UEAP/PWD/C13
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1015 |
Package Name: |
UEAP/PWD/C13 |
Sanction Cost: |
540.00 lakhs |
District: |
Tehri |
Block: |
Bhilangana |
Constituency: |
Ghanshali |
Circle: |
|
DEA: |
DEA UEAP Tehri |
DSC: |
TPF Getinsa Euroestudios S.L. |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 5301 Pilkhi-Gadoliya Motor Road (8.500 KM.) (completed) | 2 5302 Reconstruction of Inspection House approach road under Nagar Panchayat Devprayag (1.000 KM.) (in prorgress) |
|
Procurement: |
Package No.: 1015
Package Name: UEAP/PWD/C13
Tender Date: 26-04-2014
Current Status: Agreement signed
Achieved on Date: 15-10-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C13
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 07-11-2014
Intended Completion Date: 20-01-2017
Original End Date: 06-04-2016
|
Total Bond Cost: 43969327 (439.69 lakhs)
Variation Cost: 6529180.00 (65.29 lakhs) Hence Total Bond Cost is 50498507 (504.99 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 131910 for 6 days
LD Analysis for Milestone2: calculated LD is Rs 2440335 for 111 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.64 KM | 11.96 | 0.64 KM | 0.64 KM | 2.69 | 11.96 | 2. | R/Wall, B/ Wall Type Protection works | 1207.34 m | 190.59 | 1207.34 m | 1207.34 m | 42.89 | 190.59 | 3. | GSB/RBI/G-1 | 0.47 KM | 3.34 | 0.54 KM | 0.47 KM | 0.64 | 2.85 | 4. | G-2 | 0.68 KM | 3.59 | 0.68 KM | 0.61 KM | 0.72 | 3.21 | 5. | G-3 | 2.15 KM | 12.56 | 2.15 KM | 2.15 KM | 2.81 | 12.56 | 6. | BM i/c Prime Coat, Tack Coat | 2.08 KM | 45.07 | 2.08 KM | 2.08 KM | 10.07 | 45.07 | 7. | SDBC i/c Tackcoat | 10.82 KM | 69.12 | 10.82 KM | 10.82 KM | 15.6 | 69.12 | 8. | Cause Way | 3.00 No | 18.33 | 3.00 No | 3.00 No | 4.1 | 18.33 | 9. | Culverts/Scupper | 15.00 No | 47.16 | 15.00 No | 12.00 No | 9.69 | 43.38 | 10. | Crash Barrier | 850.00 m | 21.45 | 850.00 m | 750.00 m | 4.19 | 18.75 | 11. | Parapet | 555.00 No | 13.84 | 586.00 No | 586.00 No | 3.12 | 13.84 | 12. | Road Furniture | 1252.00 No | 4.84 | 1252.00 No | 1252.00 No | 1.09 | 4.84 | 13. | longitudinal Drain | 836.00 m | 2.74 | 836.00 m | 836.00 m | 0.65 | 2.74 |
Total Amount: |
444.59 |
|
98.26 |
437.24 |
|
Remarks:
No Remarks
Work Program Made On:
26-02-2015
Updation of work program on:
27-07-2017
|
|
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-December-2014 | 22.89 lakhs |
2. | 10-March-2015 | 24.50 lakhs |
3. | 20-March-2015 | 17.38 lakhs |
4. | 11-June-2015 | 42.38 lakhs |
5. | 08-September-2015 | 18.60 lakhs |
6. | 20-October-2015 | 43.29 lakhs |
7. | 07-November-2015 | 21.83 lakhs |
8. | 06-February-2016 | 29.21 lakhs |
9. | 25-May-2016 | 54.21 lakhs |
10. | 06-July-2016 | 132.83 lakhs |
11. | 16-November-2016 | 35.86 lakhs |
12. | 24-June-2017 | 18.02 lakhs |
13. | 27-September-2017 | 26.10 lakhs |
Total |
487.1 lakhs |
% Payment |
96.46 % |
|
Advance Amount: 44.00 lakhs
Recovered Amount: 44.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | PUC vehicles | Environment & Social Compliances(Sub Project level): | Reconstruction of Inspection House approach road under Nagar Panchayat Devprayag(5302) | Query, DG set |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 109 |
Number of Notice(s) issued: 73 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-08-2016 | Asena village | Plantation program is held by executive engg...one plant is equal to the 100 No's of Son | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
2. | 15-08-2016 | Km 4 near asena village | Plantation program is held by executive engg. One plant is equal to the 100 No's of Son So Save tree. | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
3. | 15-08-2016 | 2+850 | Plantation program is held in Pilki Gadoliya by executive engg. ADB UEAP | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
4. | 15-08-2016 | 2+725 | Plantation program is held in pkg C -13 With executive engg sir.. | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
5. | 13-08-2016 | 12+300 | Measure thickness after core cutting | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
6. | 13-08-2016 | 7+200 | Measure thickness after core cutting | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
7. | 13-08-2016 | 6+960 | Measure thickness after core cutting | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
8. | 13-08-2016 | 6+960 | Core cutting test | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
9. | 13-08-2016 | 4+740 | Measure thickness of BM & SDBC by core cutting | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
10. | 13-08-2016 | 4+740 | Core cutting | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
11. | 13-08-2016 | 4+515 | Core cutting of BM SDBC | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
12. | 13-08-2016 | 3+400 | Measure core thickness & found satisfactory | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
13. | 13-08-2016 | 2+740 | Core cutting of BM & SDBC | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
14. | 13-08-2016 | 2+010 | Measure thickness of core by Barnier's & found satisfactory | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
15. | 13-08-2016 | 2+010 | Core cutting test of BM & SDBC | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
16. | 13-08-2016 | 0+045 | Core cutting of SDBC | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
17. | 12-08-2016 | 5+350 | Visit by Executive engineer sir ( MBCB horizontal post work is in progress) | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
18. | 10-08-2016 | 5+100 | Horizontal post of MBCB is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
19. | 30-07-2016 | 10+750 | Vartical post of MBCB is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
20. | 22-07-2016 | 0+800 | Vertical post of MBCB work is in progress | Shivendra Prakash | AE | UEAP- CA Tehri | See Pic |
|
|