UEAP/PWD/C8
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1010 |
Package Name: |
UEAP/PWD/C8 |
Sanction Cost: |
1094.00 lakhs |
District: |
Chamoli |
Block: |
Dasholi |
Constituency: |
Badrinath |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 5103 Chamoli - Kund (41.000 KM.) (in prorgress) |
|
Procurement: |
Package No.: 1010
Package Name: UEAP/PWD/C8
Tender Date: 08-02-2014
Current Status: Agreement signed
Achieved on Date: 18-07-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C8
Contractor Name: Bharat Construction
|
Start Date: 08-08-2014
Intended Completion Date: 07-05-2016
Original End Date: 07-02-2016
|
Total Bond Cost: 76899400 (768.99 lakhs)
Variation Cost: -20378.89 (-0.2 lakhs) Hence Total Bond Cost is 76879021.11 (768.79 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 6997900 for +182 days
LD Analysis for Milestone2: calculated LD is Rs 9766300 for 254 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | R/Wall, B/ Wall Type Protection works | 270.00 m | 11.62 | 356.00 m | 270.00 m | 1.1 | 8.82 | 2. | GSB/RBI/G-1 | 0.00 KM | 0.00 | 0.46 KM | 0.20 KM | 0 | 0.00 | 3. | G-2 | 0.00 KM | 0.00 | 0.77 KM | 0.50 KM | 0 | 0.00 | 4. | G-3 | 0.08 KM | 0.11 | 1.05 KM | 0.75 KM | 0.01 | 0.08 | 5. | BM i/c Prime Coat, Tack Coat | 9.20 KM | 280.15 | 9.20 KM | 9.20 KM | 35.01 | 280.15 | 6. | SDBC i/c Tackcoat | 16.20 KM | 262.34 | 16.20 KM | 16.20 KM | 32.79 | 262.34 | 7. | Cause Way | 2.00 No | 1.60 | 3.00 No | 2.00 No | 0.13 | 1.07 | 8. | Culverts/Scupper | 2.00 No | 3.89 | 4.00 No | 2.00 No | 0.24 | 1.94 | 9. | longitudinal Drain | 5281.00 m | 52.65 | 5281.00 m | 5281.00 m | 6.58 | 52.65 | 10. | Crash Barrier | 2380.00 m | 80.51 | 2380.00 m | 2380.00 m | 10.06 | 80.51 | 11. | Parapet | 150.00 No | 4.25 | 252.00 No | 150.00 No | 0.32 | 2.53 | 12. | Road Furniture | 877.00 No | 10.58 | 877.00 No | 0.00 No | 0 | 0.00 | 13. | Other Allied Works & Finishing Work | 2.00 Job | 92.41 | 2.00 Job | 0.00 Job | 0 | 0.00 |
Total Amount: |
800.11 |
|
86.25 |
690.09 |
|
Remarks:
No Remarks
Work Program Made On:
27-02-2015
Updation of work program on:
26-02-2017
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 31-December-2014 | 6.11 lakhs |
2. | 29-May-2015 | 41.83 lakhs |
3. | 24-August-2015 | 62.61 lakhs |
4. | 08-November-2015 | 33.18 lakhs |
5. | 25-January-2016 | 48.22 lakhs |
6. | 30-March-2016 | 55.14 lakhs |
7. | 06-May-2016 | 270.09 lakhs |
8. | 02-July-2016 | 174.64 lakhs |
9. | 25-October-2016 | 46.73 lakhs |
10. | 10-May-2017 | 30.23 lakhs |
Total |
768.78 lakhs |
% Payment |
100 % |
|
Advance Amount: 76.90 lakhs
Recovered Amount: 76.90 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | PUC vehicles | Environment & Social Compliances(Sub Project level): | Chamoli - Kund(5103) | No Pending Issue |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 282 |
Number of Notice(s) issued: 78 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 13-06-2016 | 1+727 | Metal beam Crash barrier work in progress | Ravi Shankar Shukla | QC | UEAP R&B Chamoli | See Pic |
2. | 17-05-2016 | Ch. 36.190, Chamoli Kund motor road. | Parapits under construction. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
3. | 23-04-2016 | C8/40+350 | BM work in progress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
4. | 23-04-2016 | C8/40+410 | BM work in progress. | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
5. | 23-04-2016 | C8/36+170 | Sdbc work in progress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
6. | 20-04-2016 | Chopta road / 37+400 | BM laying in progress for Chamoli kund road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
7. | 20-04-2016 | Chopta road / 37+450 | BM laying & rolling work progress for Chamoli kund road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
8. | 20-04-2016 | Bharat HMP / Chamoli | BM mix material production for Chamoli kund road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
9. | 19-04-2016 | Bharat HMP /Chamoli | BM mix material production for Chamoli kund road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
10. | 19-04-2016 | Bharat HMP / Chamoli | SDBC mix material production for Chamoli kund road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
11. | 18-04-2016 | Bharat HMP / Chamoli | BM mix material production for Chamoli kund road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
12. | 18-04-2016 | Bharat HMP /Chamoli | SDBC mix material production for Chamoli kund road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
13. | 14-04-2016 | Chopta road / 38+570 | BM laying & rolling work progress for Chamoli kund road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
14. | 14-04-2016 | Chopta road / 38+850 | BM laying & rolling work progress for Chamoli kund road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
15. | 14-04-2016 | Bharat HMP / Chamoli | BM mix material production for Chamoli kund road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
16. | 13-04-2016 | C8 CH kind/39+050 | Sdbc Rolling work in progress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
17. | 13-04-2016 | C8 CH kund/39+160 | Sdbc work&Rolling work in prpgress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
18. | 13-04-2016 | Bharat HMP / Chamoli | SDBC mix material for Chamoli kund road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
19. | 12-04-2016 | Chopta road /39+050 | AE sir checked BM thickness during laying Chamoli kund road. | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
20. | 12-04-2016 | Chopta road /39+150 | BM laying & rolling work in progress at Chamoli kund road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
|
|