UDRP/PWD/08/05/RD/091
Agreement signed
|
Project: |
UDRP-RB |
Package No.: |
102 |
Package Name: |
UDRP/PWD/08/05/RD/091 |
Sanction Cost: |
1014.60 lakhs |
District: |
Bageshwar |
Block: |
Bageshwar |
Constituency: |
Bageshwar |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
only Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 1102 Bageshwar-Girichhina MR (13.400 KM.) (completed) |
|
Procurement: |
Package No.: 102
Package Name: UDRP/PWD/08/05/RD/091
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 13-01-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/05/RD/091
Contractor Name: Parihar Construction
|
Start Date: 20-01-2016
Intended Completion Date: 31-08-2017
Original End Date: 19-01-2017
|
Total Bond Cost: 46841261.26 (468.41 lakhs)
Variation Cost: -2801363.78 (-28.01 lakhs) Hence Total Bond Cost is 44039897.48 (440.4 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 1147629 for 49 days
LD Analysis for Milestone2: calculated LD is Rs 3864465 for 165 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 5.00 KM | 75.21 | 4.50 KM | 4.50 KM | 17.08 | 75.21 | 2. | R/Wall, B/ Wall Type Protection works | 1535.00 m | 143.99 | 1535.00 m | 1535.00 m | 32.69 | 143.99 | 3. | GSB/RBI/G-1 | 5.00 KM | 27.22 | 4.50 KM | 4.50 KM | 6.18 | 27.22 | 4. | G-2 | 5.00 KM | 27.61 | 4.50 KM | 4.50 KM | 6.27 | 27.61 | 5. | G-3 | 5.00 KM | 35.07 | 4.50 KM | 4.50 KM | 7.96 | 35.07 | 6. | PC/CC i/c Prime Coat, Tack Coat | 5.00 KM | 64.56 | 4.50 KM | 4.50 KM | 14.66 | 64.56 | 7. | Cause Way | 1.00 No | 3.69 | 2.00 No | 2.00 No | 0.84 | 3.69 | 8. | Culverts/Scupper | 10.00 No | 24.13 | 14.00 No | 14.00 No | 5.48 | 24.13 | 9. | longitudinal Drain | 4844.00 m | 6.05 | 4500.00 m | 4500.00 m | 1.37 | 6.05 | 10. | Crash Barrier | 150.00 m | 4.12 | 1000.00 m | 1000.00 m | 0.94 | 4.12 | 11. | Parapet | 255.00 No | 7.84 | 90.00 No | 90.00 No | 1.78 | 7.84 | 12. | Road Furniture | 113.00 No | 1.74 | 93.00 No | 93.00 No | 0.4 | 1.74 | 13. | Other Allied Works & Finishing Work | 3.00 Job | 19.18 | 3.00 Job | 3.00 Job | 4.36 | 19.18 |
Total Amount: |
440.41 |
|
100 |
440.41 |
|
Remarks:
No Remarks
Work Program Made On:
15-02-2016
Updation of work program on:
28-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 04-May-2016 | 64.12 lakhs |
2. | 28-June-2016 | 25.39 lakhs |
3. | 30-August-2016 | 23.97 lakhs |
4. | 24-October-2016 | 22.25 lakhs |
5. | 16-December-2016 | 2.64 lakhs |
6. | 06-February-2017 | 57.02 lakhs |
7. | 28-March-2017 | 79.15 lakhs |
8. | 29-June-2017 | 109.71 lakhs |
9. | 28-March-2018 | 53.03 lakhs |
Total |
437.28 lakhs |
% Payment |
99.29 % |
|
Advance Amount: 54.94 lakhs
Recovered Amount: 54.94 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 112 |
Number of Notice(s) issued: 55 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-08-2017 | Ch 13.900 | B/wall construction | Jagdish Narayan Meena | unknown | unknown | See Pic |
2. | 21-08-2017 | Ch 14.060 | B/wall | Jagdish Narayan Meena | unknown | unknown | See Pic |
3. | 21-08-2017 | Ch 14.200 | SRMD, heavy boulders | Jagdish Narayan Meena | unknown | unknown | See Pic |
4. | 21-08-2017 | Ch 14.560 | SRMD, heavy boulders | Jagdish Narayan Meena | unknown | unknown | See Pic |
5. | 01-08-2017 | Ch 14.200 | SRMD, road block due to heavy boulders | Jagdish Narayan Meena | unknown | unknown | See Pic |
6. | 01-08-2017 | Ch 14.500 | SRMD, road damaged due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
7. | 01-08-2017 | Ch 14.500 | SRMD, road surface damaged due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
8. | 01-08-2017 | Ch 14.240 | SRMD, road block due to heavy boulders | Jagdish Narayan Meena | unknown | unknown | See Pic |
9. | 12-06-2017 | Ch 12.750 | Tack coat for PC | Jagdish Narayan Meena | unknown | unknown | See Pic |
10. | 11-06-2017 | Ch 12.700 | Rolling over seal coat | Jagdish Narayan Meena | unknown | unknown | See Pic |
11. | 11-06-2017 | Ch 12.670 | Rolling over seal coat | Jagdish Narayan Meena | unknown | unknown | See Pic |
12. | 11-06-2017 | Ch 12+770 | PC surface | Jagdish Narayan Meena | unknown | unknown | See Pic |
13. | 11-06-2017 | Ch 12.720 | PC surface | Jagdish Narayan Meena | unknown | unknown | See Pic |
14. | 11-06-2017 | Ch 12.700 | Rolling over PC | Jagdish Narayan Meena | unknown | unknown | See Pic |
15. | 11-06-2017 | Ch 12.630 | Tack coat for PC | Jagdish Narayan Meena | unknown | unknown | See Pic |
16. | 11-06-2017 | Ch 12.800 | PC surface after seal coat | Jagdish Narayan Meena | unknown | unknown | See Pic |
17. | 08-06-2017 | 13+960 | Seal coat work in progress | Mohd Irfan Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
18. | 08-06-2017 | 13+960 | Seal coat work in progress | Mohd Irfan Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
19. | 08-06-2017 | Ch 13.200 | Laying of PC | Jagdish Narayan Meena | unknown | unknown | See Pic |
20. | 08-06-2017 | Ch 13.270 | PC surface after seal coat | Jagdish Narayan Meena | unknown | unknown | See Pic |
|
|