Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C6 Agreement signed
Project: UEAP-RB Package No.: 1008 Package Name: UEAP/PWD/C6 Sanction Cost: 436.00  lakhs
District: Almora Block: Hawal Bagh Constituency: Almora Circle:
DEA: DEA UEAP Almora DSC: CCEE Group India Pvt.Ltd DSC Scope: Design & Supervision No.of Sub project : 1
Subproject in this package
1  5801   NTD Kafarkhan- Dhaulchinna (8.000 KM.) (completed)
Procurement:
Package No.: 1008        Package Name: UEAP/PWD/C6        Tender Date: 13-01-2014        Current Status: Agreement signed        Achieved on Date: 21-04-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C6        Contractor Name: R.G. Buildwell.       
Start Date: 17-06-2014        Intended Completion Date: 15-06-2017        Original End Date:  16-09-2015
Total Bond Cost: 41547651.25 (415.48 lakhs)        Variation Cost: 11452505.13 (114.53 lakhs)     Hence Total Bond Cost is   53000156.38 (530 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 4404088 for 212 days        LD Analysis for Milestone2: calculated LD is Rs 1724242 for 83 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence8.00 KM2.778.00 KM8.00 KM0.522.77
2.R/Wall, B/ Wall Type Protection works460.00 m13.52460.00 m460.00 m2.5513.52
3.GSB/RBI/G-10.20 KM0.030.20 KM0.20 KM0.010.03
4.G-21.60 KM2.201.60 KM1.60 KM0.422.20
5.G-36.00 KM3.216.00 KM6.00 KM0.613.21
6.PC/CC i/c Prime Coat, Tack Coat0.67 KM4.330.67 KM0.67 KM0.824.33
7.BM i/c Prime Coat, Tack Coat10.37 KM162.1710.37 KM10.37 KM30.6162.17
8.SDBC i/c Tackcoat10.37 KM120.0310.37 KM10.37 KM22.65120.03
9.Cause Way7.00 No5.367.00 No7.00 No1.015.36
10.Culverts/Scupper 8.00 No9.368.00 No8.00 No1.779.36
11.longitudinal Drain9100.00 m31.409100.00 m9100.00 m5.9331.40
12.Crash Barrier2820.00 m86.262820.00 m2820.00 m16.2886.26
13.Parapet150.00 No4.93150.00 No150.00 No0.934.93
14.Road Furniture46.00 No80.4346.00 No46.00 No15.1880.43
15.Other Allied Works & Finishing Work 1.00 Job4.011.00 Job1.00 Job0.764.01
Total Amount: 530.01 100   530.01
Remarks: Work Completed.       Work Program Made On: 24-06-2015       Updation of work program on: 20-09-2017      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.10-February-20157.65  lakhs
2.31-March-201527.36  lakhs
3.23-June-201552.14  lakhs
4.26-June-2015105.95  lakhs
5.30-September-2015105.45  lakhs
6.06-November-201559.22  lakhs
7.30-April-201627.92  lakhs
8.01-June-201668.74  lakhs
9.14-July-201650.52  lakhs
10.17-October-20168.65  lakhs
11.20-June-201716.39  lakhs
Total 529.99  lakhs
% Payment 100 %
Advance Amount:  41.55  lakhs        Recovered Amount:  41.55  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 403     No. of Test Done : 409      No. of Test Passed : 395      No. of Test Failed : 0      No. of Test Result Awaited : 1   Test report of this package
Number of Pics Available on Web Repository: 46
Number of Notice(s) issued: 71

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-02-2017Ch0.350After completion of workRavi Shankar JoshiAEUEAP R&B Almora See Pic
2.08-02-2017Ch0.050After completion of workRavi Shankar JoshiAEUEAP R&B Almora See Pic
3.01-09-2016Ch0.080Core Cutting of B M /SDBCRavi Shankar JoshiAEUEAP R&B Almora See Pic
4.28-08-2016CH.7.600Crash Barrier work is in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
5.28-08-2016Ch 2+900After completion of crash barrier, thermoplas paint workRavi Shankar JoshiAEUEAP R&B Almora See Pic
6.28-08-2016Ch0+225After completion ofThermplastic paint&Road markerRavi Shankar JoshiAEUEAP R&B Almora See Pic
7.04-06-2016Ch9+650Laying &Rolling of SDBC&is in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
8.13-09-2015Km 6Laying of SDBC work is in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
9.12-09-2015KM 7SDBC work is in prpgressRavi Shankar JoshiAEUEAP R&B Almora See Pic
10.10-09-2015Ch7.400SDBC Work is in progressRavi Shankar JoshiAEUEAP R&B Almora See Pic
11.10-09-2015Plant SiteMaking and loading sdbc in tippers at plantRavi Shankar JoshiAEUEAP R&B Almora See Pic
12.10-09-2015Plant site for NTD Kafarkhan M Road at kwarab Mona M RoadSDBC Material loading in TippersRavi Shankar JoshiAEUEAP R&B Almora See Pic
13.03-09-2015Ch 7.750B M work is in progressA S BishtEEDEA ADB Almora See Pic
14.28-08-2015Ch3.210Drain work is in progressRavi Shankar JoshiAEUEAB R&B Almora See Pic
15.06-08-2015LGCh4.080 near KasardeviExcavation for Hume pipe culvertRavi Shankar JoshiAEUEAB R&B Almora See Pic
16.07-07-2015Ch.7.060BM work is in progressGaurav BishtJEUEAP R&B Almora See Pic
17.07-07-2015Ch.5.775BM Work is in ProgressGaurav BishtJEUEAP R&B Almora See Pic
18.25-06-2015Ch 5.900Cleaning of existing Surface for BM workGaurav BishtJEUEAP R&B Almora See Pic
19.23-06-20155.600BM Work is in Progress Inspection by Cheif Engineer UEAPGaurav BishtJEUEAP R&B Almora See Pic
20.09-05-2015Ch2.900BM &CrushBarier workGulab RamSEADB Circle See Pic