Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C14 Agreement signed
Project: UEAP-RB Package No.: 1016 Package Name: UEAP/PWD/C14 Sanction Cost: 256.00  lakhs
District: Uttarkashi Block: Naugaon Constituency: Yamunotri Circle:
DEA: DEA UEAP Uttarkashi DSC: TPF Getinsa Euroestudios S.L. DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5002   Kuwa-Kafnaul Rahdi Motor Road (47.600 KM.) (completed)
Procurement:
Package No.: 1016        Package Name: UEAP/PWD/C14        Tender Date: 26-02-2014        Current Status: Agreement signed        Achieved on Date: 08-07-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C14        Contractor Name: Ram krishna Jayara       
Start Date: 29-07-2014        Intended Completion Date: 28-10-2015       
Total Bond Cost: 23970929.69 (239.71 lakhs)        Variation Cost: 3592856.24 (35.93 lakhs)     Hence Total Bond Cost is   27563785.93 (275.64 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 359550 for 30 days        LD Analysis for Milestone2: calculated LD is Rs 1534080 for 128 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence4.25 KM15.424.25 KM4.25 KM6.115.42
2.R/Wall, B/ Wall Type Protection works790.00 m49.38790.00 m790.00 m19.5349.38
3.G-30.00 KM0.000.00 KM0.00 KM00.00
4.PC/CC i/c Prime Coat, Tack Coat0.11 KM14.760.11 KM0.11 KM5.8414.76
5.BM i/c Prime Coat, Tack Coat1.30 KM27.131.30 KM1.30 KM10.7327.13
6.SDBC i/c Tackcoat1.30 KM21.451.30 KM1.30 KM8.4821.45
7.Cause Way1.00 No0.681.00 No1.00 No0.270.68
8.longitudinal Drain3200.00 m97.093200.00 m3200.00 m38.3997.09
9.Crash Barrier300.00 m6.61300.00 m300.00 m2.616.61
10.Road Furniture530.00 No3.69530.00 No530.00 No1.463.69
11.Other Allied Works & Finishing Work 2.00 Job16.682.00 Job2.00 Job6.616.68
Total Amount: 252.89 100   252.89
Remarks:        Work Program Made On: 25-02-2015       Updation of work program on: 17-07-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.12-January-201521.92  lakhs
2.07-February-201545.53  lakhs
3.25-March-201519.08  lakhs
4.01-October-201525.21  lakhs
5.20-October-201546.92  lakhs
6.02-November-201548.62  lakhs
7.13-July-201635.86  lakhs
8.27-June-20179.75  lakhs
Total 252.89  lakhs
% Payment 91.75 %
Advance Amount:  24.00  lakhs        Recovered Amount:  24.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 636     No. of Test Done : 636      No. of Test Passed : 636      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 54
Number of Notice(s) issued: 59

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-10-20151.75Sdbc work in progressAjeet SinghAEUEAP R&B Uttarkashi See Pic
2.19-10-201512.200CC PavementAjeet SinghAEUEAP R&B Uttarkashi See Pic
3.19-10-201526/34Crush barrier work in progressAjeet SinghAEUEAP R&B Uttarkashi See Pic
4.06-09-20156+00ScupperBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
5.10-08-20157+125Scupper work in progressBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
6.10-08-201515+850Scupper work in progressBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
7.10-08-201527/33-2738Road sinkingBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
8.06-08-20156+350Scupper work in progressBheem Singh MeharJEUEAP R&B Uttarkashi See Pic
9.30-07-201527/37Sinking area (road is sink)Bheem Singh MeharJEUEAP R&B Uttarkashi See Pic
10.17-07-20159+350Sli clearance in progress jcb deployed by civil division barkot.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
11.10-07-201539+800R/wall in completeBheem Singh MeharJEDEA ADB Uttarkashi See Pic
12.10-07-201541+500R/wall in completeBheem Singh MeharJEDEA ADB Uttarkashi See Pic
13.04-04-201531.300k.c. drainAjeet SinghAEDEA ADB Uttarkashi See Pic
14.17-03-201522+20Construction of Drainage work.Bheem Singh MeharJEDEA ADB Uttarkashi See Pic
15.17-03-201531+250Drain workBheem Singh MeharJEDEA ADB Uttarkashi See Pic
16.21-02-201533/12-13Under construction R/ wall with wire crateBheem Singh MeharJEDEA ADB Uttarkashi See Pic
17.21-02-201531/15RR dry & wire crate completedBheem Singh MeharJEDEA ADB Uttarkashi See Pic
18.21-02-201530/30R/wall completedBheem Singh MeharJEDEA ADB Uttarkashi See Pic
19.21-02-201530/7R/wall completedBheem Singh MeharJEDEA ADB Uttarkashi See Pic
20.21-02-201530/19R/wall completedBheem Singh MeharJEDEA ADB Uttarkashi See Pic