Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C7 Agreement signed
Project: UEAP-RB Package No.: 1009 Package Name: UEAP/PWD/C7 Sanction Cost: 442.00  lakhs
District: Chamoli Block: Ghat Constituency: Karanprayag Circle:
DEA: DEA UEAP Chamoli DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision No.of Sub project : 2
Subproject in this package
1  5101   Nandprayag- Ghat (14.000 KM.) (in prorgress)
2  5102   Rudraprayag-pokhari-Karanprayag (14.510 KM.) (in prorgress)
Procurement:
Package No.: 1009        Package Name: UEAP/PWD/C7        Tender Date: 08-02-2014        Current Status: Agreement signed        Achieved on Date: 18-07-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C7        Contractor Name: Bharat Construction       
Start Date: 08-08-2014        Intended Completion Date: 05-04-2016        Original End Date:  07-11-2015
Total Bond Cost: 34799370 (347.99 lakhs)        Variation Cost: 8478614.26 (84.79 lakhs)     Hence Total Bond Cost is   43277984.26 (432.78 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 2644800 for +152 days        LD Analysis for Milestone2: calculated LD is Rs 2470800 for 142 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.25 KM7.400.47 KM0.35 KM0.995.51
2.R/Wall, B/ Wall Type Protection works717.00 m48.681491.00 m737.00 m5.1224.21
3.GSB/RBI/G-10.30 KM0.830.20 KM0.20 KM0.150.83
4.G-20.43 KM0.990.59 KM0.43 KM0.130.72
5.G-31.01 KM2.381.35 KM1.01 KM0.381.95
6.BM i/c Prime Coat, Tack Coat5.18 KM145.631.98 KM1.93 KM28.96144.50
7.SDBC i/c Tackcoat11.89 KM143.219.37 KM9.37 KM36.03143.21
8.Cause Way7.00 No22.5710.00 No7.00 No2.8315.80
9.Culverts/Scupper 0.00 No0.000.00 No0.00 No00.00
10.longitudinal Drain10398.00 m24.3420250.00 m7850.00 m1.427.19
11.Crash Barrier1004.00 m34.141000.00 m1000.00 m10.4534.14
12.Parapet95.00 No2.28190.00 No90.00 No0.191.02
13.Road Furniture159.00 No2.44304.00 No74.00 No0.080.44
Total Amount: 434.89 86.71   379.52
Remarks: No Remarks       Work Program Made On: 26-02-2015       Updation of work program on: 25-02-2017      
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired.
Financial Progress
SNo. Date Payment
1.30-January-201512.81  lakhs
2.16-May-20158.92  lakhs
3.25-June-201537.15  lakhs
4.19-October-201562.23  lakhs
5.09-November-2015127.16  lakhs
6.19-June-2016181.71  lakhs
Total 429.98  lakhs
% Payment 99.35 %
Advance Amount:  34.80  lakhs        Recovered Amount:  34.80  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Pending Environmental & Social issues
Environment & Social Compliances(Package level): labour licence, workmen Insurance
Environment & Social Compliances(Sub Project level):
Nandprayag- Ghat (5101)No Pending Issue
Rudraprayag-pokhari-Karanprayag(5102)No Pending Issue
Detailed report of this Package
Quality
No. of Test Required : 2     No. of Test Done : 41      No. of Test Passed : 41      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 303
Number of Notice(s) issued: 78

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-08-2016C7(Sera)ghat/13+960to14++080PRoad washout125mtr lengthGovind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
2.14-05-2016Bharat HMP / ChamoliBM mix material production for Nandprayag -ghat roadSanjay Kumar BarnwalLab TechnicianDSC2 ADB R&B See Pic
3.07-03-2016C7 Thirpak/6+700Public consultation by DrBhattachary Social ExpertDsc2Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
4.07-03-2016C7(Ghat)/18+420CC Road in progressGovind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
5.29-02-2016Ch. 18.275, Nandprayag Ghat motor road.CC road under construction.Atul ShandilyaAEUEAP R&B Chamoli See Pic
6.16-02-2016C7 Ghat /18+410CC Road M15 Work in progress.Govind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
7.16-02-2016N.p.that(Ganes nagar)/ch15+980Parapet work in progressGovind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
8.06-02-2016C7(saintuli)N.P.that/17+110Parapet work in progressGovind Ram ThapliyalSite EngineerDSC2 R&B ADB Chamoli See Pic
9.06-02-2016Km. 9, Nandprayag Ghat motor road.Constructed parapit.Atul ShandilyaAEUEAP R&B Chamoli See Pic
10.27-01-2016C7 kameda (N.p.g)9+620Parapet work ln progressGovind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
11.15-01-2016C-7 N.P.G. Gwala/3+250Parapet work in progressGovind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
12.15-01-2016C7 Tephna N.P.Chat/2+760Line drain ln progressGovind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
13.19-12-201510+050KC Drain in progressRachna BahugunaJEUEAP R&B Chamoli See Pic
14.07-11-2015Km 5.200, Nandprayag Ghat motor roadRolling of SDBC.Atul ShandilyaAEUEAP R&B Chamoli See Pic
15.03-11-2015Km 5.175, Nandprayag Ghat motor road.Laying of SDBC.Atul ShandilyaAEUEAP R&B Chamoli See Pic
16.02-11-2015Rudr.pokhri.karnapryag /C7 ch45+450Odbc laying&rolling in progress.Govind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
17.02-11-2015C7 R.p.k.(Bhardwar)/ch45+100Laying Sdbc work in progress.Govind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
18.02-11-2015Bhardwaj R.P.K./45+435B.M. patch work in progress.Govind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic
19.02-11-201545+020 bhaurawan dharSdbc work in progress .Anurag RawatJEUEAP R&B Chamoli See Pic
20.01-11-2015C7 R.P.K.(Bhairv dhar)/ch44+720Sdbc work in progress.Govind Ram ThapliyalSite SupervisorDSC2 R&B ADB Chamoli See Pic