UEAP/PWD/C4
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1006 |
Package Name: |
UEAP/PWD/C4 |
Sanction Cost: |
520.00 lakhs |
District: |
Udham Singh Nagar |
Block: |
Jaspur |
Constituency: |
Jaspur |
Circle: |
|
DEA: |
DEA UEAP Nainital |
DSC: |
CCEE Group India Pvt.Ltd |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
1 |
Subproject in this package |
1 6001 Jaspur- Dhampur (6.000 KM.) (completed) |
|
Procurement: |
Package No.: 1006
Package Name: UEAP/PWD/C4
Tender Date: 13-01-2014
Current Status: Agreement signed
Achieved on Date: 21-04-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C4
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 14-06-2014
Intended Completion Date: 13-01-2016
Original End Date: 13-09-2015
|
Total Bond Cost: 44868136 (448.68 lakhs)
Variation Cost: 6601612.80 (66.02 lakhs) Hence Total Bond Cost is 51469748.8 (514.7 lakhs)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | GSB/RBI/G-1 | 0.77 KM | 21.04 | 0.77 KM | 0.77 KM | 5.31 | 21.04 | 2. | G-2 | 0.77 KM | 12.82 | 0.77 KM | 0.77 KM | 3.24 | 12.82 | 3. | G-3 | 0.77 KM | 12.47 | 0.77 KM | 0.77 KM | 3.15 | 12.47 | 4. | BM i/c Prime Coat, Tack Coat | 3.99 KM | 133.60 | 3.10 KM | 3.10 KM | 33.74 | 133.60 | 5. | SDBC i/c Tackcoat | 4.42 KM | 71.72 | 6.00 KM | 6.00 KM | 18.11 | 71.72 | 6. | Culverts/Scupper | 3.00 No | 3.95 | 3.00 No | 3.00 No | 1 | 3.95 | 7. | longitudinal Drain | 1950.00 m | 123.76 | 1950.00 m | 1950.00 m | 31.26 | 123.76 | 8. | Road Furniture | 22.00 No | 16.61 | 20.00 No | 20.00 No | 4.19 | 16.61 |
Total Amount: |
395.97 |
|
100 |
395.97 |
|
Remarks:
No Remarks
Work Program Made On:
17-04-2015
Updation of work program on:
25-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 07-May-2015 | 285.00 lakhs |
2. | 27-June-2015 | 38.45 lakhs |
3. | 03-October-2015 | 30.44 lakhs |
4. | 29-February-2016 | 49.69 lakhs |
5. | 15-June-2017 | 37.32 lakhs |
Total |
440.9 lakhs |
% Payment |
85.66 % |
|
Advance Amount: 44.00 lakhs
Recovered Amount: 44.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
Analysis:Bill should be issued |
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 22 |
Number of Notice(s) issued: 73 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 02-08-2015 | Chsinage 5+100 | Road Side drain near police chauki Nadahi | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
2. | 02-08-2015 | Chainage 4+800 | cb | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
3. | 02-08-2015 | Chainage 4+880 | Road Side Drain near Nadhai Sugar Mill | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
4. | 08-06-2015 | Km4 | Packed company bag of glass beads | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
5. | 08-06-2015 | KM 4 | Glass Beads Using in Thermoplastic Road Marking | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
6. | 08-06-2015 | K.M.6 | Edge Line Marking | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
7. | 08-06-2015 | KM 4 | Edge line marking | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
8. | 20-05-2015 | Chainage Km 4.600 | Left side RCC drain work in progress | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
9. | 20-05-2015 | Chainage Km 4 .350 | Right side RCC drain work in progress | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
10. | 20-05-2015 | Chainage 4.700 | RCC road side drain in progress | Gulab Ram | SE | ADB Circle | See Pic |
11. | 14-05-2015 | chainage 5.300 | road side RCC drain construction work in progress | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
12. | 14-05-2015 | chainage 4.750 | ROAD SIDE RCC DRAIN WORK IN PROGRESS | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
13. | 29-04-2015 | Chainage 1+750 | Road surface after B M & S D B C work | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
14. | 29-04-2015 | Chainage 4+750 | Excavation & laying of base concrete for road side drain near Rajan's Shop | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
15. | 29-04-2015 | Chainage 4+650 | Road side drain work in progress | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
16. | 23-04-2015 | Km 4 | Final surface | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
17. | 23-04-2015 | Km 6 | Taking final level of road | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
18. | 24-03-2015 | K.M.4 | B. M.Work | Lalit Tiwari | unknown | unknown | See Pic |
19. | 24-03-2015 | K.M. 4.5 | B.M.work at jaspur | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
20. | 12-03-2015 | Km 2.780 | R C C road side drain construction | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
|
|