Menu

Package Profile Report

                            Project:               District:               Package: 

Package Profile Report

UEAP/PWD/C3 Agreement signed
Project: UEAP-RB Package No.: 1005 Package Name: UEAP/PWD/C3 Sanction Cost: 260.00  lakhs
District: Nainital Block: Betalghat Constituency: Nainital Circle:
DEA: DEA UEAP Nainital DSC: TPF Getinsa Eurostudios S.L. in Association with V DSC Scope: Design & Supervision No.of Sub project : 2
Subproject in this package
1  5903   Betalghat-Bhatrojkhan (12.000 KM.) (completed)
2  5904   Nathuwakhan-Suyalbari (26.000 KM.) (completed)
Procurement:
Package No.: 1005        Package Name: UEAP/PWD/C3        Tender Date: 01-05-2014        Current Status: Agreement signed        Achieved on Date: 15-12-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UEAP/PWD/C3        Contractor Name: Woodhill Infrastructure Ltd       
Start Date: 04-01-2015        Intended Completion Date: 03-04-2016       
Total Bond Cost: 21874812.6 (218.75 lakhs)        Variation Cost: 4182396.10 (41.82 lakhs)     Hence Total Bond Cost is   26057208.7 (260.57 lakhs) 
LD Analysis for Milestone1: calculated LD is Rs 120307 for 11 days        LD Analysis for Milestone2: calculated LD is Rs 218740 for 20 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakhs)
Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakhs)
1.Hill side Cutting & Slip clearence0.57 KM2.320.57 KM0.57 KM1.022.32
2.R/Wall, B/ Wall Type Protection works235.00 m34.74235.00 m235.00 m15.6634.74
3.G-31.00 KM2.611.00 KM1.00 KM1.162.61
4.PC/CC i/c Prime Coat, Tack Coat14.40 KM153.2814.40 KM14.40 KM67.57153.28
5.Culverts/Scupper 168.00 No6.72168.00 No168.00 No2.956.72
6.longitudinal Drain29000.00 m24.0029000.00 m29000.00 m10.4624.00
7.G-20.00 KM0.000.00 KM0.00 KM00.00
8.Cause Way2.00 No2.632.00 No2.00 No1.182.63
Total Amount: 226.3 100   226.3
Remarks: No Remarks       Work Program Made On: 16-04-2015       Updation of work program on: 03-09-2016      
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-October-201579.39  lakhs
2.30-November-201537.49  lakhs
3.29-February-20169.65  lakhs
4.02-September-2016101.24  lakhs
5.25-September-20177.18  lakhs
Total 234.95  lakhs
% Payment 90.17 %
Advance Amount:  0.00  lakhs        Recovered Amount:  0.00  lakhs        Balance to be Recovered  0.00  lakhs        * Advances are at package level not sub project level
Pending Environmental & Social issues
Detailed report of this Package
Quality
No. of Test Required : 32     No. of Test Done : 32      No. of Test Passed : 31      No. of Test Failed : 0   Test report of this package
Number of Pics Available on Web Repository: 15
Number of Notice(s) issued: 73

Mobile Pic Upload

( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.23-02-20162+020Construction of kutcha drainLalit TiwariAEDEA ADB Nainital See Pic
2.19-02-20168+200Construction of kutcha Drain and p.c workLalit TiwariAEDEA ADB Nainital See Pic
3.19-02-20168+150Construction of RWLalit TiwariAEDEA ADB Nainital See Pic
4.19-02-201613+780Construction of kutcha drainLalit TiwariAEDEA ADB Nainital See Pic
5.06-11-2015Chainage 10+000Premix carpet work startedGulab RamSEADB Circle See Pic
6.06-11-2015Chainage 1+460Damaged R/Wall contructionGulab RamSEADB Circle See Pic
7.30-09-20153+000Construction of B/W and side kuccha drainLalit TiwariAEDEA ADB Nainital See Pic
8.19-08-2015Chainage 24+600R/Wall damaged this mansoon SRMD 2015-16Rajiv GururaniEEDEA ADB Nainital See Pic
9.19-08-2015Chainage 1+450R/Wall construction which damaged this year's mansoon SRMD 2015-16Rajiv GururaniEEDEA ADB Nainital See Pic
10.20-07-20153+200Slip and B/W requiredLalit TiwariAEDEA ADB Nainital See Pic
11.20-07-20151+400Damaged R/WLalit TiwariAEDEA ADB Nainital See Pic
12.06-07-20156.170 - 7.000P.C. StartRajendra Prasad SatiJEUEAP R&B Nainital See Pic
13.27-06-201515.300slip clrarenceRajendra Prasad SatiJEUEAP R&B Nainital See Pic
14.27-06-20156.170-7.000P.C. StartedR P satiJEJE Nainital See Pic
15.29-04-2015Chainage 1+750Road surface after B M & S D B C WorkRajiv GururaniEEDEA ADB Nainital See Pic