Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C15 Agreement signed
Project: UEAP-RB Package No.: 1017 Package Name: UEAP/PWD/C15 Sanction Cost: 752.00  lakhs
District: Pithoragarh Block: Didihat Constituency: Didihat Circle:
DEA: DEA UEAP Pithoragarh DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5604   Reconstruction of internal road of Nagar Panchayat Didihaat (8.360 KM.) (completed)
Procurement:
Package No.: 1017        Package Name: UEAP/PWD/C15        Tender Date: 03-03-2014        Current Status: Agreement signed        Achieved on Date: 10-07-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C15        Contractor Name: Rami Construction       
Start Date: 04-08-2014        Intended Completion Date: 03-02-2016       
Total Bond Cost: 63124966.55 (631.25 lakhs)        Variation Cost: -14834438.78 (-148.34 lakhs)     Hence Total Bond Cost is   48290527.77 (482.91 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 6438648 for 204 days        LD Analysis for Milestone2: calculated LD is Rs 2745894 for 87 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.GSB/RBI/G-11.00 KM6.411.00 KM1.00 KM0.986.41
2.G-21.48 KM8.051.48 KM1.48 KM1.238.05
3.G-38.36 KM43.978.36 KM8.36 KM6.743.97
4.PC/CC i/c Prime Coat, Tack Coat8.36 KM32.768.36 KM8.36 KM4.9932.76
5.BM i/c Prime Coat, Tack Coat8.36 KM257.708.36 KM8.36 KM39.25257.70
6.SDBC i/c Tackcoat8.36 KM174.158.36 KM8.36 KM26.53174.15
7.Culverts/Scupper 20.00 No3.391.00 No1.00 No0.523.39
8.longitudinal Drain5340.00 m5.185340.00 m5340.00 m0.795.18
9.Crash Barrier3700.00 m107.303200.00 m3200.00 m16.35107.30
10.Parapet61.00 No1.4061.00 No61.00 No0.211.40
11.Road Furniture60.00 No1.6460.00 No60.00 No0.251.64
12.Other Allied Works & Finishing Work 2.00 Job14.532.00 Job2.00 Job2.2114.53
Total Amount: 656.48 100   656.48
Remarks:        Work Program Made On: 12-09-2016       Updation of work program on: 22-05-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-May-20156.99  lakhs
2.20-June-201532.74  lakhs
3.29-June-201536.07  lakhs
4.26-August-201550.54  lakhs
5.20-October-2015123.24  lakhs
6.31-October-201571.34  lakhs
7.28-November-201540.63  lakhs
8.18-March-20162.91  lakhs
9.25-April-201631.62  lakhs
10.28-February-201742.47  lakhs
11.12-October-201741.84  lakhs
Total 480.39  lakhs
% Payment 99.48 %
Advance Amount:  81.13  lakhs        Recovered Amount:  81.13  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 104     No. of Test Done : 104      No. of Test Passed : 96      No. of Test Failed : 0      No. of Test Result Awaited : 3   Test report of this package
Number of Pics Available on Web Repository: 45
Number of Notice(s) issued: 68

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.28-03-2017Munsiyari helipadCube casting for DLC work in progressAnkit NakotiAEUEAP- CA See Pic
2.28-03-2017Munisiyari helipadCross Checking of level given for Dlc work in presence of dsc fe and by JE FPIUAnkit NakotiAEUEAP- CA See Pic
3.11-01-2017Jal sasthan roadSdbc rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
4.11-01-2017Jal sansthan roadSdbc layingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
5.27-11-2016Jalsasthan roadGM layingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
6.15-11-2016Gic road ch820Sdbc rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
7.08-11-2016Gic road sdbcSdbc rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
8.07-11-2016Gic road...Sdbc rolling continueShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
9.07-11-2016Police stationSdbc rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
10.07-11-2016Police station sdbcSdbc rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
11.07-11-2016Dunakot road ch 1540Sdbc rollingUday RamAEUEAP R&B Pithoragarh See Pic
12.07-11-2016PlantBitumin content testShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
13.06-11-2016Dunakot roadSdbc rolling continueShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
14.06-11-2016Dunakot roadSdbc rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
15.05-11-2016Gic roadBe surface not leveled due to labour hand layingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
16.27-10-2016Dunakot road ch1900Measurement of Bm with AE sirShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
17.27-10-2016Dunakot Bm ch 990- 1000Bm workShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
18.27-10-2016Dunakot road ch 1010 to1020Bm work in progressShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
19.27-10-2016Dunakot road ch 1000 to 1100Bm rollingShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic
20.24-10-2016Gic road ch 820Bm work in progress... less amount of dry material laying on 1 square meter areaShankar TrivediJEUEAP R&B and CA Pithoragarh See Pic