UEAP/PWD/C7
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1009 |
Package Name: |
UEAP/PWD/C7 |
Sanction Cost: |
442.00 lakhs |
District: |
Chamoli |
Block: |
Ghat |
Constituency: |
Karanprayag |
Circle: |
|
DEA: |
DEA UEAP Chamoli |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 5101 Nandprayag- Ghat (14.000 KM.) (in prorgress) | 2 5102 Rudraprayag-pokhari-Karanprayag (14.510 KM.) (in prorgress) |
|
Procurement: |
Package No.: 1009
Package Name: UEAP/PWD/C7
Tender Date: 08-02-2014
Current Status: Agreement signed
Achieved on Date: 18-07-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C7
Contractor Name: Bharat Construction
|
Start Date: 08-08-2014
Intended Completion Date: 05-04-2016
Original End Date: 07-11-2015
|
Total Bond Cost: 34799370 (347.99 lakhs)
Variation Cost: 8478614.26 (84.79 lakhs) Hence Total Bond Cost is 43277984.26 (432.78 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 2644800 for +152 days
LD Analysis for Milestone2: calculated LD is Rs 2470800 for 142 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.25 KM | 7.40 | 0.47 KM | 0.35 KM | 0.99 | 5.51 | 2. | R/Wall, B/ Wall Type Protection works | 717.00 m | 48.68 | 1491.00 m | 737.00 m | 5.12 | 24.21 | 3. | GSB/RBI/G-1 | 0.30 KM | 0.83 | 0.20 KM | 0.20 KM | 0.15 | 0.83 | 4. | G-2 | 0.43 KM | 0.99 | 0.59 KM | 0.43 KM | 0.13 | 0.72 | 5. | G-3 | 1.01 KM | 2.38 | 1.35 KM | 1.01 KM | 0.38 | 1.95 | 6. | BM i/c Prime Coat, Tack Coat | 5.18 KM | 145.63 | 1.98 KM | 1.93 KM | 28.96 | 144.50 | 7. | SDBC i/c Tackcoat | 11.89 KM | 143.21 | 9.37 KM | 9.37 KM | 36.03 | 143.21 | 8. | Cause Way | 7.00 No | 22.57 | 10.00 No | 7.00 No | 2.83 | 15.80 | 9. | Culverts/Scupper | 0.00 No | 0.00 | 0.00 No | 0.00 No | 0 | 0.00 | 10. | longitudinal Drain | 10398.00 m | 24.34 | 20250.00 m | 7850.00 m | 1.42 | 7.19 | 11. | Crash Barrier | 1004.00 m | 34.14 | 1000.00 m | 1000.00 m | 10.45 | 34.14 | 12. | Parapet | 95.00 No | 2.28 | 190.00 No | 90.00 No | 0.19 | 1.02 | 13. | Road Furniture | 159.00 No | 2.44 | 304.00 No | 74.00 No | 0.08 | 0.44 |
Total Amount: |
434.89 |
|
86.71 |
379.52 |
|
Remarks:
No Remarks
Work Program Made On:
26-02-2015
Updation of work program on:
25-02-2017
|
|
Work Program Status:This Package contain more than one subproject,pleae check individua subproject for Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-January-2015 | 12.81 lakhs |
2. | 16-May-2015 | 8.92 lakhs |
3. | 25-June-2015 | 37.15 lakhs |
4. | 19-October-2015 | 62.23 lakhs |
5. | 09-November-2015 | 127.16 lakhs |
6. | 19-June-2016 | 181.71 lakhs |
Total |
429.98 lakhs |
% Payment |
99.35 % |
|
Advance Amount: 34.80 lakhs
Recovered Amount: 34.80 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level): | labour licence, workmen Insurance | Environment & Social Compliances(Sub Project level): | Nandprayag- Ghat (5101) | No Pending Issue | Rudraprayag-pokhari-Karanprayag(5102) | No Pending Issue |
Detailed report of this Package
|
|
Quality
|
|
Number of Pics Available on Web Repository: 303 |
Number of Notice(s) issued: 78 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-08-2016 | C7(Sera)ghat/13+960to14++080 | PRoad washout125mtr length | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
2. | 14-05-2016 | Bharat HMP / Chamoli | BM mix material production for Nandprayag -ghat road | Sanjay Kumar Barnwal | Lab Technician | DSC2 ADB R&B | See Pic |
3. | 07-03-2016 | C7 Thirpak/6+700 | Public consultation by DrBhattachary Social ExpertDsc2 | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
4. | 07-03-2016 | C7(Ghat)/18+420 | CC Road in progress | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
5. | 29-02-2016 | Ch. 18.275, Nandprayag Ghat motor road. | CC road under construction. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
6. | 16-02-2016 | C7 Ghat /18+410 | CC Road M15 Work in progress. | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
7. | 16-02-2016 | N.p.that(Ganes nagar)/ch15+980 | Parapet work in progress | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
8. | 06-02-2016 | C7(saintuli)N.P.that/17+110 | Parapet work in progress | Govind Ram Thapliyal | Site Engineer | DSC2 R&B ADB Chamoli | See Pic |
9. | 06-02-2016 | Km. 9, Nandprayag Ghat motor road. | Constructed parapit. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
10. | 27-01-2016 | C7 kameda (N.p.g)9+620 | Parapet work ln progress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
11. | 15-01-2016 | C-7 N.P.G. Gwala/3+250 | Parapet work in progress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
12. | 15-01-2016 | C7 Tephna N.P.Chat/2+760 | Line drain ln progress | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
13. | 19-12-2015 | 10+050 | KC Drain in progress | Rachna Bahuguna | JE | UEAP R&B Chamoli | See Pic |
14. | 07-11-2015 | Km 5.200, Nandprayag Ghat motor road | Rolling of SDBC. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
15. | 03-11-2015 | Km 5.175, Nandprayag Ghat motor road. | Laying of SDBC. | Atul Shandilya | AE | UEAP R&B Chamoli | See Pic |
16. | 02-11-2015 | Rudr.pokhri.karnapryag /C7 ch45+450 | Odbc laying&rolling in progress. | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
17. | 02-11-2015 | C7 R.p.k.(Bhardwar)/ch45+100 | Laying Sdbc work in progress. | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
18. | 02-11-2015 | Bhardwaj R.P.K./45+435 | B.M. patch work in progress. | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
19. | 02-11-2015 | 45+020 bhaurawan dhar | Sdbc work in progress . | Anurag Rawat | JE | UEAP R&B Chamoli | See Pic |
20. | 01-11-2015 | C7 R.P.K.(Bhairv dhar)/ch44+720 | Sdbc work in progress. | Govind Ram Thapliyal | Site Supervisor | DSC2 R&B ADB Chamoli | See Pic |
|
|