-04-2016 | Ch. 47.240, Rudraprayag Pokhari Karnprayag motor road. | Constrution work at Thala bend. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
10. | 27-03-2016 | 47+200 ThalaBand | ThalaBand protection work in progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
11. | 12-03-2016 | 47+100 | ThalaBand wire create work in Progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
12. | 07-03-2016 | C7Mohan khal/ch44+00 | Public Consultation by Dr Bhattacharya Social Expert Dsc2. | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
13. | 07-03-2016 | C32 (Semi-Gwad)/Ch74+600 | Public Consultation by Dr Bhattacharya Social expert Dsc2. | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
14. | 22-02-2016 | 0+700 | Exca. Work for raft Foundation at bridge site. | Anurag Rawat | JE | UEAP R&B Chamoli | See Pic |
15. | 15-02-2016 | 47+180 | Wire create in Progress | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
16. | 12-02-2016 | Thala bend | Wire crate in progress | Akhilesh Sharma | RE | DSC2 R&B ADB Chamoli | See Pic |
17. | 11-02-2016 | Ch. 47.190, Rudraprayag Pokhari Karnprayag motor road. | Sinking zone Thala bend work in progress. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
18. | 11-02-2016 | Ch. 47.220, Rudraprayag Pokhari Karnprayag motor road. | Work in progress of sinking zone Thala Bend. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
19. | 08-02-2016 | 47+220 | C32 ThalaBand work started/wire crete | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
20. | 16-01-2016 | 73+150 | Parapet Casting in Progress. | Subhash Chandra | QC | DSC2 R&B WB Tehri | See Pic |
|
|