Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C9 Agreement signed
Project: UEAP-RB Package No.: 1011 Package Name: UEAP/PWD/C9 Sanction Cost: 538.00  lakhs
District: Rudraprayag Block: unknown Constituency: Kedarnath Circle:
DEA: DEA UEAP Rudraprayag DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5201   Guptkashi Kalimath Kotma Jaal Chaumasi (18.000 KM.) (in prorgress)
Procurement:
Package No.: 1011        Package Name: UEAP/PWD/C9        Tender Date: 08-02-2014        Current Status: Agreement signed        Achieved on Date: 18-07-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C9        Contractor Name: Bharat Construction       
Start Date: 08-08-2014        Intended Completion Date: 07-02-2016       
Total Bond Cost: 59482400 (594.82 lakhs)        Variation Cost: -46794437.50 (-467.94 lakhs)     Hence Total Bond Cost is   12687962.5 (126.88 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 6007682 for 202 days        LD Analysis for Milestone2: calculated LD is Rs 5442603 for 183 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence1.60 KM11.141.60 KM0.40 KM0.692.79
2.R/Wall, B/ Wall Type Protection works741.00 m98.82741.00 m610.00 m20.1581.35
3.GSB/RBI/G-11.55 KM9.731.55 KM0.00 KM00.00
4.G-21.55 KM7.411.55 KM0.00 KM00.00
5.G-31.55 KM7.851.55 KM0.00 KM00.00
6.PC/CC i/c Prime Coat, Tack Coat2.65 KM41.542.65 KM0.00 KM00.00
7.Cause Way4.00 No11.004.00 No0.00 No00.00
8.Culverts/Scupper 22.00 No20.5522.00 No1.00 No0.230.93
9.longitudinal Drain14770.00 m45.3314770.00 m1675.00 m1.275.14
10.Crash Barrier3100.00 m105.403100.00 m2328.00 m19.679.15
11.Parapet750.00 No25.20750.00 No0.00 No00.00
12.Road Furniture1679.00 No19.821679.00 No0.00 No00.00
Total Amount: 403.79 41.94   169.36
Remarks: No Remarks       Work Program Made On: 26-02-2015       Updation of work program on: 22-07-2016      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.31-March-20157.92  lakhs
2.05-September-2015116.95  lakhs
3.27-December-20160.62  lakhs
Total 125.49  lakhs
% Payment 98.91 %
Advance Amount:  59.48  lakhs        Recovered Amount:  59.48  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 0     No. of Test Done : 42      No. of Test Passed : 42      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 42
Number of Notice(s) issued: 77

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-07-2015Ch 19+500Road damaged due to heavy rainAshok GuptaREDSC Rudraprayag See Pic
2.23-07-2015Ch 20+400Road damaged due to rainAshok GuptaREDSC Rudraprayag See Pic
3.23-07-2015Ch 19+230Culvert completAshok GuptaREDSC Rudraprayag See Pic
4.23-07-2015Ch 11+200R/W in progressAshok GuptaREDSC Rudraprayag See Pic
5.15-05-2015C- 9, ch10+310Slip clearanceAshok GuptaREDSC Rudraprayag See Pic
6.15-05-2015C - 9, ch 11+175R/W excavation in progressAshok GuptaREDSC Rudraprayag See Pic
7.15-05-2015C - 9, ch 11+425R/W excavation in progressAshok GuptaREDSC Rudraprayag See Pic
8.14-05-2015C9 guptkasi kalimat kotma jalchomasi road ch11.425Excavation for foundation of R wall in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
9.14-05-2015C9 guptkasi kalimat kotma jalchomasi road ch12.550R wall for causeway in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
10.14-05-2015C9 gupta kalimat kotma jalchomasi road ch17.050Embankment work in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
11.14-05-2015C9 guptkasi kalimat kotma jalchomasi road ch19.225Culvert in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
12.14-05-2015C9 guptkasi kalimat kotma JAL chomasi road ch15.425R Wall completeAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
13.14-05-2015C9 guptkasi kalimat kotma JAL chomasi road ch11.175R Wall in progressAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
14.14-05-2015C9 guptkasi kalimat kotma JAL chomasi road ch10.250JCB workingAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
15.14-05-2015C9 guptkasi kalimat kotma JAL chomasi road ch10.270R wall completeAnil Kumar MittalEEUEAP R&B Rudraprayag See Pic
16.26-04-2015C 9 , ch 15+400R/W inprogressAshok GuptaREDSC Rudraprayag See Pic
17.29-03-2015C 9, ch 18+400R/W inprogressAshok GuptaREDSC Rudraprayag See Pic
18.29-03-2015C 9, ch 18+400Site visit SE SrinagarAshok GuptaREDSC Rudraprayag See Pic
19.29-03-2015C 9, ch 18+400R/W inprogressAshok GuptaREDSC Rudraprayag See Pic
20.27-03-2015Ch 10.050R wall in progress c9Anil Kumar MittalEEUEAP R&B Rudraprayag See Pic