Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C17-A Agreement signed
Project: UEAP-RB Package No.: 1019 Package Name: UEAP/PWD/C17-A Sanction Cost: 285.00  lakhs
District: Almora Block: Tarikhet Constituency: Ranikhet Circle:
DEA: DEA UEAP Almora DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5806   Reconstruction of internal road of Nagar Panchayat Ranikhet (6.000 KM.) (completed)
Procurement:
Package No.: 1019        Package Name: UEAP/PWD/C17-A        Tender Date: 28-03-2014        Current Status: Agreement signed        Achieved on Date: 26-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C17-A        Contractor Name: R.G. Buildwell.       
Start Date: 16-12-2014        Intended Completion Date: 26-10-2016        Original End Date:  15-06-2016
Total Bond Cost: 31282100 (312.82 lakhs)        Variation Cost: 717899.50 (7.18 lakhs)     Hence Total Bond Cost is   31999999.5 (320 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence3.67 KM6.453.67 KM3.67 KM2.036.45
2.R/Wall, B/ Wall Type Protection works200.00 m3.91200.00 m200.00 m1.233.91
3.GSB/RBI/G-13.65 KM31.493.65 KM3.65 KM9.9231.49
4.G-23.65 KM7.463.65 KM3.65 KM2.357.46
5.G-33.65 KM7.833.65 KM3.65 KM2.477.83
6.PC/CC i/c Prime Coat, Tack Coat3.67 KM60.273.67 KM3.67 KM18.9860.27
7.BM i/c Prime Coat, Tack Coat0.20 KM6.910.20 KM0.20 KM2.186.91
8.SDBC i/c Tackcoat2.00 KM47.702.00 KM2.00 KM15.0347.70
9.Culverts/Scupper 3.00 No3.253.00 No3.00 No1.023.25
10.longitudinal Drain3643.75 m57.313643.75 m3643.75 m18.0557.31
11.Crash Barrier950.00 m29.45950.00 m950.00 m9.2829.45
12.Road Furniture60.00 No53.5860.00 No60.00 No16.8853.58
13.Other Allied Works & Finishing Work 1.00 Job1.871.00 Job1.00 Job0.591.87
Total Amount: 317.48 100   317.48
Remarks: Work Completed.       Work Program Made On: 24-06-2015       Updation of work program on: 20-09-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-201582.87  lakhs
2.25-June-201525.42  lakhs
3.07-November-201545.19  lakhs
4.29-February-201616.71  lakhs
5.31-March-201612.17  lakhs
6.08-September-201624.40  lakhs
7.25-October-201610.69  lakhs
8.25-March-201728.71  lakhs
9.20-June-201731.78  lakhs
10.13-October-201739.55  lakhs
Total 317.49  lakhs
% Payment 99.22 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.31  lakhs        Balance to be Recovered  -0.31  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 140     No. of Test Done : 135      No. of Test Passed : 122      No. of Test Failed : 0      No. of Test Result Awaited : 10   Test report of this package
Number of Pics Available on Web Repository: 41
Number of Notice(s) issued: 76

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-02-2017Ch 30.500Interlocking tiling work is completedGaurav BishtJEUEAP R&B Almora See Pic
2.08-02-2017Ch 30.700 near Vijay chokInterlocking tiling work is comletedGaurav BishtJEUEAP R&B Almora See Pic
3.08-02-2017Ch 30.300 near Vijay ChaukInterlocking tiling work is in progress.Gaurav BishtJEUEAP R&B Almora See Pic
4.29-08-2016Ch 27.200KC Drain work is in progressGaurav BishtJEUEAP R&B Almora See Pic
5.28-08-2016Ch 30.900Interlocking pavement work is in progressGaurav BishtJEUEAP R&B Almora See Pic
6.28-08-2016Ch 28.850Interlocking pavement work is in progress near KMOU stationGaurav BishtJEUEAP R&B Almora See Pic
7.28-08-2016Ch 27.800KC Drain work completedGaurav BishtJEUEAP R&B Almora See Pic
8.28-08-2016Ch 27.450KC Drain work completedGaurav BishtJEUEAP R&B Almora See Pic
9.28-08-2016Ch 27.500KC Drain work completedGaurav BishtJEUEAP R&B Almora See Pic
10.28-08-2016Ch 26.600Crash barrier work completedGaurav BishtJEUEAP R&B Almora See Pic
11.11-05-2016Ch 29.250Interlocking tile work in progress near taxi stand KMOU stationChetan BhattJEUEAP R&B Almora See Pic
12.07-05-2016Ch 28.700K C drain after completionChetan BhattJEUEAP R&B Almora See Pic
13.07-05-2016Ch 28.700KC drain in progressChetan BhattJEUEAP R&B Almora See Pic
14.26-04-2016Ch 29.400Fixing of curve stone for KC Drain in progressChetan BhattJEUEAP R&B Almora See Pic
15.08-04-2016Ch 26.500OPC cement used at siteChetan BhattJEUEAP R&B Almora See Pic
16.01-04-2016Ch 26.060Delenators fixed at siteChetan BhattJEUEAP R&B Almora See Pic
17.14-03-2016Ch 29.200Staking of interlocking tileChetan BhattJEUEAP R&B Almora See Pic
18.14-03-2016Ch 29.200Excavation for KC drainChetan BhattJEUEAP R&B Almora See Pic
19.12-03-2016Ch 29.500Excavation for hume pipe in progressChetan BhattJEUEAP R&B Almora See Pic
20.12-03-2016Ch 29.500Excavation for hume pipeChetan BhattJEUEAP R&B Almora See Pic