Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C16 Agreement signed
Project: UEAP-RB Package No.: 1018 Package Name: UEAP/PWD/C16 Sanction Cost: 907.00  lakhs
District: Almora Block: Hawal Bagh Constituency: Almora Circle:
DEA: DEA UEAP Almora DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5805   Reconstruction of internal road of Nagar Panchayat Almora (12.000 KM.) (completed)
Procurement:
Package No.: 1018        Package Name: UEAP/PWD/C16        Tender Date: 02-07-2014        Current Status: Agreement signed        Achieved on Date: 26-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C16        Contractor Name: R.G. Buildwell.       
Start Date: 16-12-2014        Intended Completion Date: 26-10-2016        Original End Date:  15-06-2016
Total Bond Cost: 69197345.75 (691.97 lakhs)        Variation Cost: 17502654.39 (175.03 lakhs)     Hence Total Bond Cost is   86700000.14 (867 lakhs) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence5.00 KM10.305.00 KM5.00 KM1.1910.30
2.R/Wall, B/ Wall Type Protection works380.00 m21.20380.00 m380.00 m2.4521.20
3.GSB/RBI/G-11.14 KM1.751.14 KM1.14 KM0.21.75
4.G-21.14 KM2.061.14 KM1.14 KM0.242.06
5.G-31.77 KM9.351.77 KM1.77 KM1.089.35
6.PC/CC i/c Prime Coat, Tack Coat3.21 KM16.293.21 KM3.21 KM1.8816.29
7.BM i/c Prime Coat, Tack Coat6.58 KM238.556.58 KM6.58 KM27.51238.55
8.SDBC i/c Tackcoat11.28 KM230.7311.28 KM11.28 KM26.61230.73
9.Cause Way3.00 No67.333.00 No3.00 No7.7767.33
10.Culverts/Scupper 3.00 No2.363.00 No3.00 No0.272.36
11.longitudinal Drain12450.00 m94.1413450.00 m13450.00 m10.8694.14
12.Crash Barrier3980.00 m115.483980.00 m3980.00 m13.32115.48
13.Parapet65.00 No2.0865.00 No65.00 No0.242.08
14.Road Furniture72.00 No53.1472.00 No72.00 No6.1353.14
15.Other Allied Works & Finishing Work 1.00 Job2.281.00 Job1.00 Job0.262.28
Total Amount: 867.04 100   867.04
Remarks: Work Completed.       Work Program Made On: 24-06-2015       Updation of work program on: 20-09-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-March-201572.11  lakhs
2.23-June-2015106.33  lakhs
3.20-October-2015290.56  lakhs
4.04-November-201549.51  lakhs
5.20-December-201583.65  lakhs
6.16-April-201668.24  lakhs
7.30-April-201616.35  lakhs
8.04-August-201645.21  lakhs
9.17-October-201626.49  lakhs
10.27-October-201613.30  lakhs
11.17-December-201610.56  lakhs
12.14-February-201737.74  lakhs
13.25-March-20179.66  lakhs
14.31-May-201713.93  lakhs
15.29-September-201723.37  lakhs
Total 867.01  lakhs
% Payment 100 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 838     No. of Test Done : 846      No. of Test Passed : 813      No. of Test Failed : 0      No. of Test Result Awaited : 5   Test report of this package
Number of Pics Available on Web Repository: 82
Number of Notice(s) issued: 71

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-07-2017Internel Road Nagar Panchayat Almora Near Ex.Eng.ADB UEAP Division Office AlmoraPlantation in Harela Festival.Ravi Shankar JoshiAEUEAP R&B Almora See Pic
2.08-02-2017Ch5.480After completion of workRavi Shankar JoshiAEUEAP R&B Almora See Pic
3.08-02-2017Km 4 ofA B A Road Internal Road of Nagar Panchayat AlmoraAfter completion of workRavi Shankar JoshiAEUEAP R&B Almora See Pic
4.28-09-2016Ch 3.850 of APR RoadCore Cutting of BM/SDBC workRavi Shankar JoshiAEUEAP R&B Almora See Pic
5.01-09-20164.800 APR RoadCore Cutting of SDBCRavi Shankar JoshiAEUEAP R&B Almora See Pic
6.01-09-2016Ch 3.950 APR RoadCore Cutting of BM/SDBC workRavi Shankar JoshiAEUEAP R&B Almora See Pic
7.30-08-2016L R Sah RoadExcavation for k C type drain in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
8.28-08-2016L R Sah RoadDrain work is in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
9.28-08-2016Ch 9+650R/Wall is in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
10.28-08-2016B A B Road Ch4+300After completion of thermoplastic paintRavi Shankar JoshiAEUEAP R&B Almora See Pic
11.29-04-2016km 5 pkg c16base concrete of 1:3:6 for kc type drainShahnawaz AliJEUEAP R&B Almora See Pic
12.29-04-2016pkg c-16 km5KC TYPE DRAIN pkg c16Shahnawaz AliJEUEAP R&B Almora See Pic
13.08-04-2016A P R Road near circle office ADB UEAP AlmoraSDBC work is in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
14.07-04-2016Ch.0.800 (Near SE UEAP office )SDBC Work is in progressGaurav BishtJEUEAP R&B Almora See Pic
15.05-04-2016Km 3Laying of SDBC in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
16.31-03-2016Cho.350 of A P R RoadK C drain work is in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
17.17-03-2016Ch0.150of Saraswati Mandir to Dhungadhara RoadInspection of s d bc workS E ADB UEAP Circle AlmoraRavi Shankar JoshiAEUEAP R&B Almora See Pic
18.09-03-2016Ch4.000Laying of SDBC in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
19.09-03-2016Ch4.300Inspection of SDBC Work by DSC 3Ravi Shankar JoshiAEUEAP R&B Almora See Pic
20.09-03-2016Ch4.400Laying of SDBCwork is in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic