UEAP/PWD/C30
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1033 |
Package Name: |
UEAP/PWD/C30 |
Sanction Cost: |
811.00 lakhs |
District: |
Rudraprayag |
Block: |
Ukhimath |
Constituency: |
Kedarnath |
Circle: |
|
DEA: |
DEA UEAP Rudraprayag |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5205 Sonprayag-Triyuginarayan (12.500 KM.) (completed) |
|
Procurement: |
Package No.: 1033
Package Name: UEAP/PWD/C30
Tender Date: 07-04-2014
Current Status: Agreement signed
Achieved on Date: 01-12-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C30
Contractor Name: Gaurav Builder
|
Start Date: 10-12-2014
Intended Completion Date: 09-06-2016
|
Total Bond Cost: 81709393.5 (817.09 lakhs)
Variation Cost: -1753515.43 (-17.54 lakhs) Hence Total Bond Cost is 79955878.07 (799.56 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 5515425 for 135 days
LD Analysis for Milestone2: calculated LD is Rs 3390965 for 83 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.23 KM | 1.22 | 0.23 KM | 0.23 KM | 0.16 | 1.22 | 2. | R/Wall, B/ Wall Type Protection works | 1089.00 m | 91.89 | 1089.00 m | 1089.00 m | 11.84 | 91.89 | 3. | GSB/RBI/G-1 | 0.82 KM | 6.27 | 0.82 KM | 0.82 KM | 0.81 | 6.27 | 4. | G-2 | 0.88 KM | 6.02 | 0.88 KM | 0.88 KM | 0.78 | 6.02 | 5. | G-3 | 3.83 KM | 26.07 | 3.83 KM | 3.83 KM | 3.36 | 26.07 | 6. | BM i/c Prime Coat, Tack Coat | 10.63 KM | 249.28 | 10.63 KM | 10.63 KM | 32.11 | 249.28 | 7. | SDBC i/c Tackcoat | 11.58 KM | 141.19 | 11.58 KM | 11.58 KM | 18.19 | 141.19 | 8. | Cause Way | 2.00 No | 8.67 | 2.00 No | 2.00 No | 1.12 | 8.67 | 9. | Culverts/Scupper | 9.00 No | 12.64 | 9.00 No | 9.00 No | 1.63 | 12.64 | 10. | longitudinal Drain | 10554.00 m | 73.30 | 10554.00 m | 10554.00 m | 9.44 | 73.30 | 11. | Crash Barrier | 4208.00 m | 117.82 | 4208.00 m | 4208.00 m | 15.18 | 117.82 | 12. | Parapet | 625.00 No | 32.21 | 625.00 No | 625.00 No | 4.15 | 32.21 | 13. | Road Furniture | 5608.00 No | 9.66 | 5608.00 No | 5608.00 No | 1.24 | 9.66 |
Total Amount: |
776.24 |
|
100 |
776.24 |
|
Remarks:
No Remarks
Work Program Made On:
26-02-2015
Updation of work program on:
08-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2015 | 20.25 lakhs |
2. | 08-May-2015 | 8.76 lakhs |
3. | 20-June-2015 | 23.98 lakhs |
4. | 25-July-2015 | 44.12 lakhs |
5. | 08-October-2015 | 18.34 lakhs |
6. | 26-October-2015 | 57.93 lakhs |
7. | 06-November-2015 | 72.40 lakhs |
8. | 30-November-2015 | 15.94 lakhs |
9. | 22-January-2016 | 25.93 lakhs |
10. | 08-February-2016 | 54.58 lakhs |
11. | 29-February-2016 | 63.40 lakhs |
12. | 19-March-2016 | 24.96 lakhs |
13. | 22-April-2016 | 82.79 lakhs |
14. | 14-June-2016 | 128.46 lakhs |
15. | 29-June-2016 | 36.18 lakhs |
16. | 06-August-2016 | 66.54 lakhs |
17. | 28-October-2016 | 29.15 lakhs |
18. | 27-December-2016 | 25.63 lakhs |
19. | 22-August-2017 | 0.20 lakhs |
Total |
799.54 lakhs |
% Payment |
100 % |
|
Advance Amount: 81.71 lakhs
Recovered Amount: 81.71 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 44 |
Number of Notice(s) issued: 66 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-07-2016 | 0+060 | BM & SDBC CORE CHEKING BY SE | Ravi Shankar Shukla | QC | UEAP R&B Chamoli | See Pic |
2. | 11-02-2016 | Ch. 4.625, Sonprayag Triyuginarayan motor road. | Measurements checking of K C drain. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
3. | 11-02-2016 | Ch. 5.980, Sonprayag Triyuginarayan motor road. | Crash barrier measurements checking. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
4. | 14-10-2015 | Plant site C30 sonprayag triyuginarayan | BM Production checking temp. | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
5. | 14-10-2015 | Plant site C30 sonprayag triyuginarayan road | Breaking stone ballast | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
6. | 21-07-2015 | C30 sonp. Triyug. mr ch 9.470 | R wall under const. | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
7. | 21-07-2015 | C 30 sonp. Triyu. mr ch 2.845 | B wall completed | Sudhir Kumar Arora | AE | UEAP R&B Rudraprayag | See Pic |
8. | 04-07-2015 | Ch 11+625 | Culvert work in progress | Ashok Gupta | RE | DSC Rudraprayag | See Pic |
9. | 04-07-2015 | Ch 10+304 | K C Drain in progress | Ashok Gupta | RE | DSC Rudraprayag | See Pic |
10. | 19-06-2015 | C30sonprayag triyuginarayan road ch11.760 | Check thickness of BM | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
11. | 19-06-2015 | C30 sonprayag triyginarayan road check 12.200 | Check thickness of BM | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
12. | 04-06-2015 | C30sonprayag triguginarayan road ch 11.440 | R Wall in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
13. | 04-06-2015 | C30sonprayag triguginarayan road ch2.450 | B wall complete | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
14. | 04-06-2015 | C30 sonprayag triguginarayan road ch9.450 | G-3 complete | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
15. | 04-06-2015 | C30sonprayag triguginarayan road ch11.400 | G-3 complete in km12 | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
16. | 04-06-2015 | C30sonprayag triguginarayan road ch11.675 | Kutcha drain in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
17. | 04-06-2015 | C30sonprayag triguginarayan road ch11.715 | Culvert in half width complete | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
18. | 04-06-2015 | C30sonprayag triguginarayan road ch11.760 | R Wall in progress | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
19. | 04-06-2015 | C30sonprayag triguginarayan road ch12.065 | Culvert in half width complete | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
20. | 04-06-2015 | C30 sonprayag triguginarayan road plant site | Weigh bridge at HMP | Anil Kumar Mittal | EE | UEAP R&B Rudraprayag | See Pic |
|
|