Package Profile Report

UDRP/PWD/08/05/RD/091 Agreement signed
Project: UDRP-RB Package No.: 102 Package Name: UDRP/PWD/08/05/RD/091 Sanction Cost: 1014.60  lakhs
District: Bageshwar Block: Bageshwar Constituency: Bageshwar Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: only Supervision No.of Sub project : 1
Subproject in this package
1  1102   Bageshwar-Girichhina MR (13.400 KM.) (completed)
Procurement:
Package No.: 102        Package Name: UDRP/PWD/08/05/RD/091        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 13-01-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/05/RD/091        Contractor Name: Parihar Construction       
Start Date: 20-01-2016        Intended Completion Date: 31-08-2017        Original End Date:  19-01-2017
Total Bond Cost: 46841261.26 (468.41 lakhs)        Variation Cost: -2801363.78 (-28.01 lakhs)     Hence Total Bond Cost is   44039897.48 (440.4 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 1147629 for 49 days        LD Analysis for Milestone2: calculated LD is Rs 3864465 for 165 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence5.00 KM75.214.50 KM4.50 KM17.0875.21
2.R/Wall, B/ Wall Type Protection works1535.00 m143.991535.00 m1535.00 m32.69143.99
3.GSB/RBI/G-15.00 KM27.224.50 KM4.50 KM6.1827.22
4.G-25.00 KM27.614.50 KM4.50 KM6.2727.61
5.G-35.00 KM35.074.50 KM4.50 KM7.9635.07
6.PC/CC i/c Prime Coat, Tack Coat5.00 KM64.564.50 KM4.50 KM14.6664.56
7.Cause Way1.00 No3.692.00 No2.00 No0.843.69
8.Culverts/Scupper 10.00 No24.1314.00 No14.00 No5.4824.13
9.longitudinal Drain4844.00 m6.054500.00 m4500.00 m1.376.05
10.Crash Barrier150.00 m4.121000.00 m1000.00 m0.944.12
11.Parapet255.00 No7.8490.00 No90.00 No1.787.84
12.Road Furniture113.00 No1.7493.00 No93.00 No0.41.74
13.Other Allied Works & Finishing Work 3.00 Job19.183.00 Job3.00 Job4.3619.18
Total Amount: 440.41 100   440.41
Remarks: No Remarks       Work Program Made On: 15-02-2016       Updation of work program on: 28-11-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.04-May-201664.12  lakhs
2.28-June-201625.39  lakhs
3.30-August-201623.97  lakhs
4.24-October-201622.25  lakhs
5.16-December-20162.64  lakhs
6.06-February-201757.02  lakhs
7.28-March-201779.15  lakhs
8.29-June-2017109.71  lakhs
9.28-March-201853.03  lakhs
Total 437.28  lakhs
% Payment 99.29 %
Advance Amount:  54.94  lakhs        Recovered Amount:  54.94  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 332     No. of Test Done : 336      No. of Test Passed : 331      No. of Test Failed : 5   Test report of this package
Number of Pics Available on Web Repository: 112
Number of Notice(s) issued: 55

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-08-2017Ch 13.900B/wall constructionJagdish Narayan Meenaunknownunknown See Pic
2.21-08-2017Ch 14.060B/wallJagdish Narayan Meenaunknownunknown See Pic
3.21-08-2017Ch 14.200SRMD, heavy bouldersJagdish Narayan Meenaunknownunknown See Pic
4.21-08-2017Ch 14.560SRMD, heavy bouldersJagdish Narayan Meenaunknownunknown See Pic
5.01-08-2017Ch 14.200SRMD, road block due to heavy bouldersJagdish Narayan Meenaunknownunknown See Pic
6.01-08-2017Ch 14.500SRMD, road damaged due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
7.01-08-2017Ch 14.500SRMD, road surface damaged due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
8.01-08-2017Ch 14.240SRMD, road block due to heavy bouldersJagdish Narayan Meenaunknownunknown See Pic
9.12-06-2017Ch 12.750Tack coat for PCJagdish Narayan Meenaunknownunknown See Pic
10.11-06-2017Ch 12.700Rolling over seal coatJagdish Narayan Meenaunknownunknown See Pic
11.11-06-2017Ch 12.670Rolling over seal coatJagdish Narayan Meenaunknownunknown See Pic
12.11-06-2017Ch 12+770PC surfaceJagdish Narayan Meenaunknownunknown See Pic
13.11-06-2017Ch 12.720PC surfaceJagdish Narayan Meenaunknownunknown See Pic
14.11-06-2017Ch 12.700Rolling over PCJagdish Narayan Meenaunknownunknown See Pic
15.11-06-2017Ch 12.630Tack coat for PCJagdish Narayan Meenaunknownunknown See Pic
16.11-06-2017Ch 12.800PC surface after seal coatJagdish Narayan Meenaunknownunknown See Pic
17.08-06-201713+960Seal coat work in progressMohd Irfan QureshiQCDSC5 R&B WB Bageshwar See Pic
18.08-06-201713+960Seal coat work in progressMohd Irfan QureshiQCDSC5 R&B WB Bageshwar See Pic
19.08-06-2017Ch 13.200Laying of PCJagdish Narayan Meenaunknownunknown See Pic
20.08-06-2017Ch 13.270PC surface after seal coatJagdish Narayan Meenaunknownunknown See Pic