Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C31 Agreement signed
Project: UEAP-RB Package No.: 1034 Package Name: UEAP/PWD/C31 Sanction Cost: 612.00  lakhs
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle:
DEA: DEA UEAP Rudraprayag DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5206   Makku-Paldwari (15.600 KM.) (completed)
Procurement:
Package No.: 1034        Package Name:  UEAP/PWD/C31        Tender Date: 07-04-2014        Current Status: Agreement signed        Achieved on Date: 17-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name:  UEAP/PWD/C31        Contractor Name: R.G. Buildwell.       
Start Date: 09-12-2014        Intended Completion Date: 08-06-2016       
Total Bond Cost: 62594744 (625.95 lakhs)        Variation Cost: 1616085.43 (16.16 lakhs)     Hence Total Bond Cost is   64210829.43 (642.11 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 31297 for 1 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.46 KM1.450.46 KM0.46 KM0.231.45
2.R/Wall, B/ Wall Type Protection works1002.00 m64.131002.00 m1002.00 m10.1164.13
3.GSB/RBI/G-10.13 KM0.790.13 KM0.13 KM0.120.79
4.G-20.59 KM2.520.59 KM0.59 KM0.42.52
5.G-31.72 KM8.631.72 KM1.72 KM1.368.63
6.BM i/c Prime Coat, Tack Coat8.48 KM257.168.48 KM8.48 KM40.52257.16
7.SDBC i/c Tackcoat14.49 KM206.6714.49 KM14.49 KM32.57206.67
8.Cause Way5.00 No13.905.00 No5.00 No2.1913.90
9.Culverts/Scupper 3.00 No4.763.00 No3.00 No0.754.76
10.longitudinal Drain11741.00 m14.6011741.00 m11741.00 m2.314.60
11.Crash Barrier1216.00 m35.871216.00 m1216.00 m5.6535.87
12.Parapet253.00 No3.86253.00 No253.00 No0.613.86
13.Road Furniture748.00 No20.28748.00 No748.00 No3.220.28
Total Amount: 634.62 100   634.62
Remarks: No Remarks       Work Program Made On: 26-02-2015       Updation of work program on: 08-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-March-20154.88  lakhs
2.25-May-201546.17  lakhs
3.12-June-201585.70  lakhs
4.11-August-201510.89  lakhs
5.23-October-2015168.97  lakhs
6.07-November-201578.72  lakhs
7.30-November-201546.58  lakhs
8.28-January-201651.94  lakhs
9.16-February-20167.16  lakhs
10.29-February-201611.55  lakhs
11.21-March-201645.87  lakhs
12.31-March-201614.86  lakhs
13.25-May-20169.27  lakhs
14.29-June-201642.51  lakhs
15.28-October-20167.00  lakhs
16.03-June-20179.82  lakhs
17.22-August-20170.20  lakhs
Total 642.09  lakhs
% Payment 100 %
Advance Amount:  62.59  lakhs        Recovered Amount:  62.59  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 1502     No. of Test Done : 1556      No. of Test Passed : 1494      No. of Test Failed : 0      No. of Test Result Awaited : 54   Test report of this package
Number of Pics Available on Web Repository: 80
Number of Notice(s) issued: 68

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.09-07-20167+420SDBC Core Cutting Work in ProgressRavi Shankar ShuklaQCUEAP R&B Chamoli See Pic
2.09-07-20168+600Bm & SDBC Core Cutting in progressRavi Shankar ShuklaQCUEAP R&B Chamoli See Pic
3.13-10-2015C31 Makku paldwadi road Ch 16.680Sdbc work in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
4.13-10-2015C31 Makku paldwadi road Ch 16.620Sdbc work in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
5.29-09-2015HMP RudrapryagProduction of sdbcAshok GuptaREDSC Rudraprayag See Pic
6.24-09-2015Plant siteBM production at plantVk RaturiJEDEA WB Guptkashi See Pic
7.23-09-2015Plant RGBBM productionVk RaturiJEDEA WB Guptkashi See Pic
8.22-09-2015HMP Rudrapryag C 31BM productionAshok GuptaREDSC Rudraprayag See Pic
9.03-08-2015Ch 22+180Protection work in progressAshok GuptaREDSC Rudraprayag See Pic
10.03-08-2015Ch 11+460Protection work in progressAshok GuptaREDSC Rudraprayag See Pic
11.22-07-2015C-31 makku paldwari mr ch 22.130Road surface and embnkment damdged due to heavy rain...Sudhir Kumar AroraAEUEAP R&B Rudraprayag See Pic
12.22-07-2015C 31 makku paldwari mr ch 21.415One meter span culvert under constructionSudhir Kumar AroraAEUEAP R&B Rudraprayag See Pic
13.22-07-2015C 31 makku paldwari mr ch 19.800R wall completadSudhir Kumar AroraAEUEAP R&B Rudraprayag See Pic
14.22-07-2015C 31 makku paldwari mr ch 14.825Wire crate completedSudhir Kumar AroraAEUEAP R&B Rudraprayag See Pic
15.22-07-2015C31 makku paldwari mr ch 14.095R wall completedSudhir Kumar AroraAEUEAP R&B Rudraprayag See Pic
16.22-07-2015C 31 makku pald. MR ch 11.460Dameg Road surface and embankmet due to heavy raim ....Sudhir Kumar AroraAEUEAP R&B Rudraprayag See Pic
17.22-07-2015C-31 makku paldwari mr ch 11.460Damege road surface and embankment due to heavy rainSudhir Kumar AroraAEUEAP R&B Rudraprayag See Pic
18.22-07-2015C-30 makku paldeari mr ch 7.400Informatry sign boardSudhir Kumar AroraAEUEAP R&B Rudraprayag See Pic
19.04-06-2015C- 31, km - 9,Laying of sdbcAshok GuptaREDSC Rudraprayag See Pic
20.31-05-2015HMP RudrapryagBitumen content for BM ProductionAshok GuptaREDSC Rudraprayag See Pic