UEAP/PWD/C31
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1034 |
Package Name: |
UEAP/PWD/C31 |
Sanction Cost: |
612.00 lakhs |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA UEAP Rudraprayag |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5206 Makku-Paldwari (15.600 KM.) (completed) |
|
Procurement: |
Package No.: 1034
Package Name:  UEAP/PWD/C31
Tender Date: 07-04-2014
Current Status: Agreement signed
Achieved on Date: 17-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C31
Contractor Name: R.G. Buildwell.
|
Start Date: 09-12-2014
Intended Completion Date: 08-06-2016
|
Total Bond Cost: 62594744 (625.95 lakhs)
Variation Cost: 1616085.43 (16.16 lakhs) Hence Total Bond Cost is 64210829.43 (642.11 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 31297 for 1 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.46 KM | 1.45 | 0.46 KM | 0.46 KM | 0.23 | 1.45 | 2. | R/Wall, B/ Wall Type Protection works | 1002.00 m | 64.13 | 1002.00 m | 1002.00 m | 10.11 | 64.13 | 3. | GSB/RBI/G-1 | 0.13 KM | 0.79 | 0.13 KM | 0.13 KM | 0.12 | 0.79 | 4. | G-2 | 0.59 KM | 2.52 | 0.59 KM | 0.59 KM | 0.4 | 2.52 | 5. | G-3 | 1.72 KM | 8.63 | 1.72 KM | 1.72 KM | 1.36 | 8.63 | 6. | BM i/c Prime Coat, Tack Coat | 8.48 KM | 257.16 | 8.48 KM | 8.48 KM | 40.52 | 257.16 | 7. | SDBC i/c Tackcoat | 14.49 KM | 206.67 | 14.49 KM | 14.49 KM | 32.57 | 206.67 | 8. | Cause Way | 5.00 No | 13.90 | 5.00 No | 5.00 No | 2.19 | 13.90 | 9. | Culverts/Scupper | 3.00 No | 4.76 | 3.00 No | 3.00 No | 0.75 | 4.76 | 10. | longitudinal Drain | 11741.00 m | 14.60 | 11741.00 m | 11741.00 m | 2.3 | 14.60 | 11. | Crash Barrier | 1216.00 m | 35.87 | 1216.00 m | 1216.00 m | 5.65 | 35.87 | 12. | Parapet | 253.00 No | 3.86 | 253.00 No | 253.00 No | 0.61 | 3.86 | 13. | Road Furniture | 748.00 No | 20.28 | 748.00 No | 748.00 No | 3.2 | 20.28 |
Total Amount: |
634.62 |
|
100 |
634.62 |
|
Remarks:
No Remarks
Work Program Made On:
26-02-2015
Updation of work program on:
08-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-March-2015 | 4.88 lakhs |
2. | 25-May-2015 | 46.17 lakhs |
3. | 12-June-2015 | 85.70 lakhs |
4. | 11-August-2015 | 10.89 lakhs |
5. | 23-October-2015 | 168.97 lakhs |
6. | 07-November-2015 | 78.72 lakhs |
7. | 30-November-2015 | 46.58 lakhs |
8. | 28-January-2016 | 51.94 lakhs |
9. | 16-February-2016 | 7.16 lakhs |
10. | 29-February-2016 | 11.55 lakhs |
11. | 21-March-2016 | 45.87 lakhs |
12. | 31-March-2016 | 14.86 lakhs |
13. | 25-May-2016 | 9.27 lakhs |
14. | 29-June-2016 | 42.51 lakhs |
15. | 28-October-2016 | 7.00 lakhs |
16. | 03-June-2017 | 9.82 lakhs |
17. | 22-August-2017 | 0.20 lakhs |
Total |
642.09 lakhs |
% Payment |
100 % |
|
Advance Amount: 62.59 lakhs
Recovered Amount: 62.59 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1502 No. of Test Done : 1556 No. of Test Passed : 1494 No. of Test Failed : 0 No. of Test Result Awaited : 54
Test report of this package
|
|
Number of Pics Available on Web Repository: 80 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 09-07-2016 | 7+420 | SDBC Core Cutting Work in Progress | Ravi Shankar Shukla | QC | UEAP R&B Chamoli | See Pic |
2. | 09-07-2016 | 8+600 | Bm & SDBC Core Cutting in progress | Ravi Shankar Shukla | QC | UEAP R&B Chamoli | See Pic |
3. | 13-10-2015 | C31 Makku paldwadi road Ch 16.680 | Sdbc work in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
4. | 13-10-2015 | C31 Makku paldwadi road Ch 16.620 | Sdbc work in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
5. | 29-09-2015 | HMP Rudrapryag | Production of sdbc | Ashok Gupta | RE | DSC Rudraprayag | See Pic |
6. | 24-09-2015 | Plant site | BM production at plant | Vk Raturi | JE | DEA WB Guptkashi | See Pic |
7. | 23-09-2015 | Plant RGB | BM production | Vk Raturi | JE | DEA WB Guptkashi | See Pic |
8. | 22-09-2015 | HMP Rudrapryag C 31 | BM production | Ashok Gupta | RE | DSC Rudraprayag | See Pic |
9. | 03-08-2015 | Ch 22+180 | Protection work in progress | Ashok Gupta | RE | DSC Rudraprayag | See Pic |
10. | 03-08-2015 | Ch 11+460 | Protection work in progress | Ashok Gupta | RE | DSC Rudraprayag | See Pic |
11. | 22-07-2015 | C-31 makku paldwari mr ch 22.130 | Road surface and embnkment damdged due to heavy rain... | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
12. | 22-07-2015 | C 31 makku paldwari mr ch 21.415 | One meter span culvert under construction | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
13. | 22-07-2015 | C 31 makku paldwari mr ch 19.800 | R wall completad | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
14. | 22-07-2015 | C 31 makku paldwari mr ch 14.825 | Wire crate completed | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
15. | 22-07-2015 | C31 makku paldwari mr ch 14.095 | R wall completed | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
16. | 22-07-2015 | C 31 makku pald. MR ch 11.460 | Dameg Road surface and embankmet due to heavy raim .... | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
17. | 22-07-2015 | C-31 makku paldwari mr ch 11.460 | Damege road surface and embankment due to heavy rain | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
18. | 22-07-2015 | C-30 makku paldeari mr ch 7.400 | Informatry sign board | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
19. | 04-06-2015 | C- 31, km - 9, | Laying of sdbc | Ashok Gupta | RE | DSC Rudraprayag | See Pic |
20. | 31-05-2015 | HMP Rudrapryag | Bitumen content for BM Production | Ashok Gupta | RE | DSC Rudraprayag | See Pic |
|
|