Package Profile Report

UEAP/PWD/C20 Agreement signed
Project: UEAP-RB Package No.: 1023 Package Name: UEAP/PWD/C20 Sanction Cost: 695.00  lakhs
District: Chamoli Block: Joshimath Constituency: Badrinath Circle:
DEA: DEA UEAP Chamoli DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5104   Reconstruction of Joshimath Auli Motor road under Nagar Palika Joshimath (9.000 KM.) (in prorgress)
Procurement:
Package No.: 1023        Package Name: UEAP/PWD/C20        Tender Date: 02-07-2014        Current Status: Agreement signed        Achieved on Date: 17-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C20        Contractor Name: R.G. Buildwell.       
Start Date: 09-12-2014        Intended Completion Date: 08-06-2016       
Total Bond Cost: 49799384 (497.99 lakhs)        Variation Cost: 53795.84 (0.54 lakhs)     Hence Total Bond Cost is   49853179.84 (498.53 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 1668300 for 67 days        LD Analysis for Milestone2: calculated LD is Rs 4008900 for 161 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.00 KM0.000.00 KM0.00 KM00.00
2.R/Wall, B/ Wall Type Protection works117.00 m8.61555.00 m117.00 m0.341.82
3.GSB/RBI/G-10.02 KM0.300.05 KM0.02 KM0.020.12
4.G-20.04 KM0.430.10 KM0.04 KM0.030.17
5.G-30.10 KM0.830.24 KM0.10 KM0.070.35
6.BM i/c Prime Coat, Tack Coat10.20 KM271.3010.20 KM10.20 KM51.51271.30
7.SDBC i/c Tackcoat10.20 KM138.9510.20 KM10.20 KM26.38138.95
8.Cause Way2.00 No4.672.00 No0.00 No00.00
9.Culverts/Scupper 3.00 No2.084.00 No2.00 No0.20.69
10.longitudinal Drain1490.00 m15.941490.00 m0.00 m00.00
11.Crash Barrier900.00 m25.20900.00 m892.00 m4.7424.98
12.Parapet200.00 No1.10900.00 No200.00 No0.050.24
13.Road Furniture990.00 No21.57990.00 No0.00 No00.00
14.Other Allied Works & Finishing Work 2.00 Job35.692.00 Job0.00 Job00.00
Total Amount: 526.67 83.35   438.62
Remarks: No Remarks       Work Program Made On: 26-02-2015       Updation of work program on: 26-02-2017      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.29-May-20157.91  lakhs
2.20-October-2015168.49  lakhs
3.25-January-201632.33  lakhs
4.30-March-201610.65  lakhs
5.19-June-201648.65  lakhs
6.29-August-201662.26  lakhs
7.17-June-201718.64  lakhs
Total 348.93  lakhs
% Payment 69.99 %
Advance Amount:  182.46  lakhs        Recovered Amount:  27.36  lakhs        Balance to be Recovered  155.10  lakhs        * Advances are at package level not sub project level
Analysis:Bill should be issued
Pending Environmental & Social issues
Environment & Social Compliances(Package level):No Pending Issue
Environment & Social Compliances(Sub Project level):
Reconstruction of Joshimath Auli Motor road under Nagar Palika Joshimath(5104) Borrow pits, DG set
Detailed report of this Package
Quality
No. of Test Required : 44     No. of Test Done : 72      No. of Test Passed : 72      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 116
Number of Notice(s) issued: 68

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.09-06-2016Auli road / 11+900Tack coat spraying for BM laying at Auli roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
2.09-06-2016Auli road /11+850BM laying & rolling work progress for Auli roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
3.09-06-2016Auli road / 11+780BM laying in progress at Auli roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
4.09-06-2016Auli road / 11+825Compressor cleaning work progress for BM layingSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
5.03-06-2016Auli road / 11+475BM laying in progress for another one km.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
6.03-06-2016Auli road /11+380BM laying & rolling work progress for another one km.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
7.03-06-2016Auli road / 11+380BM laying in progress for another one km.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
8.03-06-2016Auli road / 11+400Tack coat spraying for BM laying another one km.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
9.03-06-2016Auli road /11+425Surface cleaning for BM laying for another one km.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
10.02-06-2016RGB HMP / NandprayagBM mix material production for joshimath Auli roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
11.27-03-2016Auli road /4+350Parapet construction work progress for joshimath -Auli roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
12.05-02-20169+925Fixing of DelinatorsRavi Shankar ShuklaQCUEAP R&B Chamoli See Pic
13.20-12-2015Auli road /7+300Visit at site social experts Dr.Debasish BhattacharyaSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
14.04-11-2015Auli road/ 7+950Edge markings work in progress at Auli roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
15.09-10-2015Joshimath Aulli / 3+350Consultant,contractor and client ,Joint measurement of BM/SDBC in joshimath AulliShubham ShandilyaTechnical AssistantDSC2 ADB See Pic
16.07-10-2015Km 2.765,Joshimath Auli motor road.BM laying in progress.Atul ShandilyaAEUEAP R&B Chamoli See Pic
17.06-10-2015Joshimath Aulli / 9+425SDBC IN PROGRESSShubham ShandilyaTechnical AssistantDSC2 ADB See Pic
18.05-10-2015Auli road /9+325BM laying & rolling on progress for joshimath -- Auli roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
19.05-10-2015AULI ROAD CH. 9+350BM Laying and compactingVinod NegiEEUEAP R&B Chamoli See Pic
20.05-10-2015Auli road /9+450BM laying in progress for joshimath -- Auli roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic