UEAP/PWD/C23
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1026 |
Package Name: |
UEAP/PWD/C23 |
Sanction Cost: |
1939.00 lakhs |
District: |
Dehradun |
Block: |
Kalsi |
Constituency: |
Chakrata |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
|
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5402 Tyuni-Chakrata-Mussoorie-Chamba-Kirtinagar (47.000 KM.) (completed) |
|
Procurement: |
Package No.: 1026
Package Name:  UEAP/PWD/C23
Tender Date: 24-03-2014
Current Status: Agreement signed
Achieved on Date: 25-08-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C23
Contractor Name: Raja Construction
|
Start Date: 17-09-2014
Intended Completion Date: 16-03-2016
|
Total Bond Cost: 175103792 (1751.04 lakhs)
Variation Cost: 10214844.28 (102.15 lakhs) Hence Total Bond Cost is 185318636.28 (1853.19 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 4027392 for 46 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 45.81 KM | 28.37 | 45.81 KM | 45.81 KM | 1.53 | 28.37 | 2. | R/Wall, B/ Wall Type Protection works | 2009.00 m | 225.02 | 1619.00 m | 1619.00 m | 12.14 | 225.02 | 3. | GSB/RBI/G-1 | 2.78 KM | 15.64 | 2.78 KM | 2.78 KM | 0.84 | 15.64 | 4. | G-2 | 2.87 KM | 13.25 | 2.87 KM | 2.87 KM | 0.72 | 13.25 | 5. | G-3 | 4.10 KM | 19.20 | 4.10 KM | 4.10 KM | 1.04 | 19.20 | 6. | BM i/c Prime Coat, Tack Coat | 28.65 KM | 520.52 | 28.65 KM | 28.65 KM | 28.09 | 520.52 | 7. | SDBC i/c Tackcoat | 44.45 KM | 490.59 | 44.45 KM | 44.45 KM | 26.47 | 490.59 | 8. | Cause Way | 16.00 No | 58.88 | 14.00 No | 14.00 No | 3.18 | 58.88 | 9. | Culverts/Scupper | 57.00 No | 67.80 | 57.00 No | 57.00 No | 3.66 | 67.80 | 10. | longitudinal Drain | 44500.00 m | 72.46 | 44450.00 m | 44450.00 m | 3.91 | 72.46 | 11. | Crash Barrier | 6800.00 m | 200.41 | 6800.00 m | 6800.00 m | 10.81 | 200.41 | 12. | Parapet | 1372.00 No | 40.07 | 1269.00 No | 1269.00 No | 2.16 | 40.07 | 13. | Road Furniture | 8014.00 No | 84.62 | 14513.00 No | 14513.00 No | 4.57 | 84.62 | 14. | Other Allied Works & Finishing Work | 1.00 Job | 16.37 | 1.00 Job | 1.00 Job | 0.88 | 16.37 |
Total Amount: |
1853.2 |
|
100 |
1853.2 |
|
Remarks:
No Remarks
Work Program Made On:
25-02-2015
Updation of work program on:
21-08-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-January-2015 | 31.60 lakhs |
2. | 10-February-2015 | 41.82 lakhs |
3. | 19-March-2015 | 42.72 lakhs |
4. | 23-May-2015 | 338.75 lakhs |
5. | 20-June-2015 | 220.16 lakhs |
6. | 24-July-2015 | 118.17 lakhs |
7. | 13-October-2015 | 153.01 lakhs |
8. | 04-November-2015 | 247.91 lakhs |
9. | 26-November-2015 | 247.21 lakhs |
10. | 12-January-2016 | 160.51 lakhs |
11. | 12-February-2016 | 116.66 lakhs |
12. | 29-April-2016 | 82.42 lakhs |
13. | 29-June-2017 | 51.82 lakhs |
Total |
1852.76 lakhs |
% Payment |
99.98 % |
|
Advance Amount: 236.61 lakhs
Recovered Amount: 236.61 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 42 |
Number of Notice(s) issued: 61 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-10-2015 | 93.850 | KC drain has been completed | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
2. | 21-10-2015 | 99.800 | Measurement of WBM depth | Anuj Kumar Singh | AE | UEAP R&B Tehri | See Pic |
3. | 06-10-2015 | 98+450 | Laying of BM | Asha rawat | JE | DEA ADB Dehradun | See Pic |
4. | 27-09-2015 | CH-101+800 | BM Work | Vikas Verma | JE | UEAP R&B Tehri | See Pic |
5. | 28-08-2015 | Ch.124.370 | Laying of WBM (G-1) | Rajesh kumar | PM | DSC R&B ADB | See Pic |
6. | 28-08-2015 | Ch.124.390 | Laying of (WBM) G-1 | Rajesh kumar | PM | DSC R&B ADB | See Pic |
7. | 02-08-2015 | 100.250 | Laying of WBM Grading -2. | Rajesh kumar | PM | DSC R&B ADB | See Pic |
8. | 02-08-2015 | Ch.96.075 | Existing scrupper damage | Rajesh kumar | PM | DSC R&B ADB | See Pic |
9. | 02-08-2015 | 90.500 | Laying of sdbc | Rajesh kumar | PM | DSC R&B ADB | See Pic |
10. | 08-06-2015 | Chainage 88.200 laying of SDBC | Laying of sdbc | Rajesh kumar | PM | DSC R&B ADB | See Pic |
11. | 08-06-2015 | 127.450 | Construction of plum. | Rajesh kumar | PM | DSC R&B ADB | See Pic |
12. | 25-05-2015 | ch 96.850 | r wall under construction | Deepak Yadav | SE | ADB Circle | See Pic |
13. | 25-05-2015 | 124+407 | B/w plum concrete | Asha rawat | JE | DEA ADB Dehradun | See Pic |
14. | 25-05-2015 | 117+450 | Plum concrete work | M Amir | AE | UEAP R&B Srinagar | See Pic |
15. | 24-04-2015 | Ch.107.980 | Laying of SDBC. | Rajesh kumar | PM | DSC R&B ADB | See Pic |
16. | 24-04-2015 | 115.250 | Plum concrete of parapet | Rajesh kumar | PM | DSC R&B ADB | See Pic |
17. | 31-03-2015 | Km-119'118'&km117 | Sdbc has been done in about 2.5 km length | Shankar Ram | SE | ADB Circle | See Pic |
18. | 30-03-2015 | 124.610 | Excavation of catchpit | Rajesh kumar | PM | DSC R&B ADB | See Pic |
19. | 30-03-2015 | 104.050 | R wall | Rajesh kumar | PM | DSC R&B ADB | See Pic |
20. | 21-03-2015 | 119 | Laying tack coat. | Asha rawat | JE | DEA ADB Dehradun | See Pic |
|
|