UEAP/PWD/C3
Agreement signed
|
Project: |
UEAP-RB |
Package No.: |
1005 |
Package Name: |
UEAP/PWD/C3 |
Sanction Cost: |
260.00 lakhs |
District: |
Nainital |
Block: |
Betalghat |
Constituency: |
Nainital |
Circle: |
|
DEA: |
DEA UEAP Nainital |
DSC: |
TPF Getinsa Eurostudios S.L. in Association with V |
DSC Scope: |
Design & Supervision |
No.of Sub project : |
2 |
Subproject in this package |
1 5903 Betalghat-Bhatrojkhan (12.000 KM.) (completed) | 2 5904 Nathuwakhan-Suyalbari (26.000 KM.) (completed) |
|
Procurement: |
Package No.: 1005
Package Name: UEAP/PWD/C3
Tender Date: 01-05-2014
Current Status: Agreement signed
Achieved on Date: 15-12-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UEAP/PWD/C3
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 04-01-2015
Intended Completion Date: 03-04-2016
|
Total Bond Cost: 21874812.6 (218.75 lakhs)
Variation Cost: 4182396.10 (41.82 lakhs) Hence Total Bond Cost is 26057208.7 (260.57 lakhs)
|
LD Analysis for Milestone1: calculated LD is Rs 120307 for 11 days
LD Analysis for Milestone2: calculated LD is Rs 218740 for 20 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakhs) |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakhs) |
1. | Hill side Cutting & Slip clearence | 0.57 KM | 2.32 | 0.57 KM | 0.57 KM | 1.02 | 2.32 | 2. | R/Wall, B/ Wall Type Protection works | 235.00 m | 34.74 | 235.00 m | 235.00 m | 15.66 | 34.74 | 3. | G-3 | 1.00 KM | 2.61 | 1.00 KM | 1.00 KM | 1.16 | 2.61 | 4. | PC/CC i/c Prime Coat, Tack Coat | 14.40 KM | 153.28 | 14.40 KM | 14.40 KM | 67.57 | 153.28 | 5. | Culverts/Scupper | 168.00 No | 6.72 | 168.00 No | 168.00 No | 2.95 | 6.72 | 6. | longitudinal Drain | 29000.00 m | 24.00 | 29000.00 m | 29000.00 m | 10.46 | 24.00 | 7. | G-2 | 0.00 KM | 0.00 | 0.00 KM | 0.00 KM | 0 | 0.00 | 8. | Cause Way | 2.00 No | 2.63 | 2.00 No | 2.00 No | 1.18 | 2.63 |
Total Amount: |
226.3 |
|
100 |
226.3 |
|
Remarks:
No Remarks
Work Program Made On:
16-04-2015
Updation of work program on:
03-09-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-October-2015 | 79.39 lakhs |
2. | 30-November-2015 | 37.49 lakhs |
3. | 29-February-2016 | 9.65 lakhs |
4. | 02-September-2016 | 101.24 lakhs |
5. | 25-September-2017 | 7.18 lakhs |
Total |
234.95 lakhs |
% Payment |
90.17 % |
|
Advance Amount: 0.00 lakhs
Recovered Amount: 0.00 lakhs
Balance to be Recovered 0.00 lakhs
* Advances are at package level not sub project level
|
|
Pending Environmental & Social issues
|
|
Quality
|
|
Number of Pics Available on Web Repository: 15 |
Number of Notice(s) issued: 73 |
Mobile Pic Upload |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-02-2016 | 2+020 | Construction of kutcha drain | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
2. | 19-02-2016 | 8+200 | Construction of kutcha Drain and p.c work | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
3. | 19-02-2016 | 8+150 | Construction of RW | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
4. | 19-02-2016 | 13+780 | Construction of kutcha drain | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
5. | 06-11-2015 | Chainage 10+000 | Premix carpet work started | Gulab Ram | SE | ADB Circle | See Pic |
6. | 06-11-2015 | Chainage 1+460 | Damaged R/Wall contruction | Gulab Ram | SE | ADB Circle | See Pic |
7. | 30-09-2015 | 3+000 | Construction of B/W and side kuccha drain | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
8. | 19-08-2015 | Chainage 24+600 | R/Wall damaged this mansoon SRMD 2015-16 | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
9. | 19-08-2015 | Chainage 1+450 | R/Wall construction which damaged this year's mansoon SRMD 2015-16 | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
10. | 20-07-2015 | 3+200 | Slip and B/W required | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
11. | 20-07-2015 | 1+400 | Damaged R/W | Lalit Tiwari | AE | DEA ADB Nainital | See Pic |
12. | 06-07-2015 | 6.170 - 7.000 | P.C. Start | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
13. | 27-06-2015 | 15.300 | slip clrarence | Rajendra Prasad Sati | JE | UEAP R&B Nainital | See Pic |
14. | 27-06-2015 | 6.170-7.000 | P.C. Started | R P sati | JE | JE Nainital | See Pic |
15. | 29-04-2015 | Chainage 1+750 | Road surface after B M & S D B C Work | Rajiv Gururani | EE | DEA ADB Nainital | See Pic |
|
|