Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C8 Agreement signed
Project: UEAP-RB Package No.: 1010 Package Name: UEAP/PWD/C8 Sanction Cost: 1094.00  lakhs
District: Chamoli Block: Dasholi Constituency: Badrinath Circle:
DEA: DEA UEAP Chamoli DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5103   Chamoli - Kund (41.000 KM.) (in prorgress)
Procurement:
Package No.: 1010        Package Name: UEAP/PWD/C8        Tender Date: 08-02-2014        Current Status: Agreement signed        Achieved on Date: 18-07-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C8        Contractor Name: Bharat Construction       
Start Date: 08-08-2014        Intended Completion Date: 07-05-2016        Original End Date:  07-02-2016
Total Bond Cost: 76899400 (768.99 lakhs)        Variation Cost: -20378.89 (-0.2 lakhs)     Hence Total Bond Cost is   76879021.11 (768.79 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 6997900 for +182 days        LD Analysis for Milestone2: calculated LD is Rs 9766300 for 254 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.R/Wall, B/ Wall Type Protection works270.00 m11.62356.00 m270.00 m1.18.82
2.GSB/RBI/G-10.00 KM0.000.46 KM0.20 KM00.00
3.G-20.00 KM0.000.77 KM0.50 KM00.00
4.G-30.08 KM0.111.05 KM0.75 KM0.010.08
5.BM i/c Prime Coat, Tack Coat9.20 KM280.159.20 KM9.20 KM35.01280.15
6.SDBC i/c Tackcoat16.20 KM262.3416.20 KM16.20 KM32.79262.34
7.Cause Way2.00 No1.603.00 No2.00 No0.131.07
8.Culverts/Scupper 2.00 No3.894.00 No2.00 No0.241.94
9.longitudinal Drain5281.00 m52.655281.00 m5281.00 m6.5852.65
10.Crash Barrier2380.00 m80.512380.00 m2380.00 m10.0680.51
11.Parapet150.00 No4.25252.00 No150.00 No0.322.53
12.Road Furniture877.00 No10.58877.00 No0.00 No00.00
13.Other Allied Works & Finishing Work 2.00 Job92.412.00 Job0.00 Job00.00
Total Amount: 800.11 86.25   690.09
Remarks: No Remarks       Work Program Made On: 27-02-2015       Updation of work program on: 26-02-2017      
Work Program Status:Program Expired.
Financial Progress
SNo. Date Payment
1.31-December-20146.11  lakhs
2.29-May-201541.83  lakhs
3.24-August-201562.61  lakhs
4.08-November-201533.18  lakhs
5.25-January-201648.22  lakhs
6.30-March-201655.14  lakhs
7.06-May-2016270.09  lakhs
8.02-July-2016174.64  lakhs
9.25-October-201646.73  lakhs
10.10-May-201730.23  lakhs
Total 768.78  lakhs
% Payment 100 %
Advance Amount:  76.90  lakhs        Recovered Amount:  76.90  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): PUC vehicles
Environment & Social Compliances(Sub Project level):
Chamoli - Kund(5103)No Pending Issue
Detailed report of this Package
Quality
No. of Test Required : 155     No. of Test Done : 211      No. of Test Passed : 211      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 282
Number of Notice(s) issued: 78

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.13-06-20161+727Metal beam Crash barrier work in progressRavi Shankar ShuklaQCUEAP R&B Chamoli See Pic
2.17-05-2016Ch. 36.190, Chamoli Kund motor road.Parapits under construction.Atul ShandilyaAEUEAP R&B Chamoli See Pic
3.23-04-2016C8/40+350BM work in progressGovind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
4.23-04-2016C8/40+410BM work in progress.Govind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
5.23-04-2016C8/36+170Sdbc work in progressGovind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
6.20-04-2016Chopta road / 37+400BM laying in progress for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
7.20-04-2016Chopta road / 37+450BM laying & rolling work progress for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
8.20-04-2016Bharat HMP / ChamoliBM mix material production for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
9.19-04-2016Bharat HMP /ChamoliBM mix material production for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
10.19-04-2016Bharat HMP / ChamoliSDBC mix material production for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
11.18-04-2016Bharat HMP / ChamoliBM mix material production for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
12.18-04-2016Bharat HMP /ChamoliSDBC mix material production for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
13.14-04-2016Chopta road / 38+570BM laying & rolling work progress for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
14.14-04-2016Chopta road / 38+850BM laying & rolling work progress for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
15.14-04-2016Bharat HMP / ChamoliBM mix material production for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
16.13-04-2016C8 CH kind/39+050Sdbc Rolling work in progressGovind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
17.13-04-2016C8 CH kund/39+160Sdbc work&Rolling work in prpgressGovind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
18.13-04-2016Bharat HMP / ChamoliSDBC mix material for Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
19.12-04-2016Chopta road /39+050AE sir checked BM thickness during laying Chamoli kund road.Sanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
20.12-04-2016Chopta road /39+150BM laying & rolling work in progress at Chamoli kund roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic