UEAP/PWD/C14
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1016 |
Package Name: |
UEAP/PWD/C14 |
Sanction Cost: |
256.00 lakhs |
District: |
Uttarkashi |
Block: |
Naugaon |
Constituency: |
Yamunotri |
Circle: |
|
DEA: |
DEA UEAP Uttarkashi |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5002 Kuwa-Kafnaul Rahdi Motor Road (47.600 KM.) (completed) |
|
Procurement: |
Package No.: 1016
Package Name: UEAP/PWD/C14
Tender Date: 26-02-2014
Current Status: Agreement signed
Achieved on Date: 08-07-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C14
Contractor Name: Ram krishna Jayara
|
Start Date: 29-07-2014
Intended Completion Date: 28-10-2015
|
Total Bond Cost: 23970929.69 (239.71 lakhs)
Variation Cost: 3592856.24 (35.93 lakhs) Hence Total Bond Cost is 27563785.93 (275.64 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 359550 for 30 days
LD Analysis for Milestone2: calculated LD is Rs 1534080 for 128 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 4.25 KM | 15.42 | 4.25 KM | 4.25 KM | 6.1 | 15.42 | 2. | R/Wall, B/ Wall Type Protection works | 790.00 m | 49.38 | 790.00 m | 790.00 m | 19.53 | 49.38 | 3. | G-3 | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 4. | PC/CC i/c Prime Coat, Tack Coat | 0.11 KM | 14.76 | 0.11 KM | 0.11 KM | 5.84 | 14.76 | 5. | BM i/c Prime Coat, Tack Coat | 1.30 KM | 27.13 | 1.30 KM | 1.30 KM | 10.73 | 27.13 | 6. | SDBC i/c Tackcoat | 1.30 KM | 21.45 | 1.30 KM | 1.30 KM | 8.48 | 21.45 | 7. | Cause Way | 1.00 No | 0.68 | 1.00 No | 1.00 No | 0.27 | 0.68 | 8. | longitudinal Drain | 3200.00 m | 97.09 | 3200.00 m | 3200.00 m | 38.39 | 97.09 | 9. | Crash Barrier | 300.00 m | 6.61 | 300.00 m | 300.00 m | 2.61 | 6.61 | 10. | Road Furniture | 530.00 No | 3.69 | 530.00 No | 530.00 No | 1.46 | 3.69 | 11. | Other Allied Works & Finishing Work | 2.00 Job | 16.68 | 2.00 Job | 2.00 Job | 6.6 | 16.68 |
Total Amount: |
252.89 |
|
100 |
252.89 |
|
Remarks:
Work Program Made On:
25-02-2015
Updation of work program on:
17-07-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 12-January-2015 | 21.92 lakhs |
2. | 07-February-2015 | 45.53 lakhs |
3. | 25-March-2015 | 19.08 lakhs |
4. | 01-October-2015 | 25.21 lakhs |
5. | 20-October-2015 | 46.92 lakhs |
6. | 02-November-2015 | 48.62 lakhs |
7. | 13-July-2016 | 35.86 lakhs |
8. | 27-June-2017 | 9.75 lakhs |
Total |
252.89 lakhs |
% Payment |
91.75 % |
|
Advance Amount: 24.00 lakhs
Recovered Amount: 24.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 54 |
Number of Notice(s) issued: 59 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 19-10-2015 | 1.75 | Sdbc work in progress | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
2. | 19-10-2015 | 12.200 | CC Pavement | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
3. | 19-10-2015 | 26/34 | Crush barrier work in progress | Ajeet Singh | AE | UEAP R&B Uttarkashi | See Pic |
4. | 06-09-2015 | 6+00 | Scupper | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
5. | 10-08-2015 | 7+125 | Scupper work in progress | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
6. | 10-08-2015 | 15+850 | Scupper work in progress | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
7. | 10-08-2015 | 27/33-2738 | Road sinking | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
8. | 06-08-2015 | 6+350 | Scupper work in progress | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
9. | 30-07-2015 | 27/37 | Sinking area (road is sink) | Bheem Singh Mehar | JE | UEAP R&B Uttarkashi | See Pic |
10. | 17-07-2015 | 9+350 | Sli clearance in progress jcb deployed by civil division barkot. | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
11. | 10-07-2015 | 39+800 | R/wall in complete | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
12. | 10-07-2015 | 41+500 | R/wall in complete | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
13. | 04-04-2015 | 31.300 | k.c. drain | Ajeet Singh | AE | DEA ADB Uttarkashi | See Pic |
14. | 17-03-2015 | 22+20 | Construction of Drainage work. | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
15. | 17-03-2015 | 31+250 | Drain work | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
16. | 21-02-2015 | 33/12-13 | Under construction R/ wall with wire crate | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
17. | 21-02-2015 | 31/15 | RR dry & wire crate completed | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
18. | 21-02-2015 | 30/30 | R/wall completed | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
19. | 21-02-2015 | 30/7 | R/wall completed | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
20. | 21-02-2015 | 30/19 | R/wall completed | Bheem Singh Mehar | JE | DEA ADB Uttarkashi | See Pic |
|
|