UEAP/PWD/C16
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1018 |
Package Name: |
UEAP/PWD/C16 |
Sanction Cost: |
907.00 lakhs |
District: |
Almora |
Block: |
Hawal Bagh |
Constituency: |
Almora |
Circle: |
|
DEA: |
DEA UEAP Almora |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5805 Reconstruction of internal road of Nagar Panchayat Almora (12.000 KM.) (completed) |
|
Procurement: |
Package No.: 1018
Package Name: UEAP/PWD/C16
Tender Date: 02-07-2014
Current Status: Agreement signed
Achieved on Date: 26-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C16
Contractor Name: R.G. Buildwell.
|
Start Date: 16-12-2014
Intended Completion Date: 26-10-2016
Original End Date: 15-06-2016
|
Total Bond Cost: 69197345.75 (691.97 lakhs)
Variation Cost: 17502654.39 (175.03 lakhs) Hence Total Bond Cost is 86700000.14 (867 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 5.00 KM | 10.30 | 5.00 KM | 5.00 KM | 1.19 | 10.30 | 2. | R/Wall, B/ Wall Type Protection works | 380.00 m | 21.20 | 380.00 m | 380.00 m | 2.45 | 21.20 | 3. | GSB/RBI/G-1 | 1.14 KM | 1.75 | 1.14 KM | 1.14 KM | 0.2 | 1.75 | 4. | G-2 | 1.14 KM | 2.06 | 1.14 KM | 1.14 KM | 0.24 | 2.06 | 5. | G-3 | 1.77 KM | 9.35 | 1.77 KM | 1.77 KM | 1.08 | 9.35 | 6. | PC/CC i/c Prime Coat, Tack Coat | 3.21 KM | 16.29 | 3.21 KM | 3.21 KM | 1.88 | 16.29 | 7. | BM i/c Prime Coat, Tack Coat | 6.58 KM | 238.55 | 6.58 KM | 6.58 KM | 27.51 | 238.55 | 8. | SDBC i/c Tackcoat | 11.28 KM | 230.73 | 11.28 KM | 11.28 KM | 26.61 | 230.73 | 9. | Cause Way | 3.00 No | 67.33 | 3.00 No | 3.00 No | 7.77 | 67.33 | 10. | Culverts/Scupper | 3.00 No | 2.36 | 3.00 No | 3.00 No | 0.27 | 2.36 | 11. | longitudinal Drain | 12450.00 m | 94.14 | 13450.00 m | 13450.00 m | 10.86 | 94.14 | 12. | Crash Barrier | 3980.00 m | 115.48 | 3980.00 m | 3980.00 m | 13.32 | 115.48 | 13. | Parapet | 65.00 No | 2.08 | 65.00 No | 65.00 No | 0.24 | 2.08 | 14. | Road Furniture | 72.00 No | 53.14 | 72.00 No | 72.00 No | 6.13 | 53.14 | 15. | Other Allied Works & Finishing Work | 1.00 Job | 2.28 | 1.00 Job | 1.00 Job | 0.26 | 2.28 |
Total Amount: |
867.04 |
|
100 |
867.04 |
|
Remarks:
Work Completed.
Work Program Made On:
24-06-2015
Updation of work program on:
20-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-March-2015 | 72.11 lakhs |
2. | 23-June-2015 | 106.33 lakhs |
3. | 20-October-2015 | 290.56 lakhs |
4. | 04-November-2015 | 49.51 lakhs |
5. | 20-December-2015 | 83.65 lakhs |
6. | 16-April-2016 | 68.24 lakhs |
7. | 30-April-2016 | 16.35 lakhs |
8. | 04-August-2016 | 45.21 lakhs |
9. | 17-October-2016 | 26.49 lakhs |
10. | 27-October-2016 | 13.30 lakhs |
11. | 17-December-2016 | 10.56 lakhs |
12. | 14-February-2017 | 37.74 lakhs |
13. | 25-March-2017 | 9.66 lakhs |
14. | 31-May-2017 | 13.93 lakhs |
15. | 29-September-2017 | 23.37 lakhs |
Total |
867.01 lakhs |
% Payment |
100 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 838 No. of Test Done : 846 No. of Test Passed : 813 No. of Test Failed : 0 No. of Test Result Awaited : 5
Test report of this package
|
|
Number of Pics Available on Web Repository: 82 |
Number of Notice(s) issued: 71 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-07-2017 | Internel Road Nagar Panchayat Almora Near Ex.Eng.ADB UEAP Division Office Almora | Plantation in Harela Festival. | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
2. | 08-02-2017 | Ch5.480 | After completion of work | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
3. | 08-02-2017 | Km 4 ofA B A Road Internal Road of Nagar Panchayat Almora | After completion of work | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
4. | 28-09-2016 | Ch 3.850 of APR Road | Core Cutting of BM/SDBC work | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
5. | 01-09-2016 | 4.800 APR Road | Core Cutting of SDBC | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
6. | 01-09-2016 | Ch 3.950 APR Road | Core Cutting of BM/SDBC work | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
7. | 30-08-2016 | L R Sah Road | Excavation for k C type drain in progress | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
8. | 28-08-2016 | L R Sah Road | Drain work is in progress | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
9. | 28-08-2016 | Ch 9+650 | R/Wall is in progress | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
10. | 28-08-2016 | B A B Road Ch4+300 | After completion of thermoplastic paint | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
11. | 29-04-2016 | km 5 pkg c16 | base concrete of 1:3:6 for kc type drain | Shahnawaz Ali | JE | UEAP R&B Almora | See Pic |
12. | 29-04-2016 | pkg c-16 km5 | KC TYPE DRAIN pkg c16 | Shahnawaz Ali | JE | UEAP R&B Almora | See Pic |
13. | 08-04-2016 | A P R Road near circle office ADB UEAP Almora | SDBC work is in progress | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
14. | 07-04-2016 | Ch.0.800 (Near SE UEAP office ) | SDBC Work is in progress | Gaurav Bisht | JE | UEAP R&B Almora | See Pic |
15. | 05-04-2016 | Km 3 | Laying of SDBC in progress | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
16. | 31-03-2016 | Cho.350 of A P R Road | K C drain work is in progress | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
17. | 17-03-2016 | Ch0.150of Saraswati Mandir to Dhungadhara Road | Inspection of s d bc workS E ADB UEAP Circle Almora | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
18. | 09-03-2016 | Ch4.000 | Laying of SDBC in progress | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
19. | 09-03-2016 | Ch4.300 | Inspection of SDBC Work by DSC 3 | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
20. | 09-03-2016 | Ch4.400 | Laying of SDBCwork is in progress | Ravi Shankar Joshi | AE | UEAP R&B Almora | See Pic |
|
|