Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C30 Agreement signed
Project: UEAP-RB Package No.: 1033 Package Name: UEAP/PWD/C30 Sanction Cost: 811.00  lakhs
District: Rudraprayag Block: Ukhimath Constituency: Kedarnath Circle:
DEA: DEA UEAP Rudraprayag DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5205   Sonprayag-Triyuginarayan (12.500 KM.) (completed)
Procurement:
Package No.: 1033        Package Name: UEAP/PWD/C30        Tender Date: 07-04-2014        Current Status: Agreement signed        Achieved on Date: 01-12-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C30        Contractor Name: Gaurav Builder       
Start Date: 10-12-2014        Intended Completion Date: 09-06-2016       
Total Bond Cost: 81709393.5 (817.09 lakhs)        Variation Cost: -1753515.43 (-17.54 lakhs)     Hence Total Bond Cost is   79955878.07 (799.56 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 5515425 for 135 days        LD Analysis for Milestone2: calculated LD is Rs 3390965 for 83 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.23 KM1.220.23 KM0.23 KM0.161.22
2.R/Wall, B/ Wall Type Protection works1089.00 m91.891089.00 m1089.00 m11.8491.89
3.GSB/RBI/G-10.82 KM6.270.82 KM0.82 KM0.816.27
4.G-20.88 KM6.020.88 KM0.88 KM0.786.02
5.G-33.83 KM26.073.83 KM3.83 KM3.3626.07
6.BM i/c Prime Coat, Tack Coat10.63 KM249.2810.63 KM10.63 KM32.11249.28
7.SDBC i/c Tackcoat11.58 KM141.1911.58 KM11.58 KM18.19141.19
8.Cause Way2.00 No8.672.00 No2.00 No1.128.67
9.Culverts/Scupper 9.00 No12.649.00 No9.00 No1.6312.64
10.longitudinal Drain10554.00 m73.3010554.00 m10554.00 m9.4473.30
11.Crash Barrier4208.00 m117.824208.00 m4208.00 m15.18117.82
12.Parapet625.00 No32.21625.00 No625.00 No4.1532.21
13.Road Furniture5608.00 No9.665608.00 No5608.00 No1.249.66
Total Amount: 776.24 100   776.24
Remarks: No Remarks       Work Program Made On: 26-02-2015       Updation of work program on: 08-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-201520.25  lakhs
2.08-May-20158.76  lakhs
3.20-June-201523.98  lakhs
4.25-July-201544.12  lakhs
5.08-October-201518.34  lakhs
6.26-October-201557.93  lakhs
7.06-November-201572.40  lakhs
8.30-November-201515.94  lakhs
9.22-January-201625.93  lakhs
10.08-February-201654.58  lakhs
11.29-February-201663.40  lakhs
12.19-March-201624.96  lakhs
13.22-April-201682.79  lakhs
14.14-June-2016128.46  lakhs
15.29-June-201636.18  lakhs
16.06-August-201666.54  lakhs
17.28-October-201629.15  lakhs
18.27-December-201625.63  lakhs
19.22-August-20170.20  lakhs
Total 799.54  lakhs
% Payment 100 %
Advance Amount:  81.71  lakhs        Recovered Amount:  81.71  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 2082     No. of Test Done : 2097      No. of Test Passed : 2097      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 44
Number of Notice(s) issued: 66

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-07-20160+060BM & SDBC CORE CHEKING BY SERavi Shankar ShuklaQCUEAP R&B Chamoli See Pic
2.11-02-2016Ch. 4.625, Sonprayag Triyuginarayan motor road.Measurements checking of K C drain.Atul ShandilyaAEUEAP R&B Chamoli See Pic
3.11-02-2016Ch. 5.980, Sonprayag Triyuginarayan motor road.Crash barrier measurements checking.Atul ShandilyaAEUEAP R&B Chamoli See Pic
4.14-10-2015Plant site C30 sonprayag triyuginarayanBM Production checking temp.Anil Kumar MittalEEUEAP R&B Rudraprayag See Pic
5.14-10-2015Plant site C30 sonprayag triyuginarayan roadBreaking stone ballastAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
6.21-07-2015C30 sonp. Triyug. mr ch 9.470R wall under const.Sudhir Kumar AroraAEUEAP R&B Rudraprayag See Pic
7.21-07-2015C 30 sonp. Triyu. mr ch 2.845B wall completedSudhir Kumar AroraAEUEAP R&B Rudraprayag See Pic
8.04-07-2015Ch 11+625Culvert work in progressAshok GuptaREDSC Rudraprayag See Pic
9.04-07-2015Ch 10+304K C Drain in progressAshok GuptaREDSC Rudraprayag See Pic
10.19-06-2015C30sonprayag triyuginarayan road ch11.760Check thickness of BMAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
11.19-06-2015C30 sonprayag triyginarayan road check 12.200Check thickness of BMAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
12.04-06-2015C30sonprayag triguginarayan road ch 11.440R Wall in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
13.04-06-2015C30sonprayag triguginarayan road ch2.450B wall completeAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
14.04-06-2015C30 sonprayag triguginarayan road ch9.450G-3 completeAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
15.04-06-2015C30sonprayag triguginarayan road ch11.400G-3 complete in km12Anil Kumar MittalEEUEAP R&B Rudraprayag See Pic
16.04-06-2015C30sonprayag triguginarayan road ch11.675Kutcha drain in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
17.04-06-2015C30sonprayag triguginarayan road ch11.715Culvert in half width completeAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
18.04-06-2015C30sonprayag triguginarayan road ch11.760R Wall in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
19.04-06-2015C30sonprayag triguginarayan road ch12.065Culvert in half width completeAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
20.04-06-2015C30 sonprayag triguginarayan road plant siteWeigh bridge at HMPAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic