UEAP/PWD/C20
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1023 |
Package Name: |
UEAP/PWD/C20 |
Sanction Cost: |
695.00 lakhs |
District: |
Chamoli |
Block: |
Joshimath |
Constituency: |
Badrinath |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5104 Reconstruction of Joshimath Auli Motor road under Nagar Palika Joshimath (9.000 KM.) (in prorgress) |
|
Procurement: |
Package No.: 1023
Package Name: UEAP/PWD/C20
Tender Date: 02-07-2014
Current Status: Agreement signed
Achieved on Date: 17-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C20
Contractor Name: R.G. Buildwell.
|
Start Date: 09-12-2014
Intended Completion Date: 08-06-2016
|
Total Bond Cost: 49799384 (497.99 lakhs)
Variation Cost: 53795.84 (0.54 lakhs) Hence Total Bond Cost is 49853179.84 (498.53 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1668300 for 67 days
LD Analysis for Milestone2: calculated LD is Rs 4008900 for 161 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 2. | R/Wall, B/ Wall Type Protection works | 117.00 m | 8.61 | 555.00 m | 117.00 m | 0.34 | 1.82 | 3. | GSB/RBI/G-1 | 0.02 KM | 0.30 | 0.05 KM | 0.02 KM | 0.02 | 0.12 | 4. | G-2 | 0.04 KM | 0.43 | 0.10 KM | 0.04 KM | 0.03 | 0.17 | 5. | G-3 | 0.10 KM | 0.83 | 0.24 KM | 0.10 KM | 0.07 | 0.35 | 6. | BM i/c Prime Coat, Tack Coat | 10.20 KM | 271.30 | 10.20 KM | 10.20 KM | 51.51 | 271.30 | 7. | SDBC i/c Tackcoat | 10.20 KM | 138.95 | 10.20 KM | 10.20 KM | 26.38 | 138.95 | 8. | Cause Way | 2.00 No | 4.67 | 2.00 No | 0.00 No | 0 | 0.00 | 9. | Culverts/Scupper | 3.00 No | 2.08 | 4.00 No | 2.00 No | 0.2 | 0.69 | 10. | longitudinal Drain | 1490.00 m | 15.94 | 1490.00 m | 0.00 m | 0 | 0.00 | 11. | Crash Barrier | 900.00 m | 25.20 | 900.00 m | 892.00 m | 4.74 | 24.98 | 12. | Parapet | 200.00 No | 1.10 | 900.00 No | 200.00 No | 0.05 | 0.24 | 13. | Road Furniture | 990.00 No | 21.57 | 990.00 No | 0.00 No | 0 | 0.00 | 14. | Other Allied Works & Finishing Work | 2.00 Job | 35.69 | 2.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
526.67 |
|
83.35 |
438.62 |
|
Remarks:
No Remarks
Work Program Made On:
26-02-2015
Updation of work program on:
26-02-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-May-2015 | 7.91 lakhs |
2. | 20-October-2015 | 168.49 lakhs |
3. | 25-January-2016 | 32.33 lakhs |
4. | 30-March-2016 | 10.65 lakhs |
5. | 19-June-2016 | 48.65 lakhs |
6. | 29-August-2016 | 62.26 lakhs |
7. | 17-June-2017 | 18.64 lakhs |
Total |
348.93 lakhs |
% Payment |
69.99 % |
|
Advance Amount: 182.46 lakhs
Recovered Amount: 27.36 lakhs
Balance to be Recovered 155.10 lakhs
* Advances are at package level not sub project level
|
Analysis:Bill should be issued |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | No Pending Issue | Environment & Social Compliances(Sub Project level): | Reconstruction of Joshimath Auli Motor road under Nagar Palika Joshimath(5104) | Borrow pits, DG set |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 116 |
Number of Notice(s) issued: 68 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 09-06-2016 | Auli road / 11+900 | Tack coat spraying for BM laying at Auli road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
2. | 09-06-2016 | Auli road /11+850 | BM laying & rolling work progress for Auli road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
3. | 09-06-2016 | Auli road / 11+780 | BM laying in progress at Auli road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
4. | 09-06-2016 | Auli road / 11+825 | Compressor cleaning work progress for BM laying | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
5. | 03-06-2016 | Auli road / 11+475 | BM laying in progress for another one km. | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
6. | 03-06-2016 | Auli road /11+380 | BM laying & rolling work progress for another one km. | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
7. | 03-06-2016 | Auli road / 11+380 | BM laying in progress for another one km. | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
8. | 03-06-2016 | Auli road / 11+400 | Tack coat spraying for BM laying another one km. | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
9. | 03-06-2016 | Auli road /11+425 | Surface cleaning for BM laying for another one km. | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
10. | 02-06-2016 | RGB HMP / Nandprayag | BM mix material production for joshimath Auli road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
11. | 27-03-2016 | Auli road /4+350 | Parapet construction work progress for joshimath -Auli road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
12. | 05-02-2016 | 9+925 | Fixing of Delinators | Ravi Shankar Shukla | QC | UEAP R&B Chamoli | See Pic |
13. | 20-12-2015 | Auli road /7+300 | Visit at site social experts Dr.Debasish Bhattacharya | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
14. | 04-11-2015 | Auli road/ 7+950 | Edge markings work in progress at Auli road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
15. | 09-10-2015 | Joshimath Aulli / 3+350 | Consultant,contractor and client ,Joint measurement of BM/SDBC in joshimath Aulli | Shubham Shandilya | Technical Assistant | DSC2 ADB | See Pic |
16. | 07-10-2015 | Km 2.765,Joshimath Auli motor road. | BM laying in progress. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
17. | 06-10-2015 | Joshimath Aulli / 9+425 | SDBC IN PROGRESS | Shubham Shandilya | Technical Assistant | DSC2 ADB | See Pic |
18. | 05-10-2015 | Auli road /9+325 | BM laying & rolling on progress for joshimath -- Auli road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
19. | 05-10-2015 | AULI ROAD CH. 9+350 | BM Laying and compacting | Vinod Negi | EE | UEAP R&B Chamoli | See Pic |
20. | 05-10-2015 | Auli road /9+450 | BM laying in progress for joshimath -- Auli road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
|
|