UEAP/PWD/C19
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1022 |
Package Name: |
UEAP/PWD/C19 |
Sanction Cost: |
300.00 lakhs |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Kapkote |
Circle: |
|
DEA: |
DEA UEAP Bageshwar |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5702 Reconstruction of Internal road of Nagar Panchayat Kafkot (7.250 KM.) (completed) |
|
Procurement: |
Package No.: 1022
Package Name: UEAP/PWD/C19
Tender Date: 07-03-2014
Current Status: Agreement signed
Achieved on Date: 29-09-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C19
Contractor Name: Bharat Construction
|
Start Date: 08-10-2014
Intended Completion Date: 30-04-2017
Original End Date: 07-01-2016
|
Total Bond Cost: 33201340 (332.01 lakhs)
Variation Cost: -1387167.00 (-13.87 lakhs) Hence Total Bond Cost is 31814173 (318.14 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1875913 for 113 days
LD Analysis for Milestone2: calculated LD is Rs 1494090 for 90 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 4.00 KM | 1.38 | 4.00 KM | 4.00 KM | 0.43 | 1.38 | 2. | R/Wall, B/ Wall Type Protection works | 300.00 m | 32.42 | 300.00 m | 300.00 m | 10.19 | 32.42 | 3. | GSB/RBI/G-1 | 4.00 KM | 51.92 | 4.00 KM | 4.00 KM | 16.32 | 51.92 | 4. | G-2 | 4.00 KM | 43.32 | 4.00 KM | 4.00 KM | 13.62 | 43.32 | 5. | G-3 | 4.00 KM | 33.32 | 4.00 KM | 4.00 KM | 10.48 | 33.32 | 6. | PC/CC i/c Prime Coat, Tack Coat | 5.75 KM | 78.56 | 5.75 KM | 5.75 KM | 24.7 | 78.56 | 7. | Cause Way | 3.00 No | 7.21 | 3.00 No | 3.00 No | 2.27 | 7.21 | 8. | Culverts/Scupper | 2.00 No | 3.47 | 2.00 No | 2.00 No | 1.09 | 3.47 | 9. | longitudinal Drain | 5898.00 m | 57.03 | 5898.00 m | 5898.00 m | 17.93 | 57.03 | 10. | Crash Barrier | 200.00 m | 5.00 | 200.00 m | 200.00 m | 1.57 | 5.00 | 11. | Other Allied Works & Finishing Work | 1.00 Job | 4.49 | 1.00 Job | 1.00 Job | 1.41 | 4.49 |
Total Amount: |
318.12 |
|
100 |
318.12 |
|
Remarks:
No Remarks
Work Program Made On:
26-06-2015
Updation of work program on:
05-08-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 23-January-2015 | 33.87 lakhs |
2. | 29-June-2015 | 32.19 lakhs |
3. | 17-October-2015 | 65.34 lakhs |
4. | 31-October-2015 | 31.16 lakhs |
5. | 04-January-2016 | 38.91 lakhs |
6. | 28-January-2016 | 27.26 lakhs |
7. | 29-February-2016 | 14.80 lakhs |
8. | 22-March-2016 | 19.41 lakhs |
9. | 31-March-2016 | 39.65 lakhs |
10. | 13-December-2016 | 15.55 lakhs |
Total |
318.14 lakhs |
% Payment |
100 % |
|
Advance Amount: 33.20 lakhs
Recovered Amount: 33.20 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 13 |
Number of Notice(s) issued: 76 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-03-2016 | Ch.1.550 kapkot polling m/r pkg.C- 19 | check thickness of G1,2,3 | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
2. | 13-10-2015 | 0 point bhayun village/O.000too.o30 | P.c laying &compection in bhayun guler m/r nagerpanchayat kapkot pak.-19 | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
3. | 13-10-2015 | Near bhayun village/0.040-0.060 | Compection of G-3 in nager panchayat kapkot pak.19 | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
4. | 13-10-2015 | 0.030-0.050 near bhayun village | Laying & compection of G3 in
Nager panchayat kapkot pak.19 | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
5. | 21-09-2015 | Bhiuyn guler chainage 1.450 near gas godam | Bhiyun guler Ch 1.450 | R C Pandey | AE | DEA WB Bageshwar | See Pic |
6. | 13-07-2015 | Ch 0.300 | G 2 in bhiyun guler motor road | R C Pandey | AE | DEA WB Bageshwar | See Pic |
7. | 27-06-2015 | BAIF center | CH.1.160 Kapkot karmi m/r | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
8. | 13-06-2015 | Ch(0 .140) | Construction of side drain in Kapkot poling road | R C Pandey | AE | DEA WB Bageshwar | See Pic |
9. | 02-06-2015 | Ch. 0.40 km kapkot karmi road | PC work in progress in kapkot karmi motor road | Deepak Kumar | EE | DEA ADB Bageshwar | See Pic |
10. | 20-03-2015 | 1.750-1.800 | bhayn guler | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
11. | 20-03-2015 | ch 0.000-0.025 | tehsil approch | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
12. | 20-03-2015 | ch 2.625-2.650 | kapkotkarmi befor construction | Jagdish Kumar Tamta | AAE | UEAP R&B Bageshwar | See Pic |
13. | 20-03-2015 | Ch 0.950_0.975 | Bhiyun guler road | R C Pandey | AE | DEA WB Bageshwar | See Pic |
|
|